8 MG Peck Reservoir Replacement Project
Budget and Expenditures Summary
BUDGET
Peck Ground Level Reservoir Replacement (15836E)
$40,500,000.00
TOTAL BUDGET
$40,500,000.00
EXPENDITURES
Total Project Expenditures to Date
$39,644,246.00
Butier Engineering Inc. Amendment No. 4 – Additional CM & Inspection for Treatment Plant Startup & Commissioning 350,025
Operational LACSD Industrial Wastewater Discharge Permit (ESTIMATE) 400,000
TOTAL EXPENDITURES
$40,394,271.00
REMAINING BALANCE
$105,729.00