Budget and Expenditures Summary
Ceramic Studios Renovations Kiln Installation Project
BUDGET
Ceramic Studios Renovations Kiln Installation Project (CIP ) $527,000 TOTAL BUDGET $527,000
EXPENDITURES
Design Services Agreement (IDS Group , Inc.) $95,224.50 Design Miscellaneous $8,810.16
Inspection Services (Ardurra Group) $96,720.00
Construction Contract (RAMCO General Engineering Contractor) $273,773.00 Construction Contract Change Order No. 1 $27,233.46
Construction Contract Change Order No. 2 $15,655.99
Construction Miscellaneous $9,592.89
TOTAL EXPENDITURES $52 7,000.00
BALANCE $0.00