ITEM
NO. ITEM DESCRIPTION BID

QTY UNIT UNIT PRICE TOTAL
1 Mobilization, submittals, bonds, licenses, permits, fees, and insurance (maximum of 4% of total bid amount) 1 LS 14,000.00 $ $ 14,000.00 2 Temporary facilities, temporary power, and protection of the work 1 LS 5,000.00 $ $ 5,000.00
3 Excavation and backfill of all tank basis and all other miscellaneous earthwork 1 LS 6,400.00 $ $ 6,400.00
4 Disposal of excess earthwork materials on site 1 LS $ 600.00 $ 600.00 5 Removal and reuse of existing rock surfacing at both tank locations 1 LS 1,400.00 $ $ 1,400.00
6 Installation of Concrete Tank Bases 2 EA 12,100.00 $ $ 24,200.00 7 Installation of Concrete Pump Bases (See Note 1 ) 2 EA 2,000.00 $ $ 4,000.00 8 Installation and repair of all other miscellaneous concrete 1 LS $ 4,000.00 $ 4,000.00 9 Installation of PVC piping, valves, and supports at all locations 1 LS 13,600.00 $ $ 13,600.00
10 Installation of PVC carrier pipe, tubing, and supports at all locations 1 LS 48,100.00 $ $ 48,100.00
11 Installation of Owner supplied tanks and seismic restraints 2 EA 3,000.00 $ $ 6,000.00 12 Installation fo Owner supplied pumps and VFDs 2 EA 5,000.00 $ $ 10,000.00 13 Installation of all tank level instruments 2 EA $ 500.00 $ 1,000.00 14 Installation of all electrical conduit, pull boxes, and supports 1 LS 70,000.00 $ $ 70,000.00
15 Installation of all electrical wiring, terminations, and labeling 1 LS 12,000.00 $ $ 12,000.00
16 Installation of Contractor provided control panels and installation of Owner supplied VFDs in the control panels (See Note 2 )
2 EA 31,000.00 $ $ 62,000.00
17 All Networking, PLC, and SCADA Programming
Modifications 1 LS 30,000.00 $ $ 30,000.00
18 Preparation of interconnects and loop drawings, and Asbuilt drawings for all new work 1 LS 21,000.00 $ $ 21,000.00 19 Mechanical equipment testing and startup 1 LS 3,000.00 $ $ 3,000.00 20 Electrical equipment testing, wire testing, and other specified tests for all new or midified equipment 1 LS 17,000.00 $ $ 17,000.00 21 Miscellaneous items specified or indicated elsewhere but not listed above 1 LS $ 100.00 $ 100.00
22 Demobilization, warranty paper work, and project closeout (minimum of 1%) 1 LS 3,700.00 $ $ 3,700.00
Note 1: Q & A No 4 clarified the previous quantity of 4 was to be crossed out and to use 2 Note 2: Q & A No 4 clarified that the unit should be EA not LS WQCF Glycerin System Project
Project Estimate: $ 300,000.00