AGREEMENT BETWEEN THE CITY OF MANTECA AND
STANTEC CONSULTING SERVICES, INC. FOR A WASTEWATER AIASTER PLAN

AND SENVER RATE STUDY PROJECT
This Agreement is made and entered into this IS1 day of p QPf 2021, by and between the CITY OF MANTECA, a public body, corporate and politic (" the City") and Stantec Consulting Services Incorporated, a California corporation (" Consultant").

RECITALS
A. Consultant is specially trained, experienced, and competent to perform the professional services required by this Agreement.

B. Consultant possesses the skill, experience, ability, background, certification, and knowledge to provide the services described in this Agreement on the terms and conditions specified herein.

C. City desires to retain Consultant to render the professional services set forth in this Agreement.

AGREEMENT

1. Scope of Services. Consultant shall perform the Scope of Work for the Wastewater Master Plan and Sewer Rate Study Project (" Project") as described in Attachment 1 in accordance with the Proposal submitted by Consultant as dated September 20, 2021, and attached hereto as Attachment 2, both of which are incorporated by reference as if set forth in full. Consultant shall provide these services at the time, place, and in the manner specified in Attachment 1, subject to the direction of the City through its staff as may be provided from time to time.

2. Work Through City Staff. Consultant shall perform services under this Agreement solely at the direction of City staff. No communications, information, or documentation shall be made directly to any applicant to the City without the prior written consent of the City. This shall not apply to the sole request of information or clarification of information by Consultant from the applicant. All requests shall be noted to City in an expeditious manner.

3. Time of Performance. Consultant' s services will commence upon execution of this Agreement and shall be completed in accordance with the Schedule of Activities, attached hereto as Attachment 3, which is incorporated herein by reference as if set forth in full. All work shall be completed no later than April 30, 2024. Failure to submit work products in accordance with the Schedule of Activities may result in the City withholding progress payments. Repeated failure to complete work products in accordance with the Schedule of Activities may result in a reduction of the total compensation provided for in Section 4 herein.

4. Compensation. Without additional authorization from the City, compensation to be paid to the Consultant shall not exceed one million, forty- eight thousand DOLLARS 1, 048, 000) unless otherwise permitted herein. If additional professional services are required Exhibit "B" ATTACHMENT 3
from the City to meet the objective and needs ofthe Project, the Consultant may receive an additional amount not to exceed one- hundred and fifty thousand DOLLARS ($ 150, 000). Claims for reimbursement of additional costs shall be submitted by the Consultant in writing and approved by City staff prior to the Consultant starting the additional work. Consultant shall not be entitled to compensation for additional work performed prior to receipt of approval by City staff. Finally, payment by the City under this Agreement shall not be deemed a waiver of any defects, even ifthose defects were known to the City at the time of payment.

5. Method of Payment. Consultant shall submit monthly billings to City specifying and describing the work performed during the preceding month. Consultant' s bills shall include a brief description of the services performed, the date the services were performed, the number of hours expended, and by whom, and a description of any reimbursable expenditures. Full payment of each task will only be made at such time as each task is completed.

City shall pay Consultant no later than 30 days after approval of the monthly invoice by City staff. Payments may be delayed by City if Consultant fails to provide services in accordance with the Schedule of Activities, unless the City has provided prior written consent to any delay in or amendment to the schedule.

6. Extra Work. At any time during the term of this Agreement, City may request that Consultant perform Extra Work. As used herein, the term " Extra Work" means any work that is determined by City to be necessary for the proper completion of the Project, but which the parties did not reasonably anticipate would be necessary at the time of execution of this Agreement. Consultant shall not perform, nor be compensated for, Extra Work without the City' s prior written authorization.

7. Termination. This Agreement may be terminated by the City immediately for cause, or by either party without cause, upon 15 days' prior written notice of termination. Upon termination, Consultant shall be entitled to compensation for services satisfactorily performed up to the effective date of termination upon submittal of an invoice for same.

8. Ownership of Documents; Confidentiality.

A. All plans, studies, documents, and other writings prepared by and for Consultant, its officers, employees, agents, and subcontractors in the course of implementing this Agreement, except working notes and internal documents, shall become the property of City upon payment to Consultant for such work. City shall have the sole right to use such materials in its discretion without further compensation to Consultant or to any other party. Consultant shall, at Consultant's expense, provide such reports, plans, studies, documents and other writings to City upon written request by City. Consultant shall not be responsible for any unauthorized modification or use of such information for other than its intended purpose.

B. All memoranda, specifications, plans, procedures, drawings, descriptions, computer program data, input record data, written information, and other documents and data, either created by or provided to Consultant in connection with the performance of this Agreement, shall be held confidential by Consultant. These materials shall not, without the City' s prior written consent, be used by Consultant for any purposes other than the performance 2 of 94
Exhibit "B" ATTACHMENT 3
of the services under this Agreement. Nor shall these materials be disclosed to any person or entity not connected with the performance of services under this Agreement. Nothing furnished to Consultant that is otherwise known to Consultant, or is generally known, or has become known to the related profession shall be deemed confidential. Consultant shall not use City' s name or insignia, photographs relating to the Project for which Consultant' s services are rendered, or any publicity pertaining to the Consultant's services under this Agreement in any magazine, trade paper, newspaper, television or radio production, or other similar medium without the City' s prior written consent.

9. Consultant' s Books and Records.

A. Consultant shall maintain all ledgers, books of account, invoices, vouchers, canceled checks, and other records or documents evidencing or relating to charges for services, or expenditures and disbursements charged to City, for a minimum period of three years, or for any longer period required by law, from the date of final payment to Consultant under this Agreement.

B. Consultant shall maintain all records that document performance under this Agreement for a minimum period of three years, or for any longer period required by law, from the date of termination or completion of this Agreement.

C. Any records or documents required to be maintained pursuant to this Agreement shall be made available for inspection or audit at any time during regular business hours, upon written request by the City Manager, City Attorney, City Auditor, or a designated representative of any of these officers. Copies of such documents shall be provided to City for inspection at City Hall when it is practical to do so. Otherwise, unless an alternative is mutually agreed upon, the records shall be available at Consultant' s address specified in Section 16 of this Agreement.

D. Where City has reason to believe that records or documents may be lost or discarded due to the dissolution or termination of Consultant' s business, City may, by written request, require that custody of the records be given to the City and that the records and documents be maintained in City Hall. Access to these records and documents shall be granted to any party authorized by Consultant, Consultant's representatives, or Consultant's successor-ininterest.

10. Independent Contractor. In the performance of the work and services required by this Agreement, Consultant shall act as and be an independent contractor and not an agent, or employee of the City. Consultant shall obtain no rights to retirement or other benefits that accrue to City's employees, and Consultant expressly waives any claim it may have to any such rights.

11. Interest of Consultant.

A. Consultant represents that neither it nor any employee has any investment or interest in real property, and shall not acquire any such interest, direct or indirect, within the area covered by this Agreement, or any other source of income, interest in real property, or investment that would be affected in any manner or degree by the performance of Consultant' s 3 of 94
Exhibit "B" ATTACHMENT 3
services hereunder. Consultant further represents that, in the performance of its duties hereunder, no person having any such interest shall perform any services under this Agreement.

