ITEMDESCRIPTION QUANTITY UNITS UNIT PRICE TOTAL
1 Mobilization/Clearing & Grubbing at 5%LS LS LS $4,765 2 Erosion Control and Site Protection LS LS LS $5,000
3 Building Demolition 3000 SF $15 $45,000
4 Covered Walkway Demolition 600 SF $10 $6,000
5 Concrete Sidewalk Removal 715 SF $20 $14,300
6 Interior Removals LS LS LS $5,000
7 Debris Haul LS LS LS $10,000
8 Utility Disconnect LS LS LS $5,000
9 Irrigation and Turf 5000 SF $10 $5,000
10 Subtotal $100,065
11 Contingency at 25% $25,016
12 Total Construction $125,081
13 Design/Admin at 15% $16,370
14 Grand Total $141,451
CALL IT $142,000
6/30/2025
Construction Cost Estimate
Marine Avenue Park - Demolition of Racquetball Building City of Manhattan Beach
Cost Estimate
Manhattan Beach City Council
October 7, 2025
- Document
- Cost Estimate
- Meeting
- October 7, 2025
- Body
- Manhattan Beach City Council
- Original file
- 233 KB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.