Cycle 2 Water Infrastructure Improvements and Street Resurfacing Project Budget and Expenditures Summary
BUDGET
Cycle 2 Water Infrastructure Improvements Project (Water Fund) $2,443,500.00 Cycle 2 Water Infrastructure Improvements Project – Street Resurfacing (Measure M Fund)
$700,000.00
TOTAL BUDGET $3,143,500.00

EXPENDITURES
Inspection Services Contract (To be awarded at subsequent Council Meeting)
$200,000.00
Construction Contract award for Cycle 2 Water Infrastructure Improvements Project –Stephen Doreck Equipment Rental, Inc. $2,354,319.00
Contingency for Unforeseen Conditions (25%) $588,579.00 TOTAL EXPENDITURES $3,142,898.00