B. Consultant is not a designated employee within the meaning of the Political Reform Act because Consultant:
1) will conduct research and arrive at conclusions with respect to its rendition of information, advice, recommendation, or counsel independent of the control and direction of the City, or of any City official, other than normal Agreement monitoring; and
2) possesses no authority with respect to any City decision beyond the rendition of information, advice, recommendation, or counsel.

FPPC Reg. 18700( a)( 2).)

12. Professional Ability of Consultant.

A. City is relying upon the professional training and ability of Consultant to perform the services hereunder as a material inducement to enter into this Agreement.

Consultant shall therefore provide skilled professional and technical personnel to perform all services under this Agreement. All work performed by Consultant shall be in accordance with applicable legal requirements and shall meet the standard of quality ordinarily to be expected of competent professionals in Consultant' s field of expertise.

B. The primary provider of the services required by this Agreement shall be Stantec Consulting Services Incorporated. A list of other individuals assigned to the Project will be provided to City for its review and approval, and these individuals shall not be replaced without the City' s prior written consent.

13. Compliance with Laws. Consultant shall use the customary standard of care in its profession to comply with all applicable federal, state, and local statutes, codes, ordinances, and regulations.

14. Licenses. Consultant represents and warrants to City that it has all licenses, permits, qualifications, insurance, and approvals that are legally required of Consultant to practice its profession. Consultant represents and warrants to City that Consultant shall, at its sole cost and expense, keep in effect or obtain at all times during the term of this Agreement, any licenses, permits, insurance, and approvals that are legally required of Consultant to practice its profession.

15. Indemnification and Hold Harmless. Consultant agrees to defend, indemnify, and hold harmless the City, its officers, officials, agents, employees, and volunteers, from and against any and all claims, demands, actions, losses, damages, injuries, and liability, direct or indirect including any and all costs and expenses in connection therewith), arising out of Consultant' s performance of this Agreement, or Consultant' s failure to comply with any of its obligations contained in this Agreement; excluding, however, any claim arising out of the active negligence or willful misconduct of the City, its officers, agents, employees, or volunteers or any claims 4 of 94
Exhibit "B" ATTACHMENT 3
challenging utility rates implemented by the City as a result of Consultant' s performance of the services hereunder.

16. Insurance Requirements.

A. Job specific insurance requirements can be found on the attached Attachment 4, which is incorporated herein by reference as if set forth in full. Other insurance provisions can be found below:

B. Endorsements. Each general liability and automobile liability insurance policy shall be with insurers possessing an A.M. Best' s rating of no less than ANII and shall be endorsed with language substantially as follows:
1) The City, its elected and appointed officers, officials, employees, agents and volunteers are to be covered as additional insureds with respect to liability arising out of work performed by or on behalf of the Consultant, including materials, parts, or equipment furnished in connection with such work.
2) The policy shall be considered primary insurance as respects the City, its elected and appointed officers, officials, employees, agents and volunteers. Any insurance maintained by the City, including any self-insured retention the City may have, shall be considered excess insurance only and shall not contribute with it. 3) The insurance shall apply to each insured and additional insured as though a separate policy had been written for each, except with respect to the limits of liability of the insuring company. 4) The insurer waives all rights of subrogation against the City, its elected and appointed officers, officials, employees, and agents. 5) Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the City, its elected and appointed officers, officials, employees, agents, or volunteers. 6) The insurance provided by the policy shall not be suspended, voided, canceled, or reduced in coverage or in limits except after 30 days written notice has been received by the City.
7) The City will not accept any endorsements that were issued in 2004. Acceptable endorsement forms are CG 20 10 11 85 or both CG20101001 and CG2037 1001.

C. Deductibles and Self-Insured Retentions. Any deductibles or self-insured retentions must be declared to and approved by the City. At the City's option, Consultant shall demonstrate financial capability for payment of those deductibles or self-insured retentions. 5 of 94
Exhibit "B" ATTACHMENT 3
D. Certificates of Insurance. Consultant shall provide to City certificates of insurance with original endorsements as evidence of the required insurance coverage.

Certificates of insurance shall be filed with the City on or before commencement of performance of this Agreement. Current certification of insurance shall be kept on file with the City at all times during the term ofthis Agreement.

17. Notices. Any notice required to be given under this Agreement shall be in writing and either served personally or sent prepaid, first class mail. Any such notice shall be addressed to the other party at the address set forth below. Notice shall be deemed communicated within 48 hours from the time of mailing if mailed as provided in this section.

If to City: City of Manteca
1001 W. Center Street
Manteca, CA 95337
Attention: Elba Mijango, Associate Engineer
If to Consultant: Stantec Consulting Services Incorporated 3875 Atherton Road
Rocklin, CA 95765
Attention: Steven L. Beck, Project Manager

18. Entire Agreement. This Agreement constitutes the complete and exclusive statement of Agreement between the City and Consultant. All prior written and oral communications, including correspondence, drafts, memoranda, and representations, are superseded in their entirety by this Agreement.

19. Amendments. This Agreement may be amended only by a written document executed by both Consultant and City and approved as to form by the City Attorney.

20. Assignment and Subcontracting. The parties recognize that a substantial inducement to City for entering into this Agreement is the professional reputation, experience, and competence of Consultant. Assignments of any or all rights, duties, or obligations of the Consultant under this Agreement will be permitted only with the express written consent of the City. Consultant shall not subcontract any portion of the work to be performed under this Agreement without the written authorization of the City. If City consents to such subcontract, Consultant shall be fully responsible to City for all acts or omissions of the subcontractor.

Nothing in this Agreement shall create any contractual relationship between City and subcontractor nor shall it create any obligation on the part of the City to pay any monies due to any such subcontractor other than as may be required by law.

21. Waiver. Waiver of any breach or default under this Agreement shall not constitute a continuing waiver of a subsequent breach or default of the same or any other provision under this Agreement.

22. Severability. If any provision of this Agreement is held to be invalid, illegal, or otherwise unenforceable by a court of competent jurisdiction, the remaining provisions of this Agreement shall continue in full force and effect.
6 of 94
Exhibit "B" ATTACHMENT 3

23. Controlling Law; Venue. This Agreement and all matters relating to it shall be governed by the laws of the State of California, and any legal action relating to this Agreement shall take place in the Superior Court, County of San Joaquin.

24. Litigation Expenses and Attorneys' Fees. If either party to this Agreement commences any legal action against the other party arising out of this Agreement, the prevailing party shall be entitled to recover its reasonable litigation expenses, including court costs, expert witness fees, discovery expenses, and attorneys' fees.

25. Mediation. The parties agree to make a good faith attempt to resolve any disputes arising out of this Agreement through mediation prior to commencing litigation. The parties shall mutually agree upon the mediator and shall divide the costs of mediation equally. If the parties are unable to agree upon a mediator, the dispute shall be submitted to JAMS/ ENDISPUTE (" JAMS") or its successor in interest. JAMS shall provide the parties with the names of five qualified mediators. Each party shall have the. option to strike two of the five mediators selected by JAMS, and thereafter the mediator remaining shall hear the dispute. If the dispute remains unresolved after mediation, either party may commence litigation.

