ITEM
NO. ITEM DESCRIPTION BID

QTY UNIT UNIT PRICE TOTAL
1 Mobilization, submittals, bonds, licenses, permits, fees, and insurance (maximum of 4% of total bid amount) 1 LS 15,000.00 $ $ 15,000.00 2 Temporary facilities, temporary power, and protection of the work 1 LS 1,992.00 $ $ 1,992.00
3 Disposal of excess earthwork materials on site 1 LS 2,256.00 $ $ 2,256.00 4 Removal and reuse of existing rock surfacing at both tank locations 1 LS 31,552.00 $ $ 31,552.00
5 Installation and repair of all other miscellaneous concrete 1 LS 4,188.00 $ $ 4,188.00 6 Installation of all FW piping, hoses, valves, and supports at all locations 1 LS 164,450.00 $ $ 164,450.00
7 Installation of all other miscellaneous water, air and equipment piping, hose and supports at all locations 1 LS 13,748.00 $ $ 13,748.00 8 Installation of all conduit and electrical connections to all Owner supplied equipment , pumps, and electrical
instrument and devices.
1 LS 33,447.00 $ $ 33,447.00
9 Installation of all electrical conduit, pull boxes, and supports 1 LS 28,918.00 $ $ 28,918.00
10 Installation of all electrical wiring, terminations, and labeling 1 LS 53,410.00 $ 53,410.00 $
11 Preparation of interconnects and loop drawings, and Asbuilt drawings for all new work 1 LS 5,164.00 $ $ 5,164.00 12 Assistance with mechanical equipment testing and startup 1 LS 1,238.00 $ $ 1,238.00 13 Electrical equipment testing, wire testing, and other specified tests for all new or midified equipment 1 LS 22,131.00 $ $ 22,131.00 14 Miscellaneous items specified or indicated elsewhere but not listed above 1 LS 6,268.00 $ $ 6,268.00
15 Demobilization, warranty paper work, and project closeout (minimum of 1%) 1 LS 4,000.00 $ $ 4,000.00

PROJECT INITIATION
BID TOTAL $ 387,762.00
F2E/Food Waste Processing Facility
Project Estimate: $ 300,000.00
October 20, 2022
TNT Industrial Contractors, Inc. - Sacramento, CA
ATTACHMENT 2