FTIP #: LA0G1043
Subregion ID: I-405, I-110, I-105, and SR-91 Ramp and
Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 920000000MR31235
Rev: 12.13.2021 1 Measure R Funding Agreement – Highways – General
AMENDMENT No. 3
TO MEASURE R FUNDING AGREEMENT
BETWEEN CITY OF MANHATTAN BEACH AND THE LOS ANGELES COUNTY
METROPOLITAN TRANSPORTATION AUTHORITY
This Amendment No. 3 to the Funding Agreement (this “Amendment”), is dated as of March 25, 2022, by and between the City of Manhattan Beach ("Grantee") and the Los Angeles County Metropolitan Transportation Authority ("LACMTA").
RECITALS:
A. Grantee and LACMTA entered into that certain Funding Agreement No. 920000000MR31235 dated January 30, 2015, which was amended on August 25, 2020 and October 4, 2021, (as amended, the "Existing FA"), which Existing FA provides for the Plans, Specifications and Estimates (PS&E), Project Development, Right-of-Way, and Construction for Sepulveda Blvd at Manhattan Beach Blvd Intersection Improvements (NB, WB, EB Left turn Lanes and SB Right Turn Lane) (the “Project”); and
B. WHEREAS, the LACMTA Board at its January 27, 2022 meeting programmed and additional $1,066,000 for Plans, Specifications and Estimates (PS&E), Project Development, Right-of-Way, and Construction of Project. The total Project budget is $2,046,000; and
C. WHEREAS, the Funds are currently programmed for the Project as follows $980,000 in Measure R Funds in FY 2015-16 and $1,066,000 in Measure R Funds in FY 2021-22. The total designated amount for the Project is $2,046,000; and
D. Grantee and LACMTA desire to amend the Existing FA as provided herein.
FTIP #: LA0G1043
Subregion ID: I-405, I-110, I-105, and SR-91 Ramp and
Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 920000000MR31235
Rev: 12.13.2021 2 Measure R Funding Agreement – Highways – General
AGREEMENT:
NOW, THEREFORE, for good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the parties hereby agree as follows:
1. Part I, Paragraph 2.2 of the Existing FA is hereby amended by deleting it in its entirety and replacing it with the following: “To the extent the Measure R funds are available, LACMTA shall make to GRANTEE a grant of the Measure R funds in the amount of $2,046,000 (the “Funds”) for the Project. LACMTA Board of Directors actions on October 23, 2014, and January 27, 2022, granted the Measure R Funds for the Project. The Funds are currently programmed in Fiscal Years: $980,000 in FY 2015-16; and $1,066,000 in FY 2021-
22.”
2. Part II, Paragraph 6.1 of the Existing FA is hereby amended by deleting it in its entirety and replacing it with the following:
“6.1 GRANTEE shall submit the draft of Quarterly Progress/Expenditure Report (Attachment D-2) within sixty (60) days after the close of each quarter on the last day of the months November, February, May and August to the LACMTA Project Manager for review and pre-approval of the applicable report. LACMTA Project Manager shall review and respond in writing to the draft Quarterly Progress/Expenditure Reports within thirty (30) calendar days from receipt. Grantee shall submit the LACMTA pre-approved Quarterly Progress/Expenditure Report no later than five (5) days after receipt of LACMTA’s written approval. Should GRANTEE fail to submit either the draft or pre-approved reports within five (5) days of the due date and/or submit incomplete reports, LACMTA will not reimburse GRANTEE until the completed required reports are received, reviewed, and approved. The Quarterly Progress/Expenditure Reports shall include all appropriate documentation (such as contractor invoices, timesheets, receipts, etc.), and any changes to interim milestone dates that do not impact the final milestone date. All supporting documents must include a clear justification and explanation of their relevance to the Project. If no activity has occurred during a particular quarter, GRANTEE will still be required to submit the Quarterly Progress/Expenditure Reports indicating no dollars were expended that quarter. If a request for reimbursement exceeds $500,000 in a single month, then GRANTEE can submit such an invoice once per month with supporting documentation. Expenses that are not invoiced to LACMTA Accounts Payable within ninety (90) days after the lapsing date specified in Part II, Section 9.1 below are not eligible for reimbursement”
3. Part II, Section 9.1 (vii) of the Existing FA is hereby amended by deleting it in its entirety and replacing it with the following: “(vii) Expending the Funds granted under this FA for allowable costs by the lapsing date. All Funds programmed for FY 2015-16 are subject to lapse by June 30, 2023. All Funds programmed for FY 2021-22 are subject to lapse by June 30, 2024.”
