CHANGE ORDER
[01]

Page 1 of 2 ends

Change Order No. 01
Date: 11/10/21
Project Name: P25 Radio System Upgrade
Customer Name: Manteca Police Department
Customer Project Mgr: Charlie Goeken
The purpose of this Change Order is to: (highlight the key reasons for this Change Order) Extend completion date to 2/28/22. Due to issues with the Customers Network requiring additional design and additional link testing. This change order covers the cost to remobilize once customer’s network is ready.

Customer will need to advise 30 days prior to 2/28/22 if their network will not be completed by 3/1/22.

Contract # Lease Purchase Agreement Contract Date: 12/1/21 In accordance with the terms and conditions of the contract identified above between Manteca Police Department and Motorola Solutions, Inc., the following changes are approved:

Contract Price Adjustments
Original Contract Value: $ 497,570.00
Previous Change Order amounts for Change Order numbers
through - - - $0.00
This Change Order: $ 30,274.00
New Contract Value: $ 527,844.00
Completion Date Adjustments
Original Completion Date: 7/30/21
Current Completion Date prior to this Change Order: 7/30/21 New Completion Date: 3/31/22
ATTACHMENT 2

CHANGE ORDER
[01]

Page 2 of 2 ends

Changes in Equipment: (additions, deletions or modifications) Include attachments if needed N/A
Changes in Services: (additions, deletions or modifications) Include attachments if needed Additional PM, Engineering and ST time for change in network and retesting.

Schedule Changes: (describe change or N/A)
Move completion date to 3/31/22
Pricing Changes: (describe change or N/A)
Increase contract 30,274
Customer Responsibilities: (describe change or N/A)
Sign Change Order
Get ACUS Circuit installed
Payment Schedule for this Change Order:
(describe new payment terms applicable to this change order) Payment will be made separate from Lease Agreement
100 % due upon fully executed change order 01 document
Unless amended above, all other terms and conditions of the Contract shall remain in full force. If there are any inconsistencies between the provisions of this Change Order and the provisions of the Contract, the provisions of this Change Order will prevail.

IN WITNESS WHEREOF the parties have executed this Change Order as of the last date signed below.

Motorola Solutions, Inc. Customer
By: By:

Printed Name: Printed Name:

Title: Title:

Date: Date:

Reviewed by: Cheri Lynn Eklund Date: 11/10/21
Motorola Solutions Project Manager
Kent Martin
Regional Services Manager
November 12, 2021