Cities Index.
PowerPoint Presentation - 28th Street SW Infiltration Project

Manhattan Beach City Council
December 16, 2025

Document
PowerPoint Presentation - 28th Street SW Infiltration Project
Meeting
December 16, 2025
Body
Manhattan Beach City Council
Original file
1.2 MB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.

28th Street stormwater infiltration project
December 16, 2025

Background
28th St. Stormwater Infiltration project
december 16, 2025
March 2025 City Council Approved Plans & Specifications and Authorized the bid solicitation June 2025 Issued Request for Pre-qualification Process (RFQ) to establish a list of qualified contractors August 2025 Advertised Construction Bid Solicitation
October 7, 2025 Project Update Presented to City Council October 21, 2025 Bid Opening – Four (4) Bids Received
October 23, 2025 Presented Traffic Control Plan to Public Parking Improvement Commission

Four (4) bids were received for the Project; key bid results:

Bids received
28th st. stormwater infiltration project
December 16, 2025
Contractor
Base Bid
Total Additive Bid Items.

Total Bid Amount (Base + Additive)
Var. of Total Bid from Engr’s Est.

Zusser Company Inc.
$23,136,010.00
$3,694,500.00
$26,830,510.00
3%
Stacy and Witbeck, Inc.
$26,954,548.25
$3,535,670.00
$30,490,218.25
17%
Mike Bubalo Construction Co., Inc.
$32,569,855.00
$4,522,000.00
$37,091,855.00
43%
Environmental Construction, Inc.
$33,459,643.00
$6,168,462.00
$39,628,105.00
52%

Bid reviewed for completeness and compliance
Required documents submittals
Zusser deemed the lowest responsive and responsible bidder Bid review and analysis
28th st. stormwater infiltration project
December 16, 2025

Bid included the following additive bid items:

Additive bid items
28th st. stormwater infiltration project
December 16, 2025

Bid included the following for the additive bid items:

Additive bid items (cont.)
28th st. stormwater infiltration project
December 16, 2025

Recommended award
28th st. stormwater infiltration project
December 16, 2025

RFP Issued August 14, 2025
Four (4) Proposals Received
Transtech Engineers Best Met City’s Needs
Const. management & inspection
28th st. stormwater infiltration project
December 16, 2025

CWE Professional Design Services Agreement Amendment No.2:

Includes an additional $167,491, to complete the design phase And $353,888 for design support during construction
Extend termination date to June 30, 2028
Construction eng support
28th st. stormwater infiltration project
December 16, 2025

construction TIMELINE
28th St. Stormwater Infiltration project
December 16, 2025
26th ST PARKING LOT – MAR. 2026 TO MAR. 2027
MAN. AVE. 27TH TO 26TH – APR. 2026 TO SPRING 2027
MAN. AVE. AT 28TH – APR. 2026 TO SEPT. 2026
MAJOR CONSTRUCTION PHASE FROM DEC. 2025 TO MARCH 2027
AC PAVING MAR. 2027
NTP 1 1/15/26
NTP2 3/16/26
Construction Award 12/16/25

Project budget
28th st. stormwater infiltration project
December 16, 2025

Staff recommends that City Council:

A. Adopt Resolution No. 25-0035:

Awarding Construction Contract to Zusser Company, Inc. in the amount of $25,308,810 for the 28th Street Stormwater Infiltration Project (28th Street Project); and Authorizing the City Manager to execute the contract, and authorize the City Manager and/or his/her designee to approve an extra work contingency up to $2,530,881. recommendations
28th st. stormwater infiltration project
December 16, 2025

B. Adopt Resolution No. 25-0036:

Approving a Professional Services Agreement with Transtech Engineers, Inc. in the amount of $1,095,755 for Construction Management and Inspection Services for the 28th Street Project; and Authorizing the City Manager and/or his/her designee to execute the agreement.

C. Adopt Resolution No. 25-0037:

Approving Amendment No.2 to the Professional Services Agreement with CWE for additional design services in the amount of $521,380 for the 28th Street Project; and Authorizing the City Manager and/or his/her designee to execute the agreement.

Recommendations (Cont.)
28th st. stormwater infiltration project
December 16, 2025

Project Manager Contact Info:

Eduardo Pech, P.E.

Senior Civil Engineer
(310) 802-5340
[email protected]
Questions & answers
28th st. stormwater infiltration project
December 16, 2025

← All documents from this meeting