Manhattan Beach Boulevard and Sepulveda Boulevard Intersection Improvement Project Budget and Expenditures
Total Project Funding
Measure R South Bay Highway Program
$2,046,000
Proposition C Local Return
$414,593
Project (09823E) TOTAL
$2,460,593
Total Expenditures
Design Contract: Onward Engineering (Original Contract) $ 210,133
Onward Engineering Amendment No. 1
$ 77,035
Onward Engineering Amendment No. 2
$ 172,046

TOTAL DESIGN EXPENDITURES
$ 459,214
1101 N. Sepulveda Right-of-Way Acquisition
$ 284,000
1200 N. Sepulveda Right-of-Way Acquisition
$ 138,000
1119 N. Sepulveda Temporary Construction Easement Acquisition $ 40,500
Construction Phase
$1,579,379

TOTAL ESTIMATED RIGHT-OF-WAY ACQUISITION AND CONSTRUCTION PHASE EXPENDITURES $2,001,379
TOTAL
$2,460,593