26. Execution. This Agreement may be executed in several counterparts, each of which shall constitute one and the same instrument and shall become binding upon the parties when at least one copy has been signed by both parties.

27. Authority to Enter Agreement. Consultant warrants that it has all requisite power and authority to conduct its business and to execute, deliver, and perform this Agreement. Each party warrants to the other that the signatories to this Agreement have the legal power, right, and authority to enter into this Agreement and to bind each party.

28. Prohibited Interests.

A. Consultant warrants that it has not employed or retained any person, other than a bona fide employee working solely for Consultant, to solicit or secure this Agreement.

Further, Consultant warrants that it has neither paid nor agreed to pay any person, other than a bona fide employee working solely for Consultant, any fee, commission, percentage, brokerage fee, gift, or other consideration contingent upon or resulting from the award or making of this Agreement. For any breach or violation of this warranty, City shall have the right to rescind this Agreement without liability.

B. For the term of this Agreement, no member, officer, or employee of City, during the period of his or her service with City, shall have any direct interest in this Agreement, or obtain any present or anticipated material benefit arising therefrom.

29. Equal Opportunity Employment. Consultant represents that it is an equal opportunity employer, and it shall not discriminate against any subcontractor, employee, or applicant for employment because of race, religion, color, national origin, handicap, ancestry, sex, or age. Such non- discrimination shall include, but not be limited to, all activities related to initial employment, upgrading, demotion, transfer, recruitment or recruitment advertising, layoff or termination.
7 of 94
Exhibit "B" ATTACHMENT 3

30. Precedence. In case of conflict between the Consultant' s Proposal or attachments and the City' s Agreement or attachments, the City' s Agreement and attachments shall take precedence over the Consultant' s proposal or attachments.

This Space Purposely Left Blank
8 of 94
Exhibit "B" ATTACHMENT 3
TO EFFECTUATE THIS AGREEMENT, each of the parties has caused this Agreement to be executed by its duly authorized representative as of the date set forth in the introductory paragraph on page 1 above.

CITY OF MANTECA: STANTEC CONSULTING SERVICES, INC.:

C Corporation
Toby Wells, VIE Form oforganization)
City Manager
ATTEST: By:

Signatztre)
Steven L. Beck, Senior Principal
Cass d Candini- Tilton, Type name and title)
Director of Legislative Services
COUNTERSIGNED: By:

AAA,
Signature)
Y- t—
Jared qsen, Type name and title)
Acting Director of Finance
COUNTERSIGNED: Address: 3875 Atherton Road
l
I Rocklin, CA 95765
on Sl ter,
Director of Employee Services&
Engagement Telephone: ( 916) 773- 8100
APPR70VI AS TO FORT
Carry Valoo11eCity Attorney
9 of 94
Exhibit "B" ATTACHMENT 3
ATTACHMENT 1

REQUEST FOR PROPOSAL
10 of 94
Exhibit "B" ATTACHMENT 3
Wastewater Master Plan &
Sewer Rate Study
Request for Proposals
j E C A, cq!
z
thefenulyciiy
2c
R
R9TED MAC 26,
Issued: August 12, 2021
Electronic Proposals are Due: September 13, 2021, 5: 00 PM PST 11 of 94
Exhibit "B" ATTACHMENT 3
1 Introduction
The City of Manteca ( City) is soliciting ELECTRONIC REQUEST FOR PROPOSALS ( RFPs) from professional consulting firms to prepare the City' s Wastewater Master Plan, Sewer Rate Study, and related studies.

Refer to Table 1 for RFP deadlines.

The City is requesting proposals from qualified consultants to develop the City' s Wastewater Master Plan, Sewer Rate Study and additional work( Project) as indicated in the Scope of Services Section. A major focus of this Wastewater Master Plan and Sewer Rate Study is to determine the sustainability of the City' s capability and capacity to treat incoming wastewater flows. The goal is to provide approaches and strategies that provides long- term reliability ( 50 years and beyond) and shields the City, to the extent possible, from regulations, drought conditions, and increased labor, material, and construction costs.

Firms submitting proposals for this project must have a project manager licensed as a Professional Engineer in the State of California and have experience in the field of sewer rates, sewer system, treatment, operation, and maintenance of municipal sewer systems. The work is broken down into three main tasks: ( 1) Interim Sewer Rate Study( 2) Final Sewer Rate Study and ( 3) Wastewater Master Plan.

Primary objectives of the Final Sewer Rate Study include the following:

Overall system design that balances sustainability and resiliency; Generates sufficient revenue to meet current and future operating costs, debt obligations, and capital program needs factoring in infrastructure condition and the feasibility and timing of receiving grants;
Meets cost of service standards for fair, equitable, and reasonable rates and fees; and Strategizes rate increases during the planning period.

The main objectives of the Wastewater Master Plan include:

Operation of a sewer system that is sustainable, reliable, and efficient; Improve resiliency and minimize the effects of outside forces such as drought, changing regulatory requirements, and increasing maintenance and operations costs; Strategize planning and budgeting efforts to implement sewer system enhancements; Maintain a high level of system reliability and efficiency for current and future demands during normal, drought, and emergency situations;
Development of the City' s sewer system hydraulic model from the pipe network design selected that incorporates phasing of capital projects- the City does not have a working model and a new model would need to be created as part of the scope of work included in this RFP; and Development of a Capital Improvement Program ( CIP) and implementation schedule based on sewer capacity and condition of assets.

Proposals shall be concise, well organized, and demonstrate the consultants qualifications and experience relating to the proposed prcjcc minm,u
proposals shall include the information in the
following sections.
12 of 94
Exhibit "B" ATTACHMENT 3

1. 1 Project Timeline
The timeline below provides an approximation of time needed to complete key projects tasks. The timeline may change based on project needs.

Interim Rate Study: 10 months from Notice to Proceed ( NTP) Draft Wastewater Master Plan: 14 months from NTP
Final Rate Study: 18 months from NTP
Final Wastewater Master Plan and EIR: 26 months from NTP

1. 2 RFP and Agreement Timeline
Time is of the essence with respect to this contract. Please refer to Table 1 for deadlines. The successful proposer should be able to perform all required tasks set forth in the Scope of Services section.

Table 1: RFP Deadlines
Milestone Deadline
RFP Issued August 12, 2021
Deadline for Clarifications/ Inquiries September 2, 2021- S: OOPM PST Deadline for Proposal Submittal September 13, 2021- 5: 00 PM PST Interviews ( tentative)
September 21- 22, 2021
from: 8: 00 am to 12: 30 pm
Award of Contract( tentative) Week of October 5tn
Issue Notice to Proceed ( tentative) Week of October 11tn PST: Pacific Standard Time
Proposals received past the deadline will not be considered. The City accepts no responsibility if delivery is made to another electronic mail address or other technological issues that cause a submittal to be late or not received by the deadline. An evaluation team will review submitted proposals and select the best proposal based on the evaluation criteria outlined in the RFP. The selected consultant will then be recommended to the City Council for entering into a contractual agreement for services. A free electronic copy of the RFP can be obtained by going to the City' s website via the link below.