4. Attachment A of the Existing FA is hereby replaced by Attachment A-1, attached.
5. Attachment B1-2 of the Existing FA is hereby replaced by Attachment B1-3, FTIP #: LA0G1043
Subregion ID: I-405, I-110, I-105, and SR-91 Ramp and
Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 920000000MR31235
Rev: 12.13.2021 3 Measure R Funding Agreement – Highways – General
attached.
6. Attachment C-2 of the Existing FA is hereby replaced by Attachment C-3, attached.
7. The parties have agreed that the Monthly Progress Report is no longer required and therefore, Attachment D-1 and all references thereto are hereby deleted.
8. Attachment E– TIP Sheet of the Existing FA is hereby replaced by Attachment E-1, attached.
9. Except as expressly amended hereby, the Existing FA remains in full force and effect as originally executed. All rights and obligations of the parties under the Existing FA that are not expressly amended by this Amendment shall remain unchanged.
FTIP #: LA0G1043
Subregion ID: I-405, I-110, I-105, and SR-91 Ramp and
Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 920000000MR31235
Rev: 09.14.2021 4 Measure R Funding Agreement – Highways – General
IN WITNESS WHEREOF, the parties have caused this Amendment No.3 to the FA to be executed by their duly authorized representatives as of the dates indicated below:
LACMTA:
LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY
By: ________________________________________ Date: ____________________ Stephanie N. Wiggins
Chief Executive Officer
APPROVED AS TO FORM:
DAWYN R. HARRISON
Interim County Counsel
By: ________________________________________ Date: ____________________ Deputy
GRANTEE:
CITY OF MANHATTAN BEACH
By: _______________________________________ Date: ____________________ Bruce Moe
City Manager
APPROVED AS TO FORM:
By: _______________________________________ Date: ____________________ Quinn Barrow
City Attorney
ATTEST:
By: _______________________________________ Date: ____________________ Liza Tamura
City Clerk
FTIP #:LA0G1043
SOURCES OF FUNDS Prior Years FY2020-21 FY2021-22 FY2022-23 FY2023-24 FY2023-24 Total Budget
% of Budget
LACMTA PROGRAMMED FUNDING
MEASURE R FUNDS 980,000$ 1,066,000$ 2,046,000$
LACMTA PROGRAMMED FUNDS BY
YEAR SUBTOTAL 980,000$ -$ 1,066,000$ -$ -$ -$ 2,046,000$ 100% OTHER SOURCES OF FUNDING:
LOCAL: -$ 0%
STATE: -$ 0%
FEDERAL: -$ 0%
PRIVATE OR OTHER: -$ 0% OTHER FUNDING SUBTOTAL -$ -$ -$ -$ -$ -$ -$ 0% TOTAL PROJECT FUNDS 980,000$ -$ 1,066,000$ -$ -$ -$ 2,046,000$ 100% ATTACHMENT A-1 - PROJECT FUNDING
Measure R Program - Funding Agreement Projects - FA# 9200000000MR31235 A-1 Project Title: Sepulveda Blvd at Manhattan Beach Blvd Intersection Improvements Project#: MR312.35
PROGRAMMED BUDGET - SOURCES OF FUNDS
