Marine Avenue at Cedar Avenue Traffic Signal and Intersection Improvements Project
Budget and Expenditures
Total Project Funding
Marine Avenue at Cedar Avenue Traffic Signal and Intersection Improvements Project (ST17102, Prop C Fund)
$990,000
Total Expenditures
Design Agreement: KOA Corporation (Original Contract) $178,687 Total Design Expenditures $178,687
Construction Contract: Crosstown Electrical & Data, Inc. $311,963 25% Construction Contract Contingency & Market Volatility Adjustment
$77,990
Total Construction Contract Expenditures $389,953
Inspection Agreement: Quantum Quality Consulting, Inc. $120,250
Material Testing (TBD) $20,000
Additional Project Expenses $281,110
TOTAL $990,000