Link to this RFP: https:// www. ci. manteca. ca. us/ Pages/ RequestForProposal. aspx 2 Background
The City provides sewer service to residents within the City limits and provides treatment at the City' s Wastewater Quality Control Facility( WQCF). The City is located approximately 15 miles north of Modesto and 10 miles south of Stockton. The Un'`on_F' acific_Railroad runs diagonally from southeast to northwest through the City. State Highway 120 crosses the southern portion of the City and provides a connection between Interstate 5, located about fou miles tohe wes- of-the City, and Highway 99 along the eastern boundary of the City. t7
13 of 94
Exhibit "B" ATTACHMENT 3
The City' s current sewer service area coincides with the current City boundary. In 2020 the estimated population of the City was 84, 400, according to population data published by the California Department of Finance ( DOF).

The WQCF is located southwest of downtown Manteca on 22- acres owned by the City. The WQCF treats municipal wastewater from the City of Manteca and the City of Lathrop, and seasonally accepts industrial food processing waste effluent from Eckert Cold Storage. Per contractual agreement, 8. 42 mgd of plant capacity is allocated to the City of Manteca and 1. 45 mgd is allocated to the City of Lathrop.

The City' s current National Pollution Discharge Elimination System ( NPDES) Permit, which regulates the wastewater effluent quantity and quality upon discharge, was issued by the Central Valley Regional Water Quality Control Board and is Order 115- 2021- 0003 NPDES No. CA0081558.

The WQCF treats an average dry weather flow( ADWF) of about 7. 6 mgd and hads an original average dry weather design capacity of 9. 87 mgd. However, historic water use reductions in the community combined with population growth have drastically increased the concentration of biological oxygen demand ( BOD) and total Kjeldahl nitrogen ( TKN) in the influent wastewater. This essentially makes the incoming wastewater higher strength and makes the overall biological and nitrogen loading on the plant higher.

The City' s sewer service area is contiguous with City limits, and is divided into north, south and central sewer sheds. The municipal wastewater collection system includes 242 miles of sewer mains and 19 pump stations. The collection system includes gravity flow pipes ranging from 6- inch to 60- inch diameter, and force mains from 6- inch to 24- inch diameter.

The existing collection system generally serves the developed portions of the City, with major trunk sewers located in the core of the City ( the central sewer shed), approximately bounded by State Route 120 to the south, Austin Road to the east, Lathrop Road to the north, and Airport Way to the west.

Table 2 list links to documents referenced in this RFP and other useful resources.

Table 2: Links to Reference Documents and City Resources Document/ Resource Link
0- WWMP2021- RFP Wastewater Master
Plan& Sewer Rate Study( this document)
1— WWMP2021- Sewer Rate Study, 2008
2- WWMP2021— Sewer Monthly Rates
3- WWMP2021- 2012 Wastewater https:// www. ci. manteca. ca. us/ Pages/ RequestForProposal. aspx Collection System Master Plan Update,
2013
4- WWMP2021- WQCF Phase III Expansion
Project, 2001 F=: l
5- WWMP2021— Final Environmental
Impact Report for the City of Manteca
14of94
Exhibit "B" ATTACHMENT 3
WQCF and Collection System Master Plans
Update Project
6— WWMP2021— NPDES Permit
GIs Online Access
https:// datamanteca. opendata. arcgis. com/ datasets/ 3478489d5320463lb7909d7dle65c5O4 9 General Plan Update https:// manteca. generalplan. org/ City of Manteca Municipal Code https:// www, ci. manteca. ca. us/ CityClerk/ Pages/ Municipal- Code. aspx This Wastewater Master Plan and Sewer Rate Study will include analyzing full build- out of development per the most recent version of the City' s General Plan ( which is anticipated to be approved prior to the approval of the new Wastewater Master Plan). The draft General Plan is available online; please refer to the link below.

General Plan Update link: https: Hmanteca. generalplan. org/ 3 Proposal Submission and Format
Proposers must submit a Work Proposal and Cost Proposal via email. All responses must be completed as required, signed by an officer of the firm who is authorized to enter into a binding agreement with the City on behalf of the company ( proof of signature authority must be attached), and must be received in the place and time designated in Table 1.

Proposal packages are to be submitted to: emiiango@ci. manteca. ca. us Submittals or inquiries sent to other emails will not be accepted. 4 Work Proposal

4. 1 Work Proposal
All proposals shall have a 26- page ( one- sided page) limit. The proposal, resumes, and project schedule shall all be included within the page limit. The cover letter shall consist of maximum two ( 2) pages and include the following:
a. The proposer' s legal name, add ress,- teIeph_one, number, email address, and contact person for the remainder of the selection proce s,
b. An qualifying statements or comentsLe17l ` the ro oser' s submittal, includin roof of prposer' s capabilities to prepare a Waltter Master Plan and Sewer Rate Study; g p
c. Statement indicating the validity of the proposal for a minimum period of 120 calendar days subsequent to the proposal due date; and
15 of 94
Exhibit "B" ATTACHMENT 3
d. Resumes provided for each staff member shall be one page long at most. Resumes shall indicate college education, degrees earned, year licensing was obtained, and relevant project experience.

4. 2 Organization g Credentials Background g
a. Number of years in business preparing Wastewater Master Plans and Sewer Rate Studies for municipal clients and Sewer agencies;
b. Type of organization ( partnership, corporation, etc.); c. Location of the office that will support your project team and perform the work. The individuals identified in the proposal shall be the same individuals that must complete the project work and meet/ communicate with City staff on an on- going, consistent, and regular basis. The City shall be notified in writing of any change in staff members at minimum 30- days in advance. Changes is staff will need to be approved in writing by the City. This applies to all staff including staff from other firms; and
d. Count and description of personnel resources within the firm, including, but not limited to, inhouse professional disciplines of the firm.

4. 3 Experience
Relevant experience with the preparation of Wastewater Master Plans and Sewer Rate Studies for municipalities and sewer districts is required. A minimum of five references of existing and past municipal and sewer district clients with emphasis given to work completed within the last five years. Experience shall also include sewer modeling. Please provide the following:
a. Project name/ location
b. Project Manager name
c. Completion date or current status
d. Client name and client representative with telephone number and e- mail address e. Description of project
f. Original project budget and final cost
g. Original project duration and final project duration h. If project team includes a prime consultant and sub- consultants, provide detail regarding the role of the consultant and sub- consultants. Provide details of prior work together on the preparation of Wastewater Master Plans and Sewer Rate Studies for other clients. Referenced work shall include information listed above.

4. 4 Project Team

4.4. 1 Lead Firm
Clearly identify the lead firm noting the following items:, J
A. The lead firm shall oversee the ro' e ct b e r ns'ibblfr the successful completion of the work and coordinate the work of all itssub- onl ltants
B. The lead firm must provide information that demonstrates its experience as a prime or major subconsultant on projects of similar type, size, and complexity as the project under consideration. 16 of 94
Exhibit "B" ATTACHMENT 3
C. Firm completing hydraulic model should provide at least three project references with the following minimum requirements:
i. Utilized hydrologic and hydraulic modeling, with emphasis on sewer systems; ii. Included use of a fully dynamic hydraulic model calibrated to flow monitoring data; iii. Have a minimum fee of$ 200, 000 for each referenced project; and iv. Have occurred within the past five years.

D. The lead firm shall indicate the relevance of the projects to this proposed scope of work, and emphasize the experience of the specific individuals proposed to do the work. The lead firm shall specify which projects, if any, are due to regulatory requirements, in particular consent decrees.

