ID Task
Mode
Task Name Duration Start Finish Resource Names
1 Architectural Only 265 days Mon 8/2/21 Fri 8/5/22
2 City Provided Comments on Draft Arch Plans 0 days Mon 8/2/21 Mon 8/2/21 Comm Dev 3 Final Draft Arch Plans 240 days Mon 8/2/21 Fri 7/1/22 Friends 4 Submit Architectural Plans to City 1 day Mon 7/4/22 Mon 7/4/22 Friends 5 City Reviews Final Arch Plans 24 days Tue 7/5/22 Fri 8/5/22 Comm Dev 6 MOU at City Council 1 day Tue 5/17/22 Tue 5/17/22 P&R 7 Design (All Disciplines) 197 days Wed 6/1/22 Thu 3/2/23 8 Arch + Eng Team Agreement 1 day Wed 6/1/22 Wed 6/1/22 Friends 9 35% Design 60 days Thu 6/2/22 Wed 8/24/22 Friends
10 City Review 35% Design 22 days Thu 8/25/22 Fri 9/23/22 P&R+PW 11 65% Design 35 days Mon 9/26/22 Fri 11/11/22 Friends
12 City Review 65% Design 23 days Mon 11/14/22 Wed 12/14/22 P&R+PW 13 95% Design 35 days Thu 12/15/22 Wed 2/1/23 Friends
14 City Review 95% Design 21 days Thu 2/2/23 Thu 3/2/23 P&R+PW 15 3rd Party Cost/Constructability Review 21 days Thu 2/2/23 Thu 3/2/23 P&R+PW 16 Environmental 386 days Tue 5/17/22 Tue 11/7/23
17 Agreement Approved at City Council 1 day Tue 5/17/22 Tue 5/17/22 Comm Dev 18 Environmental Documentation 270 days Tue 7/5/22 Mon 7/17/23 Comm Dev 19 Staff Report Enviro & Gen Use Permit 20 days Tue 7/18/23 Mon 8/14/23 Comm Dev 20 Planning Commission 1 day Wed 8/23/23 Wed 8/23/23 Comm Dev 21 Appeal Period 15 days Thu 8/24/23 Thu 9/7/23
22 Staff Report/Notice (Appeal Comments) 30 days Fri 9/8/23 Thu 10/19/23 Comm Dev 23 City Council (Appeal Comments) 1 day Tue 11/7/23 Tue 11/7/23 Comm Dev 24 Permitting 157 days Thu 2/2/23 Fri 9/8/23
25 Demolition Permit 35 days Thu 2/2/23 Wed 3/22/23 Friends+CommDev 26 Issue Demo Permit 1 day Fri 9/8/23 Fri 9/8/23
27 Building Permit 130 days Thu 2/2/23 Wed 8/2/23 Friends+CommDev 28 Issue Building Permit 1 day Fri 9/8/23 Fri 9/8/23
29 Bidding and Award 125 days Wed 11/8/23 Tue 4/30/24
30 Bidding ‐ Package/Advertise/Opening 90 days Wed 11/8/23 Tue 3/12/24 PW 31 City Council for Construction Contract Award 1 day Tue 3/19/24 Tue 3/19/24 PW 32 Agreement/NTP 30 days Wed 3/20/24 Tue 4/30/24 PW
33 Construction 300 days Wed 5/1/24 Tue 6/24/25 PW
8/2
Friends
Friends
Comm Dev
P&R
Friends
Friends
P&R+PW
Friends
P&R+PW
Friends
P&R+PW
P&R+PW
Comm Dev
Comm Dev
Comm Dev
Comm Dev
Comm Dev
Comm Dev
Friends+CommDev
Friends+CommDev
PW
3/19
PW
PW
Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul Oct Jan Apr Jul arter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Qua Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Senior and Scout Community Center Replacement Project
DRAFT PRELIMINARY
Date: Wed 5/4/22