Rev. 05.03.19 FA Measure R Hwys Gen Attachment A Project Funds SOURCES OF FUNDS Prior
Expenditures
FY 2021-22
Qtr 1
FY 2021-22
Qtr 2
FY 2021-22
Qtr 3
FY 2021-22
Qtr 4
FY 2022-23
Qtr 1
FY 2022-23
Qtr 2
FY 2022-23
Qtr 3
FY 2022-23
Qtr 4
TOTAL
BUDGET
LACMTA PROGRAMMED FUNDS:
MEASURE R FUNDS:
PAED $0
PS&E $62,800 $62,800
RW Support $37,000 $100,000 $166,000 $303,000
Const. Support $0
RW $108,000 $40,000 $400,000 $400,000 $948,000
Construction $0
Total MEASURE R $207,800 $40,000 $0 $0 $0 $500,000 $566,000 $0 $0 $1,313,800 SUM PROG LACMTA FUNDS: $207,800 $40,000 $0 $0 $0 $500,000 $566,000 $0 $0 $1,313,800
PROJECT FUNDING
FY21-22 and FY22-23 $207,800 $40,000 $0 $0 $0 $500,000 $566,000 $0 $0 $1,313,800 SOURCES OF FUNDS FY 2023-24
Qtr 1
FY 2023-24
Qtr 2
FY 2023-24
Qtr 3
FY 2023-24
Qtr 4
FY 2024-25
Qtr 1
FY 2024-25
Qtr 2
FY 2024-25
Qtr 3
FY 2024-25
Qtr 4
FY 2025-26
Qtr 1
TOTAL
BUDGET
LACMTA PROGRAMMED FUNDS:
MEASURE R FUNDS:
PAED $0
PS&E $0
RW Support $0
Const. Support $33,300 $33,300 $66,600
RW $0
Construction $332,800 $332,800 $665,600
Total MEASURE R $366,100 $366,100 $0 $0 $0 $0 $0 $0 $0 $732,200 SUM PROG LACMTA FUNDS: $366,100 $366,100 $0 $0 $0 $0 $0 $0 $0 $732,200
PROJECT FUNDING
FY23-24 and FY24-25 $366,100 $366,100 $0 $0 $0 $0 $0 $0 $0 $732,200
SUMMARY OF ALL FUNDS
PAED $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
PS&E $62,800 $0 $0 $0 $0 $0 $0 $0 $0 $62,800
RW Support $37,000 $0 $0 $0 $0 $100,000 $166,000 $0 $0 $303,000 Const. Support $33,300 $33,300 $0 $0 $0 $0 $0 $0 $0 $66,600 RW $108,000 $40,000 $0 $0 $0 $400,000 $400,000 $0 $0 $948,000 Construction $332,800 $332,800 $0 $0 $0 $0 $0 $0 $0 $665,600 TOTAL MILESTONES $573,900 $406,100 $0 $0 $0 $500,000 $566,000 $0 $0 $2,046,000 SUM PROG LACMTA FUNDS $573,900 $406,100 $0 $0 $0 $500,000 $566,000 $0 $0 $2,046,000 SUM NON-LACMTA FUNDS $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL PROJECT FUNDING $573,900 $406,100 $0 $0 $0 $500,000 $566,000 $0 $0 $2,046,000 ATTACHMENT B1-3 - EXPENDITURE PLAN COST & CASH FLOW BUDGET Measure R Program - Funding Agreement Projects - FA# 9200000000MR31235 A-3 Project Title: Sepulveda Blvd at Manhattan Beach Blvd Intersection Improvements Project#: MR312.35
PROGRAMMED SOURCES OF FUNDS
FTIP #: LA0G1044
Subregion ID: I-405, I-110, I-105 and SR-91 Ramp
and Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 9200000000MR31235
Rev: 05.03.19 1 FA Measure R Hwys Gen Attachment C Scope of Work
ATTACHMENT C-3
SCOPE OF WORK
PROJECT TITLE:
Sepulveda Blvd at Manhattan Beach Blvd Intersection Improvements (NB, WB, EB Left Turn Lanes and SB Right Turn Lane)
PROJECT LOCATION:
The project is located in the City of Manhattan Beach – Manhattan Beach Boulevard and Sepulveda Boulevard.
