Manhattan Beach Boulevard and Peck Avenue Traffic Signal Improvement Project
Budget and Expenditures
Total Project Funding
Measure R Local Return Program $795,000
Additional Measure R Local Return $250,000
TOTAL $1,045,000
Total Expenditures
Design Agreement: Iteris, Inc. (Original Contract) $149,802 20% Design Contract Contingency $29,960
Total Design Expenditures $179,762
Construction Contract: Calpromax Engineering, Inc. $611,936 20% Construction Contract Contingency & Market Volatility Adjustment
$122,387
Total Construction Contract Expenditures $734,323
Inspection Agreement: Quantum Quality Consulting, Inc. $120,250
Material Testing (TBD) $10,665
TOTAL $1,045,000