12100-0001\2654178v1.doc
City of MB Form
B-1
BID
CITY OF MANHATTAN BEACH
P
IER RAILING REPLACEMENT PROJECT
T
O THE HONORABLE MAYOR AND CITY COUNCIL OF THE CITY OF MANHATTAN BEACH:
The undersigned, as Bidder, declares that: (1) this Bid is made without collusion with any other person and that the only persons or parties interested as principals are those named herein; (2) the undersigned has carefully examined the Contract Documents (including all Addenda) and the Project site; and (3) the undersigned has investigated and is satisfied as to the conditions to be encountered, the character, quality and quantities of Work to be performed, and the materials to be furnished. Furthermore, the undersigned agrees that submission of this Bid shall be conclusive evidence that such examination and investigation have been made and agrees, in the event the Contract be awarded to it, to execute the Contract with the City of Manhattan Beach to perform the Project in accordance with the Contract Documents in the time and manner therein prescribed, and to furnish or provide all materials, labor, tools, equipment, apparatus and other means necessary so to do, except as may otherwise be furnished or provided under the terms of the Contract Documents, for the following stated unit prices or lump-sum price as submitted on the Bid herein.
This Bid is made with the full knowledge of the kind, quantity, and quality of the materials and W
ork required and, if it is accepted by the City, the Bidder shall enter into a Contract and furnish the bonds, insurance, and other documents as required by the Contract Documents within ten calendar days after award of the Contract. The Bidder agrees that failure to execute and return the Contract or the required faithful performance bond, labor and materials payment bond, warranty bond, and insurance certificates to the City within the ten calendar day period shall be sufficient cause for the rescission of the award and forfeiture of the Bid Security to the City to the extent permitted by law.
Accompanying this Bid is cash, a cashier’s check, a certified check or a Bid Bond in an amount e
qual to at least ten percent of the total aggregate Bid price based on the quantities shown and the unit prices quoted. The undersigned further agrees that, should it be awarded the Contract and thereafter fail or refuse to execute the Contract and provide the required evidence of insurance and Bonds within ten calendar days after delivery of the Contract to the undersigned, then the cash, check or Bid Bond shall be forfeited to the City to the extent permitted by law. 12100-0001\2654178v1.doc
City of MB Form
B-2
C
ITY OF MANHATTAN BEACH
BI
D SCHEDULE FOR
PIER RAILING REPLACEMENT PROJECT
Bidder’s Name:
Bidder’s Address:
To the Honorable Mayor and Members of the City Council:
In compliance with the Notice Inviting Bids, the undersigned hereby agrees to execute the Contract to furnish all labor, materials, equipment and supplies for the Project in accordance with the Contract Documents to the satisfaction and under the direction of the City Engineer, at the following prices:
Base Bid Schedule A (Pier, Stairs, and Parking Lots)
Items as Follows:
1. General Requirements: The lump sum price paid shall include full compensation for bonds, insurance, required permits and fees, shop drawings, project phasing, staging, supervision, coordination of concurrent work with other contractors, meetings, “as-built” plans or record drawings, clean up of the work area including removal of USA markings at project completion, movement of personnel, equipment, supplies, and incidentals to and from the project site, surveying, resetting survey monuments, and potholing; for the establishment of all other facilities necessary for work on the project; for all other work and operations which must be performed or costs incurred prior to beginning work on the various contract items of work on the project site; for work and improvements called for or implied by the Contract Documents, which are not included in the other bid items but are required to complete the Work; for furnishing all labor, materials, tools, equipment and incidentals for implementation, and for maintaining engines and mufflers of other equipment.
2. Remove and Dispose of Existing Handrail: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for removing and disposing of the existing handrail along the existing Pier, stairs, and parking lots as noted on the drawings.
3. Remove and Dispose of Existing Concrete Curb: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for removing and disposing of the existing concrete curb along the Pier or other areas as noted on the drawings.
4. Remove and Dispose of Existing North Timber Staircase: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for removing and disposing of the existing timber staircase on the north side of the Pier including concrete footings, excavation, backfill, and compaction to facilitate construction of the new timber staircase as noted on the drawings.