The project team shall include, though is not limited to, the appropriate personnel capable of performing all required project tasks, including management, technical leads and support, appropriate oversight and review, and technical editing and publishing.

E. The Lead Firm shall possess all permits, licenses, and professional credentials necessary to perform services as specified under this RFP.

4. 4. 2 Project Manager
Identify the Project Manager, which will be the primary client contact, that will be responsible for the management of the project( through the duration of the entire project), and for ensuring that the project performs within the agreed- upon scope, schedule, and budget. Information regarding the Project Manager' s qualifications and experience ( both technical and managerial) shall be provided as indicated below.

A. Project Manager shall conduct presentation during interview by City staff.

B. The Project Manager must have demonstrated strong project management and organization skills, contract management abilities, and effective communication and interpersonal skills.

C. The Project Manager must meet the minimum qualifications, as follows:
i. An employee of the lead firm; and
ii. A minimum of 10 years of relevant experience with the preparation of wastewater master plans and hydraulic studies and modeling.

4.4. 3 Project Team
Only personnel that will work on the project ( through the duration of the project) shall be identified in the proposal. Changes to the project team shall be approved by the City. a. The project team may consist of staff from the lead firm and from other consulting firms with expertise in specific areas ( sub- consultants).
b. The proposal should clearly identify key personnel and Subject Matter Experts with workload information and commitments of availability to work on the project to ensure that all prescribed deadlines are met.
c. The project team should provide-at-least two-ref remprojects relating to dynamic hydrologic and hydraulic modeling of s e' yems, at minimum, with the following minimum requirements:

L At least three reference projects;
17 of 94
Exhibit "B" ATTACHMENT 3
ii. One project must be completed in the last 5 years, and one project must include the use of hydrologic and hydraulic sewer system modeling with continuous simulations over multiple storms events;
iii. At minimum, one Subject Matter Expert with at least five years of experience; iv. Have a minimum fee of$ 75, 000 for each referenced project; and V. Utilized hydrologic and hydraulic modeling, with emphasis on potable sewer systems. d. List of proposed team members with titles that are expected to be involved throughout the life of the project, including prime consultants and sub- consultants; e. Provide an organization chart of the proposed project staffing; and f. Provide resumes( one- page maximum per team member) and related experience of each member that will be involved, specifically addressing experience with preparation of Wastewater Master Plans and Sewer Rate Studies for municipalities and sewer district clients. Emphasis should be given to work completed for comparable municipalities and sewer districts within the last three years.

4. 5 Project Understanding and Approach
This section should demonstrate the proposer' s understanding of the Project and the services required under this RFP, how the work will be organized, and anticipated key issues to be addressed. This section should include:
a. Description of the proposer' s overall approach to the services required under the Scope of Services, such as an outline of a work plan that describes how the proposer will organize the services;
b. Proposed staffing plan/ organizational chart indicating anticipated work hours per week by classification both on and off-site. This should convey how proposer will provide public utility engineering and financial services in the most efficient, cost effective manner. Innovative staffing plans are encouraged based on best management practices and/ or methods utilized successfully by the firm in other municipalities and sewer districts; c. Description of those areas that the proposer is most likely to have challenges, and discuss means to resolve those conflicts or avoid them altogether;
d. Identify what the proposer feels are the key components to making the project successful; and e. Other information that will assist City in selecting the most qualified consultant.

4. 6 Hydraulic Model
Clearly identify the professional staff who would be assigned as the Project Manager, Lead Hydraulic Modeler, QA/ QC, and other key project personnel for this work. Include a Team Organization Chart that clearly indicates the role of each team member and the firm of each team member if sub- consultants are used. The proposal should summarize the_abilities,_qu fi--ations, and experience of these individuals, in addition to providing resumes.
18 of 94
Exhibit "B" ATTACHMENT 3

4. 7 Schedule of Work
The proposal shall include a schedule of work items on a task- by- task basis, including an estimated completion date for each task.

4. 8 Objections to Professional Services Agreement
Objections shall be submitted in writing with justification clearly stated. Any consultant with objections to terms contained in the City' s Agreement for Professional Services( see Attachment A) must advise the City of such objections and requested modifications as part of its proposal. Failure of a proposer to accept the terms of the City' s Agreement for Professional Services may result in the rejection of the proposal. It shall be the responsibility of the prospective consultants to review all sections and exhibits of the Agreement for Professional Services, including insurance requirements included as Attachment B. If no objections are received, the City will assume the proposer is able to and will enter into the Agreement for Professional Services and fulfill the terms and requirements set therein. The City may recover any damages accruing to the City as a result of the successful consultant' s failure or refusal to execute the City' s Agreement for Professional Services.
5 Scope of Services
The Scope of Services is comprised of the tasks detailed in the following sections.

5. 1 Task 1 - Kick- Off Meeting
The consultant shall attend a project kick- off conference call with the use of screen sharing capability with City staff to discuss project parameters, scheduling constraints, and other relevant information regarding services required by this RFP to prepare the Interim Rate Study, Wastewater Master Plan, Final Sewer Rate Study, and additional documents as outlined below. Consultant shall maintain a project schedule, which shall be updated, and submitted to the City at least once per month.

If in- person meetings or gatherings are needed, considerations for enhancing protection of individuals and preventing spread of coronavirus disease 2019 ( COVID- 19) will need to be implemented. City staff and consultant will coordinate and determine, whether and how to implement these considerations, making adjustments to meet the unique needs and circumstances of the local community. ZOOM or similar remote meeting applications may be used if in- person meetings are needed. In- person meetings or gatherings are not recommended given the COVID- 19 pandemic. City staff and consultant will coordinate the best use of remote meeting applications to encourage public participation.

The consultant shall prepare a detailed schedule of the project and identify completion dates for key milestones. The consultant is responsible!- for reviewing am becoming familiar with all pertinent data and requirements for completion of the IntenrnSewer ate%Study,-Wastewater Master Plan, Final Sewer Rate Study, and the other studies identified in'thisf FP U
19 of 94
Exhibit "B" ATTACHMENT 3

5. 2 Task 2 - Interim Sewer Rate Study
The focus of the Interim Sewer Rate Study is to provide an interim rate structure while the Wastewater Master Plan, Final Sewer Rate Study, and other studies are completed. The Interim Sewer Study shall include:

Current known capital and maintenance costs and other financial obligations to update the rates from 2013 rates to 2021 rates. The goal of the Interim study is to proactively bring rates up to realistic 2021 levels.

Analysis of accounting, past studies, projects, maintenance costs, and financial obligations to date to establish a base line of the City' s current finances; Develop interim capital plan to keep system functional and meet regulatory requirements until overall system design approach is approved, final rates are approved and updated capital plan is approved;
Determine short- term sewer rate structure that will enable the City to maintain system function and meet regulatory requirements;
Proposed rate structure will include separate billing components for operations, capital, and debt service, to be billed and accounted for in separate funds. Identify critical Capital Improvement Projects ( CIPS) scheduled through 2026;
Estimate funding needed for CIPS scheduled through 2026; Estimate funding needed for required city operations through 2026; Advise and manage on the Prop 218 rate increase process and present information as necessary to the Council and the Public meetings; and
Coordinate with Engineering, Finance,- and Public Works staff to ensure that the adopted rate is correctly loaded into the City' s utility billing software.

