City of Manteca Change Order Change Order - 05
Project Name: Senior Center Improvements - Phase 2 Approval Date:
Project Manager: Michael Rosales CIP/ Contract No: 18049/20012 Project JHK Construction, Inc. C2021-137
Contractor:
It is agreed to modify the Contract referred to above as follows:
CPR DESCRIPTION OF CHANGES CHANGE IN CHANGE IN
CONTRACT PRICE CONTRACT TIME
PCO Cost Change due to dry rot repairs to roof
20217-13 replacement and kitchen hood repairs
{ANSUL Svstem)
It is agreed to modify the Contract referred to above as follows:
a. Contract Amount + Approved Change Orders:
b. Net Increase (Decrease) of this Change Order:
$21,668.32
c. Revised Contract Amount + all Change Orders: (a +b = c) d. Contract Time (Final Completion) Prior to this Change Order (Calendar Da s) ✓ or Working Days
e. Net Increase (Decrease) of this Change Order:
f. Revised Contract Time with all Approved Changes
(Calendar Days) or (Working O s): (d + e = f)
30 days
$1,173,096.10
$21,668.32
$1,194,764.42
266
30 296 Calendar Days
cl in accordance with the terms, stipulations, and conditions of the original Date
Date
1 /1-0 /zo z.,,_
Date
Approved By: lnterm City Manager - Toni Lundgren Date
Attest City Clerk: Cassandra Candini-Tilton Date