Larsson 2nd Street Booster Pump Station Upgrade Project Budget and Expenditure Summary Report

TOTAL BUDGET
Larsson Street Pump Station Improvement (12828E) $1,457,048.89 TOTAL BUDGET $1,457,048.89

EXPENDITURES

Professional Design Services Agreement (PACE) $138,116.00 Professional Design Services Agreement Amendment No. 1
(PACE)
$149,810.00
Professional Design Services Agreement Amendment No. 2
(PACE)
$96,480.00

TOTAL DESIGN EXPENDITURES $384,406.00

Construction Costs (TBD) $1,072,642.89
TOTAL CONSTRUCTION EXPENDITURES $1,072,642.89
TOTAL EXPENDITURES $1,457,048.89