Manhattan Beach Advanced Traffic Signal System Project
Budget and Expenditures
Total Project Funding
Measure M Funding FY20/21 3,640,000
Measure M Funding FY21/22 1,800,000
Original Measure M Funding Approved by LACMTA 9/26/2019 $5,440,000
Measure M Funding FY22/23 5,310,000
Measure M Funding FY23/24 2,000,000
Additional Measure M Funding Approved by LACMTA 9/23/2021 $7,310,000
TOTAL $12,750,000
Total Expenditures
Engineering Design Services Agreement: DKS Associates 1,283,417 Design Contract Contingency 0
TOTAL DESIGN EXPENDITURES $1,283,417
Construction Phase (TBD) 11,466,583
TOTAL ESTIMATED CONSTRUCTION PHASE I
EXPENDITURES
$11,466,583
TOTAL $12,750,000