PROJECT LIMITS:
This project limits are 1,000 feet on the east leg and west leg of Manhattan Beach Boulevard and north leg of Sepulveda Boulevard
NEXUS TO HIGHWAY OPERATION, DEFINITION/PROJECT PURPOSE:
The project will involve widening and restriping of the intersection of Sepulveda Boulevard at Manhattan Beach Boulevard to provide Westbound to Southbound, Eastbound to Northbound and Northbound to Westbound Left-Turn Lanes. Left-turn movements at Sepulveda Boulevard at Manhattan Beach Boulevard are congested due to the lack of lane capacity.
PROJECT BUDGET:
COMPONENT AMOUNT
PA/ED 00,000
PS&E 62,800
R/W Support 303,000
R/W 948,000
Construction 665,600
Construction Support 66,600
Total Budget $2,046,000
SCOPE:
The Sepulveda Boulevard and Manhattan Beach Boulevard intersection is located in an area of the City of Manhattan Beach with limited street-side parking and moderately heavy pedestrian usage.
The design and subsequent construction is taking into account the need for the lowest possible impact on the livelihood of the residents, visitors and business owners. The intersection improvements include:
• Street widening at all quadrants of the intersection; • Additional left-turn lane in northbound, eastbound and westbound approaches; • Extension of median island along Sepulveda Boulevard at 11th Street; • New pavement, curb, gutters, sidewalk and driveway;
• Modifying the existing storm drain catch basin and connector pipe to address drainage issues;
• Signal, signing & striping layout; and
• Landscape/irrigation restoration and other appurtenant work.
FTIP #: LA0G1044
Subregion ID: I-405, I-110, I-105 and SR-91 Ramp
and Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 9200000000MR31235
Rev: 05.03.19 2 FA Measure R Hwys Gen Attachment C Scope of Work
The scope of work also includes records research, environmental analysis, agency/utility coordination, legal & plat mapping, utility potholing, field survey, fiber optic interconnect, ITS relocation and geotechnical work.
DESIGN:
I. Preliminary Design
Consultant to perform the following tasks:
A. Account for field visits of the project area to identify design issues. Record existing site conditions in photographs and/or video.
B. Read, review and understand all aspects and goals of the Lead Agency’s General Plan Circulation Element and other plans, as these plans pertain to the widening and ultimate build-out of ___ Road.
C. Incorporate provided layout plans to be incorporated into the final design.
D. Provide a complete survey of the project area, establishing horizontal and vertical control for the project. Mapping shall include topographic features within 50 feet of project area.
E. Identify and coordinate with all utilities in the project area to facilitate the final design of the Project.
F. Identify right-of-way acquisitions, and/or vacations to provide for the optimal alignment of Road, which shall incorporate roadway widening, development build outs and preservation of existing improvements and scenic character of the area.
G. Identify street pavement structural sections for project area.
H. Identify all drainage/BMP structure improvements, based upon hydrology, hydraulic calculations and water quality issues. Structural BMPs shall be incorporated into the street design for stormwater quality improvements prior to entering natural waterways.
I. Prepare and submit a Report identifying the ultimate alignment of roadway improvements, as well as the recommended ultimate repair strategy for As part of the Report, the Consultant shall prepare and provide CAD drawings of the proposed alignment, which shall include vertical and horizontal alignment, improvements, and drainage/BMP structures. Right-of-way acquisitions and/or vacations shall be clearly identified.
J. Prepare and submit an Engineer’s construction cost estimate for all recommended improvements identified in the Report.
II. Environmental Analysis
Consultant to perform the following tasks:
A. Define a complete and detailed project description and delineate project study areas that will meet the needs of technical analyses and Initial Study/Mitigated Negative Declaration (IS/MND).
B. Conduct the required technical analysis for the project.
C. Prepare, following completion of appropriate technical analysis, an Administrative Draft IS, consistent with CEQA Guidelines Appendix G, for review and approval by the City.