5. Remove and Dispose of Existing South Timber Staircase: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for removing and disposing of the existing timber staircase on the north side of the Pier including concrete footings, excavation, backfill, and compaction to facilitate construction of the new timber staircase as noted on the drawings.
Applied Restoration Inc.
1965 Gillespie Way, suite 104, El Cajon, CA. 92020
12100-0001\2654178v1.doc
City of MB Form
B-3
6. Construct Type 1 Guardrail and Connection: Work under this item shall include, but not be l
imited to, all labor, tools, equipment, and material costs to furnish, prep, install, and finish Type 1 railing system along the Pier, complete in place as indicated on the contract documents.
7. Construct Type 2 Guardrail and Connection: Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, install, and finish Type 2 railing system adjacent to the Pier and along the parking lots, complete in place as indicated on the contract documents.
8. Construct Type 3 Guardrail and Connection: Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, install, and finish Type 3 railing system along the timber stairs, complete in place as indicated on the contract documents.
9. Construct Type 4 Guardrail and Connection: Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, install, and finish Type 4 railing system along the concrete stairs, complete in place as indicated on the contract documents.
10. Construct Entrance Gate: Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, install, and finish entrance gate system at the Pier, complete in place as indicated on the contract documents.
11. Construct Epoxy/Grout Cracks in Curb (Allowance): Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, form, pour, cure, and finish concrete epoxy grout crack repairs as directed by the City.
12. Furnish and Install CIP Concrete Curb Repair: Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, form, pour, cure, and finish concrete curb repairs including all steel reinforcement as indicated on the contract documents.
13. Construct North Timber Staircase: Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to construct the timber staircase system at the north side of the Pier, including all timber, miscellaneous hardware, fasteners, concrete footings, excavation and backfill necessary to construct the timber staircase complete the work in place.
14. Construct South Timber Staircase: Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to construct the timber staircase system at the south side of the Pier, including all timber, miscellaneous hardware, fasteners, concrete footings, excavation and backfill necessary to construct the timber staircase complete the work in place.
15. New Signage (Allowance): Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish and install new signage as directed by the City.
16. ADA Signage and Striping (Allowance): Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish and install new ADA signage and striping as directed by the City.
12100-0001\2654178v1.doc
City of MB Form
B-4
17. Special Event Remobilization: The lump sum price paid shall include full compensation for c
oordination of concurrent work with other contractors, special events, meetings, clean up of the work area, movement of personnel, equipment, supplies, and incidentals to and from the project site; for all other work and operations which must be performed or costs incurred prior to beginning work on the various contract items of work on the project site; for cease of work activities during any duration shown in the Special Provisions, and for furnishing all labor, materials, tools, equipment, and incidentals for implementation and staging area remobilization up to five (5) special events, as directed by the Engineer.
18. Type 1 Railing Additional Stock: Furnish, package and deliver to City two (2) extra removable sections of Type 1 Guardrail, Connection Hardware, Spare Parts and Tools for future repairs.
Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, and finish Type 1 railing system extra stock, complete per the contract documents.
19. Type 2 Railing Additional Stock: Furnish, package and deliver to City two (2) extra removable sections of Type 2 Guardrail, Connection Hardware, Spare Parts and Tools for future repairs.
Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, and finish Type 2 railing system extra stock, complete per the contract documents.
Additive Bid Schedule B (Bike Path) as Follows:
20. General Requirements: The lump sum price paid shall include full compensation for bonds, insurance, required permits and fees, shop drawings, project phasing, staging, supervision, coordination of concurrent work with other contractors, meetings, “as-built” plans or record drawings, clean up of the work area including removal of USA markings at project completion, movement of personnel, equipment, supplies, and incidentals to and from the project site, surveying, resetting survey monuments, and potholing; for the establishment of all other facilities necessary for work on the project; for all other work and operations which must be performed or costs incurred prior to beginning work on the various contract items of work on the project site; for work an improvements called for or implied by the Contract Documents, which are not included in the other bid items but are required to complete the Work; for furnishing all labor, materials, tools, equipment and incidentals for implementation, and for maintaining engines and mufflers of other equipment.
