CONSIDERATION OF OPTIONS FOR THE ESCALATORS AT METLOX PARKING STRUCTURE DECEMBER 16, 2025

TABLE OF CONTENTS
DECEMBER 16, 2025

EXISTING CONDITIONS

FINAL DESIGN OPTIONS TO REPLACE ESCALATORS
OPTION I: REPLACE WITH MARINE HARDENED ESCALATORS
OPTION II: REPLACE WITH TWO ELEVATORS (AND REFURBISH EXISTING EMERGENCY EGRESS STAIRWAY)

SUMMARY OF DESIGN OPTIONS

FUTURE SECOND ELEVATOR OPTIONS

AERIAL VIEW OF LOCATION
DECEMBER 16, 2025

AREA OF WORK

EXISTING - PLAZA RENDERING
DECEMBER 16, 2025

EXISTING - ADDITIONAL VIEWS
DECEMBER 16, 2025

EXISTING - SECTIONS
DECEMBER 16, 2025
ALL RENDERINGS ASSUME A STANDARD 6:12 ESCALATOR RUN

OPTION I - REPLACE WITH MARINE HARDENED ESCALATORS
DECEMBER 16, 2025

OPTION I - POTENTIAL COSTING
DECEMBER 16, 2025
THROUGHPUT:
6,000 PEOPLE PER HOUR FOR ESCALATORS
ESTIMATED COST:
$850,000
SCHEDULE:
2-4 MONTH DESIGN/PERMIT
4-6 MONTHS FABRICATION
3-4 MONTHS INSTALL
9-14 MONTHS TOTAL

OPTION II - INSTALL TWO NEW ELEVATORS & REFURBISH EGRESS STAIR DECEMBER 16, 2025

OPTION II - GARAGE VIEW
DECEMBER 16, 2025

OPTION II - REFURBISHED ADJACENT EMERGENCY EGRESS STAIRWAY DECEMBER 16, 2025

RECOMMENDED FINISH NOTES

UPGRADED DOORS ON MAGNETIC HOLD OPENS TIED TO FIRE ALARM

FLOORS TO REMAIN

NEW PAINT/GRAPHICS

WAYFINDING SIGNAGE

NEW LIGHTING
A
B
C
C
D
E
E

OPTION I - POTENTIAL COSTING
DECEMBER 16, 2025
THROUGHPUT:
350 PEOPLE/HOUR FOR ELEVATORS
800 PEOPLE/HOUR FOR STAIR
ESTIMATED COST:
$1.5M
SCHEDULE:
4-6 MONTH DESIGN/PERMIT
4-6 MONTHS FABRICATION
2-4 MONTHS INSTALL
10-16 MONTHS TOTAL

SUMMARY
DECEMBER 16, 2025
OPTION II: ELEVATOR/ELEVATOR + REFURBISHED ADJACENT STAIRWAY OPTION I: REPLACEMENT W/ MARINE HARDENED ESCALATORS

THROUGHPUT
6000 PEOPLE PER HOUR
COST:
$0.85M
SCHEDULE:
9-14 MONTHS TOTAL
THROUGHPUT:
350 PEOPLE PER HOUR*
COST:
$1.5M
SCHEDULE:
10-16 MONTHS TOTAL
*ELEVATORS ONLY

FUTURE SECOND ELEVATOR OPTIONS
DECEMBER 16, 2025
A
C
B

FUTURE SECOND ELEVATOR OPTION A
DECEMBER 16, 2025
E
ELEVATOR CONNECTS THREE STORIES AND WOULD REQUIRE A 1-HOUR RATED ENCLOSURE AND LOBBIES/DEPLOYABLE SHUTTERS LOCATION OPENS ON FLAT SLAB AT ALL AREAS BUT WOULD REDUCE OVERALL PARKING BY 2 STALLS

AN ALTERNATE IS POSSIBLE ON THE SOUTH SIDE OF THE STAIR FOR NO PARKING LOSS BUT WOULD ENCROACH ON THE PLAZA

THIS WOULD LOOK MOST INTENTIONAL
P2 LEVEL
P1 LEVEL

GROUND LEVEL

FUTURE SECOND ELEVATOR OPTION B
DECEMBER 16, 2025

ELEVATOR CONNECTS THREE STORIES BUT DUE TO LOCATION MAY FORGO LOBBIES/HOISTWAY PROTECTION

LOCATION REQUIRES CUSTOM CAB WITH SIDE/FRONT OPENING TO AVOID QUEUING IN TRAFFIC WOULD REQUIRE MINIMAL DEMO AND CAN BE BRACED FROM EXISTING STRUCTURE.

WOULD LIKELY BE MOST COST EFFECTIVE
P2 LEVEL
P1 LEVEL

GROUND LEVEL

FUTURE SECOND ELEVATOR OPTION C
DECEMBER 16, 2025
ELEVATOR CONNECTS THREE STORIES AND WOULD REQUIRE A 1-HOUR RATED ENCLOSURE AND LOBBIES/DEPLOYABLE SHUTTERS

LOCATION OPENS ON FLAT SLAB AT ALL AREAS BUT WOULD NOT REDUCE PARKING

THIS WOULD LIKELY BE LEAST DISRUPTIVE LOCATION
P2 LEVEL
P1 LEVEL

GROUND LEVEL

QUESTIONS
DECEMBER 16, 2025