RESOLUTION NO. 24-0063

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF

MANHATTAN BEACH, CALIFORNIA, ADOPTING A LIST OF
STREET REPAIR PROJECTS FOR FISCAL YEAR 202 4-
2025 FUNDED BY S ENATE BILL 1: THE ROAD REPAIR
AND ACCOUNTABILITY ACT OF 2017; AND AUTHORIZING

THE PUBLIC WORKS DIRECTOR TO SUBMIT THE

NECESSARY PROJECT INFORMATION TO THE

CALIFORNIA TRANSPORTATION COMMISSION
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and signed into law by the Governor in April 2017 to address the significant multi -modal transportation funding shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of our City are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and WHEREAS, the City must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and
WHEREAS, the City, will receive an estimated $907,812 RMRA funding in Fiscal Year 2024-25 from SB 1; and
WHEREAS, this is the seventh year in which the City is receiving SB 1 funding and will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements and, increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City Council annually adopts a Capital Improvement Plan which has undergone a robust public process to ensure public input into our community’s transportation project list and received the latest Pavement Management Program updated report at the January 1 8, 20 22 City Council meeting, and
WHEREAS, the City used a Pavement Management Program to develop the SB 1 project list to ensure revenues are being used on the most high -priority and cost -effective projects that also meet the communit y’s priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate streets/roads throughout the City this year and similar projects into the future; and
WHEREAS, the City’s latest Pavement Management Program Assessment found that the City’s streets and roads are, on average, in a fair condition and this SB 1 revenue will help us increase the overall quality of our road system and over the next decade will bring our streets and roads into an improved condition; and WHEREAS, the SB 1 project list and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting -edge technology, materials and practices, will have significant positive co-benefits statewide.

NOW, THEREFORE THE MANHATTAN BEACH CITY COUNCIL HEREBY
RESOLVES AS FOLLOWS:

SECTION 1. The foregoing recitals are true and correct.

SECTION 2. The Annual Street Resurfacing Program has been delayed by the Pandemic and subsequent inflation resulting in construction cost escalation.

The original bids received for the Cycle 2 Street Resurfacing Project were higher than the allowable budget which resulted in a bifurcation of the scope and a rebid of the project. The following previously proposed and adopted projects from fiscal years 2023-2024 may also utilize fiscal year 2024 -2025 Road Maintenance and Rehabilitation Account (RMRA) revenues. The Capital Improvement Plan Budget will utilize funding in the approximate amount of $ 907,812 from the fiscal year 2024-2025 RMRA revenues funded by Senate Bill 1. The City intends to resurface or reconstruct these streets by cold mill and overlay, or full -depth reconstruction, respectively. Where necessary, repairs to the curb and gutter, sidewalk, and installation/reconstruction of curb ramps will also be constructed to comply with the Americans with Disabilities Act (ADA).

The following previously proposed and adopted projects may also utilize Fiscal Year 2024 -25 Road Maintenance and Rehabilitation Account revenues in their delivery. With the relisting of these projects in the adopted fiscal year resolution, the City is reaffirming to the public and the State our intent to fund these projects with Road Maintenance and Rehabilitation Account revenues:

Project: Cycle 2 Street Resurfacing Project – Marine Ave and 14th Streets Street Names
(Surfaces or
Reconstruct)
Between Intersecting
Streets
Useful Life
(Years)
Estimated
Schedule
Marine Avenue Blanche Road–
Valley Drive
15-20 July ’24 -
December ‘24
14th Street Laurel Avenue –
Pacific Avenue
15-20 July ’24 -
December ‘24
14th Street Ardmore Avenue –
Deegan Place
15-20 July ’24 -
December ‘24

The following list of newly proposed projects will be funded in-part or solely with Fiscal Year 2024-2025 Road Maintenance and Rehabilitation Account revenues:

Project: Design Services for Cycle 3 Street Resurfacing Project Street Names
(Design)
Between
Intersecting Streets
Useful Life
(Years)
Estimated
Schedule
Manhattan Beach
Blvd
Sepulveda Blvd –
Dianthus Street
15-20 June ’24 – June ‘25
Pech Avenue Marine Avenue – 18th
Street & 12th Street –
Manhattan Beach
Blvd
15-20 June ’24 – June ‘25
19th Street Peck Avenue -
Herrin Avenue
15-20 June ’24 – June ‘25
SECTION 3. The Council hereby directs the Public Works Director to submit the street information to the California Transportation Commission as required by the Act including year-end reporting for all SB 1 projects.

SECTION 4. The City Clerk shall certify to the passage and adoption of this resolution.

ADOPTED on June 4, 2024
AYES:

NOES:

ABSENT:

ABSTAIN:

_________________________________

JOE FRANKLIN
Mayor
ATTEST:
_________________________________

LIZA TAMURA
City Clerk

← All documents from this meeting