21. Remove and Dispose of Existing Handrail: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for removing and disposing the existing handrail along the bike path as noted on the drawings.
22. Construct Type 2 Guardrail and Connection: Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, install, and finish Type 2 railing system along the bike path, complete in place, as indicated on the contract documents.
Additive Bid Schedule C (Comfort Station) as Follows:
23. General Requirements: The lump sum price paid shall include full compensation for bonds, insurance, required permits and fees, shop drawings, project phasing, staging, supervision, coordination of concurrent work with other contractors, meetings, “as-built” plans or record drawings, clean up of the work area including removal of USA markings at project completion, movement of personnel, equipment, supplies, and incidentals to and from the project site, surveying, resetting survey monuments, and potholing; for the establishment of 12100-0001\2654178v1.doc
City of MB Form
B-5
all other facilities necessary for work on the project; for all other work and operations which m
ust be performed or costs incurred prior to beginning work on the various contract items of work on the project site; for work an improvements called for or implied by the Contract Documents, which are not included in the other bid items but are required to complete the Work; for furnishing all labor, materials, tools, equipment and incidentals for implementation, and for maintaining engines and mufflers of other equipment.
24. Remove and Dispose of Existing Handrail: Work under this item shall include, but not be limited to, all labor, tools, equipment and material costs for removing and disposing the existing handrail at the comfort station, as noted on the drawings.
25. Construct Type 2 Guardrail and Connection: Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, install, and finish Type 2 railing system at the comfort station, complete in place, as indicated on the contract documents.
26. Construct Type 4 Guardrail and Connection: Work under this item shall include, but not be limited to, all labor, tools, equipment, and material costs to furnish, prep, install, and finish Type 4 railing system at the comfort station, complete in place, as indicated on the contract documents.
BASE BID SCHEDULE A (Pier, Stairs, and Parking Lots):
ITEM
N
O.
CODE DESCRIPTION UNIT ESTIMATED
QUANTITY
UNIT
PRICES
EXTENDED
AMOUNT
1 %
General
R
equirements:
Mobilization /
Demobilization /
Disposal Fees, and
other contract
requirements not
covered under other
bid items (5%
Maximum of total bid
price)
LS 1
N
/A
$
2 Remove and Dispose
o
f Existing Handrail LF 2 ,500 $ $
3 Remove and Dispose
o
f Existing Concrete
Curb
LF 5 0 $ $
4 %
Remove and Dispose
o
f Existing North
Timber Staircase
LS 1 N/A $
5 %
Remove and Dispose
o
f Existing South
Timber Staircase
LS 1 N/A $
6 Construct Type 1
G
uardrail and
Connection
LF 1 ,960 $ $
7 Construct Type 2
G
uardrail and
Connection
LF 3 10 $ $
12100-0001\2654178v1.doc
City of MB Form
B-6
ITEM
N
O.
CODE DESCRIPTION UNIT ESTIMATED
QUANTITY
UNIT
PRICES
EXTENDED
AMOUNT
8 Construct Type 3
G
uardrail and
Connection
LF 1 30 $ $
9 Construct Type 4
G
uardrail and
Connection
LF 6 0 $ $
10 % Construct Entrance
G
ates LS 1 N/A $
11 %
Construct Epoxy/Grout
C
racks in Curb
(Allowance)
LS 1 N/A $10,000
12 Furnish and Install CIP
Concrete Curb Repair LF 3
0 $ $
13 % Construct North
T
imber Staircase LS 1 N/A $
14 % Construct South
T
imber Staircase LS 1 N/A $
15 S, % New Signage
(Allowance) LS 1
N/A $5,000
16 S, % ADA Signage and
Striping (Allowance) LS 1 N/A $5,000
17 Special Event
Remobilization EA 5
$ $
18 Furnish and Deliver to
City Type 1 Guardrail
and Connection
Hardware, etc.
Additiona Stock
EA 2
$ $
19 Furnish and Deliver to
City Type 2 Guardrail
and Connection
Hardware, etc.
