Manhattan Beach Boulevard and Peck Avenue Traffic Signal Improvement Project
Budget and Expenditures
Total Project Funding
Measure R Local Return Program $205,000
LACMTA Measure R Grant 100,000
LACMTA Measure M Grant 740,000
TOTAL $1,045,000
Total Estimated Expenditures
Design Agreement: Iteris, Inc. (Original Contract) $149,802 20% Design Contract Contingency 29,960
Total Design Expenditures $179,762
Construction Contract: Calpromax Engineering, Inc. $611,936 20% Construction Contract Contingency & Market Volatility Adjustment 122,387 Total Construction Contract Expenditures $734,323
Inspection Agreement: Quantum Quality Consulting, Inc. $120,250 Material Testing 6,826
Additional Project Contingency 3,839
Total Other Expenditures $130,915
TOTAL $1,045,000