EXHIBIT C
Construction and Permitting Costs - Scout Community Center Project

Del Amo - Construction Cost Total $ 4,337,098
Right of Way permits $627
Fire Permit $1,500
Demo Permit $1,500
Water Meter / Sewer Connection Fees $4,250
Public Art Fee $ 16,000
Plan Check / Permit Fee $ 25,000
CEQA (range) $153,000
Contingency (15%) $ 650,565

Total $5,189,540