Additiona Stock
EA 2
$ $
T OTAL BASE BID
SCHEDULE A: $___________
12100-0001\2654178v1.doc
City of MB Form
B-7
ADDITIVE BID SCHEDULE B (Bike Path):
ITEM NO. C ODE DESCRIPTION UNIT ESTIMATED
QUANTITY
UNIT
PRICES
EXTENDED
AMOUNT
20 %
General Requirements:
Mobilization /
Demobilization / Disposal
Fees, and other contract
requirements not
covered under other bid
items
LS 1 N/A $
21 Remove and Dispose of
E
xisting Handrail
LF 4 90 $ $
22 Construct Type 2
G
uardrail and
Connection
LF 490 $ $
T OTAL ADDITIVE BID
SCHEDULE B: $___________
ADDITIVE BID SCHEDULE C (Comfort Station):
ITEM NO. CODE DESCRIPTION UNIT ESTIMATED
QUANTITY
UNIT
PRICES
EXTENDED
AMOUNT
23 %
General Requirements:
Mobilization /
Demobilization / Disposal
Fees, and other contract
requirements not
covered under other bid
items
LS 1 N/A $
24 Remove and Dispose of
E
xisting Handrail LF 290 $ $
25 Construct Type 2
G
uardrail and
Connection
LF 170 $ $
26 Construct Type 4
G
uardrail and
Connection
LF 120 $ $
T OTAL ADDITIVE BID
SCHEDULE C: $___________
N
OTES:
1) In the CODE column (S) denotes a specialty item, (%) denotes progress payments for that lump sum item will be allowed based on the percentage of completion in each pay period, and (C) denotes payments will be made after the completion of the lump sum item. See Subsection 9-
2.1 of the General Provisions for details.
2) In the UNIT column (LS) denotes a lump sum item. See Section 9 of the General Provisions for details
.
12100-0001\2654178v1.doc
City of MB Form
B-8
3) Estimated quantities are for the purpose of Bid comparison only; payments will be made on the basis of actual measurement of Work completed, except for lump sum (LS) items. For lump sum items, see Note 1. The Bid Price shall include, but not limited to, sales tax and all other applicable taxes and fees.
4) Items may be adjusted or deleted. Therefore, regardless of total actual volume (percentage) compared to estimated quantities, the unit prices provided above by the Bidder shall be applied to the final quantity when payment is calculated for these items. No adjustment in the unit prices will be allowed. The City reserves the right to not use any of the estimated quantities; and if this right is exercised, the Contractor will not be entitled to any additional compensation. Cost of all export of material shall be included in the above unit costs; no additional compensation will be granted for such expenses.
Total Bid Price = Base Bid Schedule Amount Plus (+) All Additive Bid Schedule Amounts S
IGNATURE PAGE TO FOLLOW:
12100-0001\2654178v1.doc
City of MB Form
B-9
TOT
AL BID PRICE IN DIGITS: $
TOTAL BID PRICE IN WORDS:
The undersigned certifies to have a minimum of three consecutive years of current experience in the type of Work related to the Project and that this experience is in actual operation of the firm with permanent employees performing a part of the Work as distinct from a firm operating entirely by subcontracting all phases of the Work. The undersigned also certifies to be properly licensed by the State as a contractor to perform this type of Work. The undersigned possesses California Contractor’s License
Number , Class , which expires on .
Signature: Title: Date:
Signature: Title: Date:
1081367 A,B 09/30/2023
Oscar Bianchi CEO 10/28/2022
2,340,590.00
Two Million Three Hundred FourtyThousand Five Hundred Ninty Dollars 12100-0001\2654178v1.doc
City of MB Form
B-10
B
IDDER’S PROPOSAL – CONTRACTOR’S STATEMENT
PIER RAILING REPLACEMENT PROJECT
Fill out all of the following information. Attach add itional sheets if necessary. (1) Bidder’s Name:
(2) If the Bidder’s name is a fictitious name, who or what is the full name of the registered owner? If the Bidder’s name is not a fictitious name, write “N/A” in the response to this question. If you are doing business under a fictitious name, provide a copy of the filed valid Fictitious Business Name Statement.