D. Prepare the Draft IS and CE for public circulation.
FTIP #: LA0G1044
Subregion ID: I-405, I-110, I-105 and SR-91 Ramp
and Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 9200000000MR31235
Rev: 05.03.19 3 FA Measure R Hwys Gen Attachment C Scope of Work
E. Coordinate with the City and prepare permit applications/notifications for the Project as applicable.
III. Final Design – Plans, Specifications and Estimates
Consultant to perform the following tasks:
A. Design the southbound to westbound right-turn lane on Aviation Boulevard.
B. Prepare civil roadway plans for the required improvements, consistent with City format. At a minimum, the plan set shall include Title Sheet, Site Plan, General Construction Notes, Horizontal Control, Typical Sections and Details, Plan and Profile, Drainage/BMP Structure(s) Details, Traffic Striping/Signage/Signal Plans, Street Lighting/Electrical, Bike Lane Plans, and Median/Landscaping Plans.
C. Submittal of plan set shall be delivered at 50% and 90% complete and final (five (5) sets per submittal). When project is complete, the Consultant shall provide AutoCAD files for all plan sheets.
D. Assist the City for the right-of-way acquisition.
E. Prepare construction specifications consistent with City format (SSPWC “Greenbook” APWA, current edition with updates.
F. Submittal of specifications shall be delivered to the City at 90% complete and final. When project is complete, the Consultant shall provide a digital file of specification package in Microsoft Word format for Windows.
G. Prepare an engineer’s construction cost estimate based on the itemized quantity take-off from the contract documents.
H. Submittal of the engineer’s construction cost estimate shall be delivered to the City at 90% complete and final in a spreadsheet format.
IV. Project Management and Preparation of Periodic Updated Schedule, Deliverables and Meetings
Consultant to perform the following tasks:
A. Meet as needed with the City to accomplish Project tasks as outlined. Meetings expected between the Consultant and City, shall be and not be limited to: Project Kick-off Meeting, presentation of “Summary Letter Report”, progress meetings and preparation for the Community Information Workshop at 90% design completion.
B. Provide periodic schedule updates on deliverables and meetings as changes to original schedule occur or as needed based on the needs of the project.
RIGHT-OF-WAY:
Right-of-Way Support and Right-of-Way Capital
Right-of-Way Support:
Consultant to perform the following tasks:
FTIP #: LA0G1044
Subregion ID: I-405, I-110, I-105 and SR-91 Ramp
and Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 9200000000MR31235
Rev: 05.03.19 4 FA Measure R Hwys Gen Attachment C Scope of Work
A. Prepare and provide exhibits, plats and legal descriptions for the properties requiring right of way acquisition, slope easements, temporary construction easements and/or rights-of-entry.
B. Meet as needed with the City to accomplish Project tasks as outlined. Meetings expected between the Consultant and City, shall be and not be limited to: Project Kick-off Meeting, site visits, progress meetings and preparation for City Council meetings.
C. Provide periodic schedule updates on deliverables and meetings as changes to original schedule occur or as needed based on the needs of the project.
Right-of-Way Capital:
Consultant to perform the following tasks:
A. Order title reports/litigation guarantees.
B. Present conceptual plans to property owners adjacent to project.
C. Shall choose an Appraiser to prepare and provide appraisal of properties requiring right of way acquisition.
D. Authorize appraisals and improvements pertaining to properties.
E. Notify and meet with property owners of appraisals and detailed improvements to their properties.
F. Set just compensation.
G. Present written offer letters and appraisal summaries to property owners.
H. Conduct negotiations to settlement.
CONSTRUCTION:
Based on Caltrans’s comments received to date, it is likely there will be insufficient funds remaining for construction. The project team will be able to determine the revised construction cost after the 5th plan check submittal to Caltrans.
City expects to Contract with a separate engineering firm to provide Construction Inspection for the Project. This will be accomplished through an RFP. The City will contract with a Contractor for construction.
