Cycle 2 Storm Drain Infrastructure Improvements Project Budget and Expenditures Summary
BUDGET
Cycle 2 Storm Drain Infrastructure Improvements Project (SW15842) $625,675.00 Additional Request for Emergency Work 7,428.20
Inspection Services for Emergency Work 4,896.00
TOTAL BUDGET $637,999.20

EXPENDITURES
Construction Contract Work for Cycle 2 Storm Drain Infrastructure Improvements Project – Ramona, Inc.
$544,075.00
Change Order #1 – 35th St Catch Basin Improvement – Ramona, Inc. 25,666.08 Change Order #2 – Misc. Extra Work Items – Ramona, Inc. 21,967.15 CYCLE 2 SUBTOTAL $591,708.23

Change Order #3 – Emergency Work – Ramona, Inc. $41,394.97 Inspection Services for Emergency Work – Wallace and Associates 4,896.00 EMERGENCY WORK SUBTOTAL $46,290.97

TOTAL EXPENDITURES $637,999.20