Manhattan Beach Boulevard and Sepulveda Boulevard
Intersection Improvement Project

Budget and Expenditures

Total Project Funding
Measure R South Bay Highway Program $980,000
Proposition C Local Return $414,593
Additional Measure R South Bay Highway Program $1,066,000 Project (09823E) TOTAL $2,460,593

Total Expenditures
Design Contract: Onward Engineering (Original Contract) $ 210,133 Onward Engineering Amendment No. 1 $ 77,035
Onward Engineering Amendment No. 2 $ 172,046
TOTAL DESIGN EXPENDITURES $ 459,214

Right-of-Way Acquisition and Construction Phase (TBD) $ 2,001,379

TOTAL ESTIMATED RIGHT-OF-WAY ACQUISITION AND

CONSTRUCTION PHASE EXPENDITURES
$ 2,001,379

TOTAL $2,460,593