STORMWATER CIP BUDGET 2024‐2029 PROJECT COST
Annual Storm Drain Repairs $3,622,073
Replace various sections of stormwater drain line.
Storm Drain Capital Best Management Practices (BMPs) $1,635,81 0 Installation of storm drain debris collection devices to prevent trash from entering storm drain pipes.
Peck Avenue Storm Drain Improvements $1,530,00 0
The project will construct a new storm drain line along 21st Street to the existing storm drains on Meadows Avenue and Peck Avenue.
Shelley Street Storm Drain Improvements $700,000
Construction of storm drain piping, and additional catch basins with water quality inserts to improve water quality.
Beach Cities Green Streets $362,500
Multi‐jurisdiction project to construct a regional stormwater quality improvements project.
Golf Course Storm Drain Lift Station Electrical Upgrades $350,00 0 Procure and replace the electrical elements at the Westdrift Golf Course Storm Drain Lift Station.
CCTV Storm Drain System $150,000
Use CCTV to perform an assessment of the City's storm drain system.
TOTAL PROJECT COSTS 8,350,383 $