The Design Consultant shall meet as needed with the City to accomplish Project tasks as outlined. Meetings expected between the Consultant and City, shall be and not be limited to: Pre-Construction Meeting, progress meetings and preparation of response to RFIs.
FTIP #: LA0G1044
Subregion ID: I-405, I-110, I-105 and SR-91 Ramp
and Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 9200000000MR31235
Rev: 05.03.19 5 FA Measure R Hwys Gen Attachment C Scope of Work
MILESTONES: The implementation schedule for this project will be as follows.
START DATE COMPLETION DATE
SOLICITATION (BID/PROPOSAL) 8/8/2016 1/3/2017
Develop Solicitation Package 8/8/2016
Solicitation Response 8/31/2016
Evaluations 9/1/2016 9/14/2016
Selection 9/19/2016 9/22/2016
Board Approval 1/3/2017
Contract Award 1/3/2017
Fully Executed Contract 1/3/2017
PLANNING
Prepare Concept Report
Prepare Feasibility Study
Prepare Project Study Report
Intelligent Transportation System (ITS)
Feasibility Study
Concept Exploration
PRELIMINARY DESIGN 1/2017 6/2017
Prepare Detailed Design Plans
Prepare Detailed Construction Plans
Prepare Project Cost Estimate
Intelligent Transportation System (ITS)
Concept of Operations
System Requirements
High Level Design
PA&ED 6/2019 3/2017
Prepare Environmental Document
Document Type:______________
6/1/2019 9/2/2019
Categorical Exemption
Scoping
Technical Studies
Draft Environmental Document
Final Environmental Document
Community Outreach
Secure Project Approval
Intelligent Transportation System (ITS)
Categorical Exemption Filing 9/2/2019
PS&E 4/2017 12/2022
35% PS&E 4/5/2017 3/5/2018
Preliminary Investigations
Preliminary Foundation
Geometric Drawings 4/5/2017 7/20/2017
Bridge Type Selection Roadway and Retrofit
Strategy
ADL Review
Utilities 1/5/2018
Right-of-Way 3/5/2018 12/2022
Estimating 3/5/2018
Civic Design
Structural Design
Intelligent Transportation System (ITS)
Detailed Design 3/5/2018
ITS Drawings
System Plans
Communications Plans
FTIP #: LA0G1044
Subregion ID: I-405, I-110, I-105 and SR-91 Ramp
and Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 9200000000MR31235
Rev: 05.03.19 6 FA Measure R Hwys Gen Attachment C Scope of Work
CONSTRUCTION MILESTONES: The implementation schedule for this project will be as follows.
START DATE COMPLETION DATE
SOLICITATION (BID/PROPOSAL) 3/2023 6/2023
Develop Solicitation Package
Solicitation Response
Systems Integrations Plans
Software Specifications
Project Review & Comments
65% PS&E 5/16/2018 8/20/2018
Civil Design Plans
Right-of-Way Engineering
Structural Design
Prepare Project Cost Estimate
Intelligent Transportation System (ITS
Detailed Design
ITS Drawings
System Plans
Communications Plans
Systems Integrations Plans
Equipment Specifications
Software Specifications
Project Review & Comments
95% PS&E 4/8/2019 12/2022
Civil Design Plans
Structural Design
Intelligent Transportation System (ITS)
Detailed Design
ITS Drawings
System Plans
Communications Plans
Systems Integrations Plans
Equipment Specifications
Software Specifications
Submittals & Reviews
Submit Final PS&E 12/2022
Outside Agency Review
RIGHT OF WAY SUPPORT 9/2021 12/2022
Certification/Mapping
Appraisal
RIGHT OF WAY ACQUISITION 12/2021 12/2022