(3) Business Address:
(4) Telephone: Email:
(5) Type of Firm – Individual, Partnership, LLC or Corporation:
(6) Corporation organized under the laws of the State of:
(7) California State Contractor’s License Number and Class:
Original Date Issued: Expiration Date:
(8) DIR Contractor Registration Number:
(9) List the name and title of the person(s) who inspected the Project site for your firm:
(10) Number of years’ experience the company has as a contractor in construction work:
(11) List the names, titles, addresses and telephone numbers of all individuals, firm members, partners, joint ventures, and company or corporate officers having a principal interest in this Bid:
(12) List all current and prior D.B.A.’s, aliases, an d fictitious business names for any principal having interest in this Bid:
Applied Restoration Inc.
1965 Gillespie Way Suite 104, El Cajon, CA. 92020
310-951-6396 [email protected]
S Corporation
California
1081367 / A, B, C-33, C-39
2007 06/2023
1000000100
Oscar Bianchi / CEO
30 Oscar Bianchi / CEO / 1965 Gillespie Way, 104. El Cajon CA 92020 1965 Gillespie Way, 104. El Cajon CA 92020Larry White / President Oscar 310-951-6396 Larry 360-975-2605
ARI.
12100-0001\2654178v1.doc
City of MB Form
B-11
(
13) List the dates of any voluntary or involuntary b ankruptcy judgments against any principal having an interest in this Bid:
(14) For all arbitrations, lawsuits, settlements and the like (in or out of court) that the company or any principal having an interest in this Bid has been involved with in the past five years:
a. List the names, addresses and telephone numbers of contact persons for the parties:
b. Briefly summarize the parties’ claims and defenses :
c. State the tribunal (e.g., Superior Court, American Arbitration Association, etc.), the matter number, and the outcome:
(15) Has the company or any principal having an inter est in this Bid ever had a contract terminated by the owner or agency? If yes, explain.
None
None
N/A
N/A
N/A
12100-0001\2654178v1.doc
City of MB Form
B-12
(
16) Has the company or any principal having an inte r est in this Bid ever failed to complete a project? If yes, explain.
(17) Has the company or any principal having an inte r est in this Bid ever been terminated for cause, even if it was converted to a “termination of convenience”? If yes, explain. (18) For projects that the company or any principal h aving an interest in this Bid has been involved with in the last five years, did you have any claims or actions:
a. By you against the owner? Circle one: Yes No
b. By the owner against you? Circle one: Yes No
c. By any outside agency or individual for labor comp
liance?
Circle one: Yes No
d. By Subcontractors? Circle one: Yes No
e. Are any of these claims or actions unresolved or o
utstanding?
Circle one: Yes No
If your answer is “yes” to any part or parts of this question, explain. (19) Has the company or any of its principals ever be en debarred by any agencies? Is yes, please explain.
NO
NO
N/A
N/A
12100-0001\2654178v1.doc
City of MB Form
B-13
(20) For all public agency projects in excess of $15,000.00 that you are currently working on or have worked on in the past two years, provide the following information:
Project 1 Name/Number City of Newport Beach American Leigon Project Description Concrete Repair , Handrails
Approximate Construction Dates From: 08/ 23/22 To: Present Agency Name: City of Newport Beach
Contact Person: Chris Miller Telephone: 714-815-6104 Address:
Original Contract Amount: $990,900.00 Final Contract Amount: $ 990,00 If final amount is different from original amount, please explain (change orders, extra work, etc.).
Did you or any Subcontractor, file any claims against the Agency? Circle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No If you answered yes to either of the above two questions, please explain and indicate outcome of claims.
Project 2 Name/Number City of Neewport Beach City Bridge Maintance City Newport Beach
Project Description Concrete Repair
Approximate Construction Date From: 02/03/22 To: 04/03/22 Agency Name: City of Newport Beach
Contact Person: Tom Sandefur Telephone: 310 383-4790 Address:
Original Contract Amount: $800,000 Final Contract Amount: $ 800,000 If final amount is different from original amount, please explain (change orders, extra work, etc.).
