Manhattan Beach Advanced Traffic Signal System Project
Budget and Expenditures
Total Project Funding
Measure M Funding FY20/21 $3,640,000
Measure M Funding FY21/22 $1,800,000
TOTAL $5,440,000
Total Expenditures
Engineering Design Services Agreement: DKS Associates $1,283,417 TOTAL DESIGN EXPENDITURES $1,283,417
Available Funds for Construction Phase (TBD) $4,156,583
TOTAL $5,440,000