Certification/Mapping
Title Report
Meet with Property Owners
Appraisal
Environmental Investigation
Closing/Acquire Property/Relocation
Physical Possession
Remediation
Utility Relocation
Third Party Coordination
Design Utilities
Relocate Utilities
FTIP #: LA0G1044
Subregion ID: I-405, I-110, I-105 and SR-91 Ramp
and Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 9200000000MR31235
Rev: 05.03.19 7 FA Measure R Hwys Gen Attachment C Scope of Work
Evaluations
Selection
Board Approval Process
Contract Award
Fully Executed Contract
EXCAVATION 7/2023 7/2024
Clear/Grub
Survey
Sample Borings
Grading
Compaction
Drainage
ENVIRONMENTAL
Hazardous Materials Handling
Archaeological
Air Quality Monitoring
CONCRETE
Form Work
Rebar Placement
Pole Placement
TRAFFIC CONTROL
TMP
STRUCTURAL
False Work
Iron Placement
Pole Placement
UTILITIES
DWP
SCE
LADOT
MATERIALS
Long-Lead Equipment
Staging
Material Lay Down Area
Signage
ELECTRICAL
Power U/G Communication
A/G Testing/Acceptance
FTIP #: LA0G1044
Subregion ID: I-405, I-110, I-105 and SR-91 Ramp
and Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 9200000000MR31235
Rev: 05.03.19 8 FA Measure R Hwys Gen Attachment C Scope of Work
START DATE COMPLETION DATE
LANDSCAPE
Clearing
Planting
Plant Establishment
Irrigation
Testing
General Construction/close out project 7/2024
CHANGE ORDERS
P.O. Processing Time
Weather
Third Party Issues
Strike Labor Walk Outs
Force Majeure
Claims
FTIP #: LA0G1044
Subregion ID: I-405, I-110, I-105 and SR-91 Ramp
and Interchange Improvements (South Bay)
Project#: MR312.35
Amendment No. 3
FA# 9200000000MR31235
Rev: 05.03.19 9 FA Measure R Hwys Gen Attachment C Scope of Work
ATTACHMENT C – Location Map(s)
Los Angeles Metropolitan Transportation Authority
2021 Federal Transportation Improvement Program ($000)
LA0G1044TIP ID Implementing Agency Manhattan Beach, City of SCAG RTP Project #: 1AL04
Conformity Category: EXEMPT - 93.126
Project Description: Sepulveda Bl at Manhattan Beach Bl, Dual Left-Turn Lanes, WB to SB, NB to WB & EB to NB. Study:N/A Is Model: NO Model #:
PM: Prem Kumar - (310) 802-5352
Email: [email protected]
LS: N LS GROUP#:
PPNO:EA #:
Program Code: NCN95 - LEFT TURN LANE(S) Stop Loc:
Air Basin: SCAB Envir Doc: DRAFT NEGATIVE DECLARATION - 03/31/2014
Uza: Los Angeles-Long
Beach-Santa Ana
Sub-Area: Sub-Region: South Bay Cities
COG
CTIPS ID:
Lane # Extd: Lane # Prop: Imprv Desc:
Hov acs eg loc: Toll Rate:
0.00 Toll Colc Loc: Toll Method:
System :Local Hwy Completion Date 06/30/2025Phase: ROW AcquisitionDistance: Postmile: Route :
PRIOR PROG TOTAL BEYONDPHASE 25/2624/2523/2422/2321/2220/21 $0 $0 $0 PEMR20H - Measure R 20% Highway
CON
RW
SUBTOTAL $2,046 $1,066 $980
$980 $0 $980
$1,066 $1,066 $0
$980 $1,066 TOTAL
TOTAL PE: $0 TOTAL RW: $1,066 TOTAL CON: $980
$2,046
TOTAL PROGRAMMED: $2,046
- General Comment: The project is at ROW process. Funding increase of $1,066,000 is to cover ROW engineering and acquisition. - Modeling Comment:
- TCM Comment:
- Amendment Comment:
- CMP Comment:
- Narrative:
Change reason:Funding increase of $1,066,000 Total Project CostLast Revised Amendment 21-21 - Submitted $2,046 1Page Wednesday, March 9, 2022