Manteca City Council – September 2023
Valley Rail Improvements
Manteca/Lathrop
Manteca City Council - September 2023
Stacey Mortensen – Executive Director
ATTACHMENT 1
Manteca City Council – September 2023
Content Overview
• Valley Rail Service Implementation
• Improvements in the Manteca/Lathrop Area
• Manteca Station
• Lathrop Wye and Track Extension
• North Lathrop Transfer Station
• Status of Project Delivery
2 ATTACHMENT 1
Manteca City Council – September 2023
Valley Rail Program Overview
• Valley Rail Program includes
expansion of both ACE and the
San Joaquins Services
• Valley Rail has received about
$1.6 billion in state and other
funding sources
3 ATTACHMENT 1
Manteca City Council – September 2023
Lathrop – Merced Expansion
(UP Fresno Subdivision)
4 ATTACHMENT 1
Manteca City Council – September 2023
Stockton – Sacramento Extension
(UP Sacramento Subdivision)
• Service to Sacramento Valley
Station via current route is capped
by UP
• UPRR Sacramento Subdivision will
support additional San Joaquins
service and new ACE service.
• Working with Butte CAG and
SACOG to plan for further
extension north to Marysville/Yuba
City and Butte County
5 ATTACHMENT 1
Manteca City Council – September 2023
End of 2026
• New Stations Opening:
• Natomas
• Midtown
• Elk Grove
• Downtown Manteca
• Modesto
• Ceres
• Madera
• Oakley
• 1 New ACE Round-Trip Ceres to San Jose
• 1 Existing ACE Round-Trip Extended to Natomas
• Midtown, and Madera will be ready in 2025,
but due to endpoint layover needs, service will begin in late 2026 when Natomas and Ceres are completed.
6 ATTACHMENT 1
Manteca City Council – September 2023
End of 2027
• New Stations Opening:
• North Lathrop Transfer Station
• Lodi
• Ripon
• Stockton Diamond Grade Separation Completed
• 2 New ACE Round-Trips Ceres to Natomas with ability to transfer to/from San Jose at North Lathrop Transfer Station • 1 New intercity Round-Trip Stockton to/from Natomas
• Assumes funding is secured for Tuolumne
and Stanislaus River Bridges
7 ATTACHMENT 1
Manteca City Council – September 2023
2029
• New Stations Opening:
• Old North Sacramento*
• City College
• Turlock
• 1 New San Joaquins Round-Trip Fresno to/from Natomas
• 1 New San Joaquins Round-Trip Stockton to/from Natomas • Ceres – Turlock Extension
• *Subject to City of Sacramento
Redevelopment Study
8 ATTACHMENT 1
Manteca City Council – September 2023
High-Speed Rail Planning Horizon
2030-2033
• New Stations Opening:
• Livingston
• Atwater*
• Merced (new)
• Extensions Opening:
• Union City
• North Valley Extension
• Service optimized to meet HSR.
• *Subject to Local Funding
9 ATTACHMENT 1
Manteca City Council – September 2023
Manteca Station
10 • Location is adjacent to Manteca
Transit Center
• Potential for phased/split bid
construction of the parking,
platform and overcrossing
Background
Scope
• Center loaded platform with
pedestrian overcrossing
• Protect in place for existing gas
line
• No specific track construction,
close coordination with track
construction
• Range: $25M+
• Duration: 22 months
ATTACHMENT 1
Manteca City Council – September 2023
Manteca Station
11 • Final Plans and Specs: 04/2024
• Bid Document Release: 04/2024
• Pre-Bid Meeting: 04/2024
• Bids Due: 05/2024
• Contract Award: 07/2024
• NTP: 07/2024
• Construction Complete:05/2026
• Phased/split bid construction
of the parking, platform and
overcrossing
• PG&E Gas line protected in
place
• Protection of transit facility
operations
Schedule Potential Construction Challenges
ATTACHMENT 1
Manteca City Council – September 2023
Lathrop Wye and Track Ext.
12 • Located in Manteca and Lathrop
• Coordination with SSJID
• Potential for split/phased
construction
Background
Scope
• Double Cell Box Culvert at SSJID
• Trackwork from Lathrop through
Manteca Station
• Coordination with SSJID
• Multiple at-grade crossings
• Range: $36M+ (including UP)
• Duration: 19 months
Lathrop/Manteca
Station
Manteca Station
ATTACHMENT 1
Manteca City Council – September 2023
Lathrop Wye and Track Ext.
13 • Final Plans and Specs: 08/2024
• Bid Document Release: 09/2024
• Pre-Bid Meeting: 09/2024
• Bids Due: 10/2024
• Contract Award: 11/2024
• NTP: 12/2024
• Construction Complete: 07/2026
• Environmental Permitting
• Work Windows
• Phase construction of atgrade crossings
Schedule Potential Construction Challenges
ATTACHMENT 1
Manteca City Council – September 2023
North Lathrop Transfer Station
14 • Major transfer location for
passengers
• Key station for Valley Rail
• Located at Sharpe Army Depot
Background
Scope
• Center loaded platform with long
pedestrian overcrossing
• Parking lot
• Intersection improvements at
Lathrop Road
• Coordination with Port/Sharpe
• Range: $30M+ (including UP)
• Duration: 23 months
ATTACHMENT 1
Manteca City Council – September 2023
North Lathrop Transfer Station
15 • Final Plans and Specs: 08/2025
• Bid Document Release: 08/2025
• Pre-Bid Meeting: 09/2025
• Bids Due: 10/2025
• Contract Award: 12/2025
• NTP: 01/2026
• Construction Complete: 11/2027
• Working on the Sharpe Army
Depot property
• SSJID culvert extension
• Potential environmental
permitting
Schedule Potential Construction Challenges
ATTACHMENT 1
16 Manteca City Council – September 2023
Questions/Comments?