Budget and Expenditure Summary Report

Manhattan Beach City Council
June 4, 2024

Document
Budget and Expenditure Summary Report
Meeting
June 4, 2024
Body
Manhattan Beach City Council
Original file
437 KB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.

Item Description Measure M CIP Fund Bond Fund Water Wastewater Total Fire Station No. 2 Project $ 1,134,600 $ 9,100,000 $ 10,234,600 Traffic Signal Replacement Program $ 100,000 $ 100,000
SCADA $ 10,000 $ 24,000 $ 34,000
MB Automated Traffic Signal Project (MBATS) $ 8,944 $ 8,944 Facilities Improvements Program $ 105,000 $ 105,000
Totals $ 108,944 $ 1,239,600 $ 9,100,000 $ 10,000 $ 24,000 $ 10,482,544 Item Description
Fire Station No.
2 Project
Traffic Signal
Replacement
Program
Water and
Wastewater SCADA
Accounts
Manhattan Beach
Automated Traffic
Signal Project
Facilities
Improvements
Program Total
Feasibility Study (Griffin Structures) $ 136,362 $ 136,362 Design Services (WLC/PBK) $ 764,710 $ 764,710
Construction Management (Griffin Structures) $ 983,486 $ 983,486 Geotech. & Const. Testing (Leighton) $ 81,000 $ 81,000
Construction Contract (Monet) $ 7,055,000 $ 7,055,000
Construction Contingency (Monet) $ 897,506 $ 100,000 $ 30,201 $ 8,944 $ 39,284 $ 1,075,935 Fire Alerting System (Westnet) $ 146,722 $ 146,722
Furniture (Multiple Vendors) $ 65,716 $ 65,716
Permits & Misc. Fees $ 169,814 $ 169,814
Estimated $ 10,234,600 $ 100,000 $ 30,201 $ 8,944 $ 105,000 $ 10,478,745 FIRE STATION NO. 2

BUDGET & EXPENDITURE SUMMARY REPORT
Project Budget
Project Expenditures