Public Outreach/ Proposition 218 Assistance
Develop and provide public outreach materials ( flyers, handouts, mailers, etc.) to communicate information and messaging to the public;
Provide assistance with Proposition 218 complaint public notifications.

5. 3 Task 3 - Final Sewer Rate Study
The Final Sewer Rate Study shall include the following items:

Long Range Financial Forecast
Develop pro-forma cash flow and budget projections for five-year period, July 1, 2022 through June 30, 2027. Work with City representatives to include relevant assumptions ( operational functions, etc.) in financial modelz odel casib low/ budgets at alternative rate increase levels.

Determine optimal funding ne ds for 0!peratio nS—and appropriate fund reserves, based on industry best practices and City polioe LI
20 of 94
Exhibit "B" ATTACHMENT 3
Rate Study
Review and analyze current wastewater flow rates, sewer fees, customer service levels( i. e. meter sizes) and operational activities/ expenses;
Evaluate the effects of water conservation measures and recent state legislation on Revenues; Conduct a comprehensive review of the City' s existing rate structure and if necessary, recommend improvements, including modifications that encourage conservation and/ or funding conservation programs;
Develop a cost of services study for City utility operations that comply with Proposition 218; Develop a consistent and objective fee structure that meets the needs of the City, customers and State guidelines;
Use the City' s overhead cost allocation plan and model to incorporate adequate overhead costs into the fee structure;
Review City documents and interview City staff members to document operations/ maintenance costs. Integrate these items into pro-forma budgets;
Develop a structure for fixed/ variable costs into base utility rates and consumption- based rates; Provide billing samples using proposed charges for each class and tier of customer noting the changes each class may expect;
Compare existing and proposed City rate structure to up to five ( 5) other public agencies, as determined by the City;
Provide potential implementation strategies to reduce adverse impacts on customer service levels/ groups.

Reports/ Public Meetings
Attend at least eight ( 8) public meetings, for the Interim and Final Sewer Rate Studies, including public workshops, to review rate study findings and rate alternatives, and assist with required Proposition 218 public meetings.

Public Outreach/ Proposition 218 Assistance
Develop and provide public outreach materials ( flyers, handouts, mailers, etc.) to communicate information and messaging to the public;
Provide assistance with Proposition 218 complaint public notifications.

The

5. 3. 1
scope
Update
of services
of Municipal
shall include
Code
an update
FF
of the applicable City of Manteca Municipal Code, Title 13 with emphasis on the chapters listed below. The consultant shall provide assistance with notification 21 of 94
Exhibit "B" ATTACHMENT 3
requirements for public review, and assistance through the adoption process at the City of Manteca Planning Commission and City Council.
a. Chapter 13. 12: Sewer Connection Charges
b. Chapter 13. 14: Sewer Capacity Charges
c. Chapter 13. 16: Sewer Service Charges
Link to the City of Manteca Municipal Code:
https:// www. ci. manteca. ca. us/ CityClerk/ Pages/ Municipal- Code. aspx

5. 4 Task 4 - Wastewater Master Plan
The Wastewater Master Plan shall be based on a 50- Year Planning Period to ensure for the City' s longterm sustainability, and keep up with demands from population growth and commercial/ industrial development. Wastewater Master Plan sections shall include, but not limited to the following sections, and include the subtasks detailed below.

Planning Service Area and Growth to ultimate buildout
Treatment Requirements and regulatory environment
Overall Collection System Design Evaluation
Recommend Collection System Improvements
Capital Improvement Plan
Hydraulic modeling of various phases to buildout of sewer system Financial plan including sewer rate study

1. Perform Data Collection and Review: The Consultant will review prior reports, studies and data related to the conduct of a typical wastewater system master plan. For this study, the Consultant shall also review appropriate flow information obtained from the City. This information and other information requested by the Consultant will be provided by the City, if available.

2. Review Past CIP Projects: Review and assess validity of past CIPs and incorporate with new CIPs from the updated analysis included in this RFP. The primary objective is to compile an updated CIP list.

3. Develop/ Conduct Flow Monitoring Program: The Consultant will develop a flow- monitoring program to develop various land use loading factors in support of calibrating the hydraulic model of the wastewater system. The Consultant will identify appropriate monitoring locations and carry out flow monitoring. It is expected that an analysis under wet and dry weather conditions will be performed by using this flow monitoring data and supplemented with available data from the City' s existing flow data. Consultant shall provide flo nitoring equipment.

4. Develop Population and Land Use Criteri wI Population projections provided by Planning staff and land use data acquired by the Consultant will be documented to be consistent with the long range planning. A design population forecast will be developed in close collaboration with Engineering and Planning staff and compared with other such forecasts to provide a rational for selecting the 22 of 94
Exhibit "B" ATTACHMENT 3
Consultant' s forecast. Land use projections will be provided by Planning staff. The Consultant will prepare an annual growth forecast that is consistent with the long range planning to reflect the number and types of new service connections.

5. Establish Wastewater Flow Criteria: Estimates of sewage flows will be made from the land use data and criteria. The Consultant will analyze existing wastewater flows by land use type. Peaking ratios will be developed using City data, and existing literature, and reviews conducted by the Consultant for other municipalities similar to the City. Design factors will be developed for average and peak flow conditions and will include allowances for infiltration and inflow into the system.

Future projected flows will be correlated to the population and land use projected time line and will be used to evaluate system deficiencies in the City' s system under future conditions.

6. WQCF Capacity Expansion Phasing: develop WQCF plant expansions based on future development growth along with accompanying CIPs needed to support future growth.

7. UV System Technical Memorandum: Evaluation existing UV System and provide a minimum three potential alternatives to provide treatment that meets the WQCF' s NPDES Permit.

8. Evaluate Operation and Maintenance Program: The primary goal of this subtask is to assess the need for additional resources and equipment to provide the desired level of service associated with the City' s wastewater maintenance and operations fund. If needed, this subtask should result in a business case for these additional resources. To meet this need, the Consultant will review the City' s current maintenance and operations practices, and will recommend a general operation and maintenance approach and schedule including an assessment of personnel and major equipment requirements and annual costs of operation. Recommendations will document existing maintenance operations, detail any required additional operations to meet level of service goals and NPDES Permit requirements, prepare applicable cost estimates, and compare these costs with historical costs and similar operation and maintenance programs of other municipalities and private agencies.

5. 5 Task 5 — Hydraulic Models for Phased Buildout
Develop a technical memorandum outlining the pros and cons of three different hydraulic modeling software. Software shall be suitable for the City' s sewer distribution system taking into ,account city growth and ability to make adjustments and calibrate the hydraulic model. Analysis shall include the following:

Development a hydraulic model of the City' s current sewer system to develop baseline of existing conditions, and for future development
Benefits of purchasing a software license { ncluding+software updates and additional modules Recommendations for model calibration and adjustments
Staffing recommendations versos hinng- a third pair--ty Data requirements
Provide Training for City staff( if needed)
23 of 94
Exhibit "B" ATTACHMENT 3
Costs and timeline to create the City' s sewer model

5. 6 Task 6— Wastewater Master Plan Environmental Document Consultant shall evaluate the City' s 2007 Wastewater Master Plan, the environmental documents included in Table 2, and other relevant documents to prepare the required CEQA documentation for a programmatic EIR that can be used for maintenance, operations, and capital projects. Evaluation of the required documents shall be submitted as a technical memorandum. The scope of work shall include the following items:

The cost for CEQA documents in the proposal.

