Sepulveda Bridge Widening Project
Construction Phase Budget and Expenditure Summary Report August 2022
REMAINING PROJECT FUNDING
Funding Source Grant Amount
1. MTA Call for Projects (13840E) $1,026,658
2. Proposition C Local Returns (10827E) $530,088
3. MTA Measure R Grant Funds (13841E) $4,589,703
TOTAL $6,146,449
EXPENDITURES
HDR Design Services Agreement Amendment No. 7 (Awarded
July 7, 2020)
$424,546.00
S2 Construction Management Services Agreement (Awarded July 7, 2020)
$1,689,703.46
S2 Construction Management Services Agreement Amendment No. 1 (December 7, 2021)
$590,000.00
S2 Construction Management Services Agreement
Amendment No. 2
$379,940.00
C.A. Rasmussen Construction Contract (Awarded July 7, 2020) $8,791,039.70 Additional Work – Construction Contingency of 10% (Awarded July 7, 2020)
$879,105.00
TOTAL $12,754,334.16