12100-0001\2654178v1.doc
City of MB Form
B-14
Did you or any Subcontractor, file any claims against the Agency? C
ircle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No If you answered yes to either of the above two questions, please explain and indicate outcome of c
laims.
Project 3 Name/Number Scripps Health care
Project Description Exterior Facade
Approximate Construction Dates From: 02/20/22 To: 06/30/22 Agency Name: Hiffman Asset Managment
Contact Person: Sonia Vales Telephone: 619-244-2049
Address:
Original Contract Amount: $1,100,000.00 Final Contract Amount: $ 1,220,000.00 If final amount is different from original amount, please explain (change orders, extra work, etc.).
Did you or any Subcontractor, file any claims against the Agency? Circle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No If you answered yes to either of the above two questions, please explain and indicate outcome of claims.
Project 4 Name/Number
Project Description
Approximate Construction Dates From: To
Centennial Real Estate
Concrete Repair , Deck Coating
09/20/22 Present
12100-0001\2654178v1.doc
City of MB Form
B-15
Agency Name:
Contact Person: Telephone:
Address:
Original Contract Amount: $ Final Contract Amount: $
If final amount is different from original amount, please explain (change orders, extra work, etc.).
Did you or any Subcontractor, file any claims against the Agency? C
ircle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No If you answered yes to either of the above two questions, please explain and indicate outcome of c
laims.
Project 5 N ame/Number
Project Description
Approximate Construction Dates From: To:
Agency Name:
Contact Person: Telephone:
Address:
Original Contract Amount: $ Final Contract Amount: $
If final amount is different from original amount, please explain (change orders, extra work, etc.).
Did you or any Subcontractor, file any claims against the Agency? C
ircle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No Centennial Real Estate
Jeff M 949351-3792
300,000.00 300,000.00
12100-0001\2654178v1.doc
City of MB Form
B-16
If you answered yes to either of the above two questions, please explain and indicate outcome of claims.
Project 6 Name/Number
Project Description
Approximate Construction Dates From: To:
Agency Name:
Contact Person: Telephone:
Address:
Original Contract Amount: $ Final Contract Amount: $
If final amount is different from original amount, please explain (change orders, extra work, etc.).
Did you or any Subcontractor, file any claims against the Agency? Circle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No
If you answered yes to either of the above two questions, please explain and indicate outcome of claims.
[Continue to Next Page]
12100-0001\2654178v1.doc
City of MB Form
B-17
Upon request of the City, the Bidder shall furnish e vidence showing a notarized financial statement, financial data, construction experience, or other additional information.
Failure to provide truthful answers to the questions above or in the following References Form may result in the Bid being deemed non-responsive.
Urban Runoff Certification. The Bidder certifies to
the City that he/she has trained his/her
employees and Subcontractors, if any, for Urban Runoff management and has included sufficient sums in the Bid Price to cover such costs of training as stipulated in the most current Regional Water Quality Control Board requirements, including the Municipal Separate Storm Sewer System National Pollutant Discharge Elimination System (NPDES) Permit. The Contractor is responsible for all clean up and payment of all fines levied as a result of any illegal discharge (as defined in NPDES permit) occurring as a result of the Contractor’s Work and/or operations.
I, the undersigned, certify and declare that I have
read all the foregoing answers to the Bidder’s
Proposal – Contractor’s Statement and know their contents. The matters stated in the Bidder’s Proposal – Contractor’s Statement answers are true of my own knowledge and belief, except as to those matters stated on information and belief, and as to those matters I believe them to be true. I declare under penalty of perjury under the laws of the State of California that the foregoing is correct.
Company
S
ignature:
Name:
Title:
Date:
Signature:
Name:
Title:
Date:
Oscar Bianchi
Oscar Bianchi
CEO
10/28/2022
City of Manhattan Beach
Pier Railings Replacement Project (E1268-22C), bidding on 10/31/2022 11:00 AM (PDT)
Printed 10/31/2022
PlanetBids, Inc.