Proposed project team that will work on the project through the duration of the project.

Time for consultant to compile and respond to public comments in writing.

Two iterations of response to public comments.

5. 7 Document Submittals
The following document submittal guidelines shall apply, except where noted, for each document identified for each task.

Draft version of each document for internal review
Second draft version prior to public review
Third draft version for public review
Final version, which incorporates comments from the public, and comments from City staff.

5. 8 Deliverables
The Consultant shall provide to the City the following products and services as part of this project and others the consultant deems necessary to provide a complete Project. The list applies to each document i. e., one draft of the Interim Sewer Rate Study, one draft of the Master Plan, one draft of the Sewer Rate Study, one of each technical memorandum, and one draft of the Sewer Hydraulic Model.

5. 8. 1 Draft copies
One ( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format One ( 1) electronic version in PowerPoint file format ( applies to presentations) One ( 1) AutoCAD version of figures and exhibits, where needed One ( 1) hydraulic software file

5. 8. 2
One (
Final
1)
document
PDF copy
rc - FP
One ( 1) electronic version of the complete document in Word 2010 file format 24 of 94
Exhibit "B" ATTACHMENT 3
One ( 1) electronic version in PowerPoint file format( applies to presentations) One ( 1) hydraulic software

5. 8. 3 Project Schedule
Given the complexity and number of documents required in the Scope of Work, the consultant shall update the project schedule on a monthly basis. Please submit PDF copy and a copy in Microsoft Project format.
6 Cost Proposal
The proposer must submit a detailed cost proposal for all services and materials anticipated to complete the Scope of Services with a " not- to- exceed" fixed fee, which shall be the sum of all tasks. The cost proposal shall be submitted as a separate PDF file. The file name shall follow this naming convention:

Waste waterMasterCost- Firm- Nam e.pdf'. Provide a fixed dollar amount for each of the services and materials as described in the Scope of Services.

Include an hourly rate table for typical planning and engineering classifications that may be requested for separate tasks not included in this RFP.

Innovation is encouraged to provide the City with comprehensive services in the most efficient, cost effective manner.
7 Proposal Evaluation
City staff will evaluate each proposal for completeness and content. Each proposal will be evaluated based upon the relevant qualifications and experience of the proposer. Staff may choose to interview two or more closely ranked firms, allowing 30 minutes for a presentation of the short- listed firms and another 30 minutes for a questions/ answer session. License status and references will also be verified. The proposal review will focus on the following criteria:
a. Project Management ( 15 points). Components of project management that demonstrate capability in management of projects of this scope. Include a sample monthly report. Please include a project schedule that accounts for the Scope of Services. b. Project Understanding/ Project Approach ( 40 points). The proposal adequately demonstrates an understanding and experience in preparing Wastewater Master Plans and Sewer Rate Studies for municipalities and sewer districts. Innovative approaches for alternative solutions and recommendations are preferred.
c. Experience ( 40 points). The firm's_exper is _ and professional qualifications with similar work.

Qualifications of the firm and individuals ae_ ssigned(to fform the work. d. Project 1 schedule 5 points). p ) Thoroug ss ofthe project pro ectschedule, abilityY to complete p the project p J within the selected timeframe. r U U
25 of 94
Exhibit "B" ATTACHMENT 3
8 Acceptance or Rejection of Proposal
The City reserves the right to accept or reject any and all proposals. The City also reserves the right to waive any informality or irregularity in any proposal or in the bidding as deemed to be in its best interest.

Additionally, the City may, for any reason, decide not to award an agreement as a result of this RFP or cancel the RFP process. The City shall not be obligated to respond to any proposal submitted, nor be legally bound in any manner by the submission of the proposal. The City reserves the right to negotiate Project deliverables and associated costs.

The City may require selected consultant to submit additional data or information the City deems necessary to substantiate the costs presented by the proposer. The City may also require selected consultant to revise one or more elements of its proposal in accordance with contract negotiations. 9 Inquiries and Addenda
All inquiries and questions shall be submitted in writing via email. The contact information is below.

Inquiries received after the due date to ask questions will be disregarded. Please include the following in the subject line of the email: " Wastewater Master Plan RFP." Telephonic inquiries will not be taken.

Questions and answers will be posted on the City' s website.

Contact: Elba Mijango, Associate Engineer
Email: emiiango@ci. manteca. ca. us
Subject Line: Wastewater Master Plan RFP
Deadline to ask questions: refer to Table 1 of this RFP for applicable deadlines. Questions and/ or inquiries via phone and to other city personnel will not be answered.

The City will issue any revisions to this RFP as addenda. The City will distribute addenda to all potential proposers via e- mail and post on the City' s website. Proposers are responsible for receipt of all addenda.

The City' s issuance of a written addendum is the only official method whereby the City will interpret, clarify, or provide additional information concerning this RFP. No oral revision to any provision in the RFP shall be binding.
10 Agreement for Professional Services
Refer to Attachment A for the City' s Agreement for Professional Services. 11 Insurance RequirementsAdditionally, the successful proposer sh, alo se' curial insu once required under the Agreement for Professional Services and provide any necessar ocument!ation to the City as part of the Agreement for Professional Services. Refer to Attachment B for details. 26 of 94
Exhibit "B" ATTACHMENT 3
ATTACHMENT— A

WASTEWATER MASTER PLAN & SEWER RATE STUDY

REQUEST FOR PROPOSALS

AGREEMENT FOR PROFESSIONAL SERVICES
This Agreement is made and entered into this day of 20 , by and between the CITY OF MANTECA, a
public body, corporate and politic (" City") and
a corporation (" Consultant").

RECITALS
A. Consultant is specially trained, experienced, and competent to perform the professional services required by this Agreement.

B. Consultant possesses the skill, experience, ability, background, certification, and knowledge to provide the services described in this Agreement on the terms and conditions specified herein.

C. City desires to retain Consultant to render the professional services set forth in this Agreement.

AGREEMENT

1. Scope of Services. Consultant shall perform the services described in the attached Attachment 1 that is incorporated by this reference, and pursuant to the Proposal submitted by Consultant dated and attached hereto as Attachment 2.

Consultant shall provide these services at the time, place, and in the manner specified in Attachment 1, subject to the direction of the City through its staff that may be provided from time to time. Performance of the services is sometimes referred to herein as " the Project."

2. Work Through Cit. S Consultant shall perform its services pursuant to this Agreement solely through City staff. No communications, information or documentations shall be made directly to any applicant to the City without the prior written consent ofthe City. This shall not apply to the sole request of information or clarification of information by Consultant from the applicant. All requests shall be noted to City in an expeditious manner.

