Budget and Expenditures Summary
Rowell Avenue Sidewalk Gap Closure Between 1st Street and Curtis Avenue BUDGET
Rowell Avenue Sidewalk Gap Closure between 1st Street and Curtis Avenue (CIP Measure M ST20104) $840,000
TOTAL BUDGET
$840,000
EXPENDITURES
Pre Design Miscellaneous
$5,721.90
Design Services Agreement (TAIT & Associates, Inc.)
$145,221.00
Easement LA County Recorder
$75.00
Construction Contract (FS Contractors, Inc.)
$547,970.00
Construction Contingency (10%)
$54,797.00
Inspection Services (estimated)
$86,215.10
TOTAL EXPENDITURES
$840,000.00
BALANCE
$0.00