City of Manhattan Beach
Pier Railings Replacement Project (E1268-22C), bidding on 10/31/2022 11:00 AM (PDT)
Printed 10/31/2022
PlanetBids, Inc.
City of Manhattan Beach
Pier Railings Replacement Project (E1268-22C), bidding on 10/31/2022 11:00 AM (PDT)
Printed 10/31/2022
PlanetBids, Inc.
City of Manhattan Beach
Pier Railings Replacement Project (E1268-22C), bidding on 10/31/2022 11:00 AM (PDT)
Printed 10/31/2022
PlanetBids, Inc.
City of Manhattan Beach
Pier Railings Replacement Project (E1268-22C), bidding on 10/31/2022 11:00 AM (PDT)
Printed 10/31/2022
PlanetBids, Inc.
12100-0001\2654178v1.doc
City of MB Form
B-18
DESIGNATION OF SUBCONTRACTORS
[Public Contract Code Section 4104]
PIER RAILING REPLACEMENT PROJECT
List all Subcontractors who will perform Work or lab o r or render service to the Contractor in or about the construction of the Work or improvement, or a Subcontractor licensed by the State of California who, under subcontract to the Contractor, specially fabricates and installs a portion of the Work or improvement according to detailed drawings contained in the Plans and Specifications, in an amount in excess of one-half of one percent of the Contractor’s total Bid or, in the case of bids or offers for the construction of streets or highways, including bridges, in excess of one-half of one percent of the Contractor’s total Bid or $10,000.00, whichever is greater. If all Subcontractors do not fit on this page, attach another page listing all information for all other Subcontractors.
Name under which
S
ubcontractor is
Licensed
and Registered
CSLB License
Number(s) and
Class(es)
DIR
Contractor
Registration
Number
Address and Phone Number Type of Work
(e
.g., Electrical)
Percentage of Total
Bi
d (e.g., 10%)*
*The percentage of the total Bid shall represent the “portion of the work” for the purposes of Public Contract Code Section 4104(b).
Craneveyor Corp 194646 1000006528 1524 North Potrero Ave South El Monte Railing Install 68
12100-0001\2654178v1.doc
City of MB Form
B-21
NONCOLLUSION DECLARATION FORM
T
O BE EXECUTED BY BIDDER AND SUBMITTED WITH BID
[Public Contract Code Section 7106]
P
IER RAILING REPLACEMENT PROJECT
The undersigned declares:
I am the of , the party making the foregoing
Bid.
The Bid is not made in the interest of, or on behalf
of, any undisclosed person, partnership,
company, association, organization, or corporation. The Bid is genuine and not collusive or sham.
The Bidder has not directly or indirectly induced or solicited any other Bidder to put in a false or sham Bid. The Bidder has not directly or indirectly colluded, conspired, connived, or agreed with any Bidder or anyone else to put in a sham Bid, or to refrain from bidding. The Bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the Bid price of the Bidder or any other Bidder, or to fix any overhead, profit, or cost element of the Bid price, or of that of any other Bidder. All statements contained in the Bid are true. The Bidder has not, directly or indirectly, submitted his or her Bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, Bid depository, or to any member or agent thereof, to effectuate a collusive or sham Bid, and has not paid, and will not pay, any Person or entity for such purpose.
Any person executing this declaration on behalf of a
Bidder that is a corporation, partnership, joint
venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the Bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on [date], at [city], [state].
S
ignature:
Printed Name:
S
ignature:
Printed Name:
Date: Date:
CEO Applied Restoration Inc.
10/28/2022
El Cajon Ca
Oscar Bianchi
Oscar Bianchi
10/28/2022
12100-0001\2654178v1.doc
City of MB Form
B-22
ADDENDA ACKNOWLEDGEMENT FORM
PIER RAILING REPLACEMENT PROJECT
Bidder’s Name:
The Bidder shall signify receipt of all Addenda here, if any:
Addendum Number Date Received Signature
If there are more Addenda than there is room in the chart above, attach another page acknowledging receipt of the Addenda.
Addenda #1 10/28/2022 Oscar Bianchi
Applied Restoration Inc.