Manhattan Beach Boulevard Eastbound Left-Turn Improvement at Aviation Boulevard Project Budget and Expenditures Summary Report
Total Project Funding
Measure M Transportation System & Mobility Program
$1,200,000
Total Expenditures
Design Agreement: KOA Corporation (Original Contract)
$ 161,780
20% Contingency
$ 32,356
TOTAL DESIGN EXPENDITURES
$ 194,136
Construction Agreement (DBX, Inc.)
$ 543,606
25% Contingency
$ 135,901
TOTAL ESTIMATED CONSTRUCTION EXPENDITURES
$ 679,507
Material Testing & Inspection
$ 326,357
TOTAL
$1,200,000