3. Time of Performance. Consultant' s services will commence upon execution of this Agreement and shall be completed in accordance with the Schedule of Activities, attached hereto as Attachment 3. All work shall be completed no later than Failure to submit work products in accordance with the Schedule of Activities may result in the City withholding progress payments. Repeated failure to complete work products in accordance with the Schedule ofActivities may result in a reduction of the total compensation provided for in Section 4 herein.

4. Compensation. WithoutI additional authorization from the City, compensation to be paid to Consultant shall not exceed DOLLARS ($ Payment by City under this Agreement shall not be deemed a waiver of any defects, even ifthose defects were known to the City at the time of payment.
27 of 94
Exhibit "B" ATTACHMENT 3

ATTACHMENT- A

WASTEWATER MASTER PLAN & SEWER RATE STUDY

REQUEST FOR PROPOSALS

5. Method of Payment. Consultant shall submit monthly billings to City specifying and describing the work performed during the preceding month. Consultant' s bills shall include a brief description of the services performed, the date the services were performed, the number of hours expended and by whom, and a description of any reimbursable expenditures. Full payment of each task will only be made at such time as each task is completed.

City shall pay Consultant no later than 30 days after approval of the monthly invoice by City staff. Payments may be delayed by City if Consultant fails to provide services in accordance with the Schedule of Activities, unless the City has provided prior written consent to any delay in the schedule.

6. Extra Work. At any time during the term of this Agreement, City may request that Consultant perform Extra Work. As used herein, the term " Extra Work" means any work that is determined by City to be necessary for the proper completion of the Project, but which the parties did not reasonably anticipate would be necessary at the time of execution of this Agreement. Consultant shall not perform, nor be compensated for, Extra Work without the City' s prior written authorization.

7. Termination. This Agreement may be terminated by the City immediately for cause, or by either party without cause upon 15 days' prior written notice of termination. Upon termination, Consultant shall be entitled to compensation for services performed up to the effective date of termination upon submittal of an invoice for same.

8. Ownership of Documents; Confidentiality.

A. All plans, studies, documents, and other writings prepared by and for Consultant, its officers, employees, agents, and subcontractors in the course of implementing this Agreement, except working notes and internal documents, shall become the property of City upon payment to Consultant for such work. City shall have the sole right to use such materials in its discretion without further compensation to Consultant or to any other party. Consultant shall, at Consultant' s expense, provide such reports, plans, studies, documents and other writings to City upon written request by City. Consultant shall not be responsible for any unauthorized modification or use of such information for other than its intended purpose.

B. All memoranda, specifications, plans, procedures, drawings, descriptions, computer program data, input record data, written information, and other documents and data, either created by or provided to Consultant in connection with the performance of this Agreement, shall be held confidential by Consultant. These materials shall not, without the City' s prior written consent, be used by Consultant for any purposes other than the performance of the services under this Agreement. Nor shall these materials be disclosed to any person or entity not connected with the performance of services under this Agreement. Nothing furnished to Consultant that is otherwise known= to Consultant,- or,.is generally known, or has become known to the related profession shall_ be--0eemed- confidential. Consultant shall not use City' s name or insignia, photographs relafig' to the Projefor which Consultant' s services are rendered, or any publicity pertaining to tli&Consultant' s services under this Agreement in any magazine, trade paper, newspaper, television or radio production, or other similar medium without the City' s prior written consent.
28 of 94
Exhibit "B" ATTACHMENT 3
ATTACHMENT— A

WASTEWATER MASTER PLAN & SEWER RATE STUDY

REQUEST FOR PROPOSALS

9. Consultant' s Books and Records.

A. Consultant shall maintain all ledgers, books of account, invoices, vouchers, canceled checks, and other records or documents evidencing or relating to charges for services, or expenditures and disbursements charged to City, for a minimum period of three years, or for any longer period required by law, from the date of final payment to Consultant under this Agreement.

B. Consultant shall maintain all records that document performance under this Agreement for a minimum period of three years, or for any longer period required by law, from the date of termination or completion of this Agreement.

C. Any records or documents required to be maintained pursuant to this Agreement shall be made available for inspection or audit at any time during regular business hours, upon written request by the City Manager, City Attorney, City Auditor, or a designated representative of any of these officers. Copies of such documents shall be provided to City for inspection at City Hall when it is practical to do so. Otherwise, unless an alternative is mutually agreed upon, the records shall be available at Consultant' s address specified in Section 16 of this Agreement.

D. Where City has reason to believe that records or documents may be lost or discarded due to the dissolution or termination of Consultant's business, City may, by written request, require that custody of the records be given to the City and that the records and documents be maintained in City Hall. Access to these records and documents shall be granted to any party authorized by Consultant, Consultant's representatives, or Consultant' s successor-ininterest.

10. Independent Contractor. In the performance of the work and services required by this Agreement, Consultant shall act as and be an independent contractor and not an agent, or employee of the City. Consultant shall obtain no rights to retirement or other benefits that accrue to City' s employees, and Consultant expressly waives any claim it may have to any such rights.

11. Interest of Consultant.

A. Consultant represents that neither it nor any employee has any investment or interest in real property, and shall not acquire any such interest, direct or indirect, within the area covered by this Agreement, or any other source of income, interest in real property, or investment that would be affected in any manner or degree by the performance of Consultant' s services hereunder. Consultant further represents that, in the performance of its duties hereunder, no person having any such interest shall perform any services under this Agreement.

B. Consultant is not-- a designated— employee within the meaning of the Political Reform Act because Consultant: )
1) will condtt` reslarch and arrive at conclusions with respect to its rendition of information, advice, recommendation, or counsel independent of the control and direction ofthe City, or of any City official, other than normal Agreement monitoring; and
29 of 94
Exhibit "B" ATTACHMENT 3
ATTACHMENT— A

WASTEWATER MASTER PLAN & SEWER RATE STUDY

REQUEST FOR PROPOSALS
2) possesses no authority with respect to any City decision beyond the rendition of information, advice, recommendation, or counsel.

FPPC Reg. 18700( a)( 2).)

12. Professional Ability of Consultant.

A. City is relying upon the professional training and ability of Consultant to perform the services hereunder as a material inducement to enter into this Agreement.

Consultant shall therefore provide skilled professional and technical personnel to perform all services under this Agreement. All work performed by Consultant shall be in accordance with applicable legal requirements and shall meet the standard of quality ordinarily to be expected of competent professionals in Consultant's field of expertise.

B. The primary provider of the services required by this Agreement shall be A list of other individuals assigned to the Project will be provided to City for its review and approval, and these individuals shall not be replaced without the City' s prior written consent.

13. Compliance with Laws. Consultant shall use the customary standard of care in its profession to comply with all applicable federal, state, and local statutes, codes, ordinances, and regulations.

14. Licenses. Consultant represents and warrants to City that it has all licenses, permits, qualifications, insurance, and approvals that are legally required of Consultant to practice its profession. Consultant represents and warrants to City that Consultant shall, at its sole cost and expense, keep in effect or obtain at all times during the term of this Agreement, any licenses, permits, insurance, and approvals that are legally required of Consultant to practice its profession.

15. Indemnification and Hold Harmless. Consultant agrees to defend, indemnify, and hold harmless the City, its officers, officials, agents, employees, and volunteers, from and against any and all claims, demands, actions, losses, damages, injuries, and liability, direct or indirect including any and all costs and expenses in connection therewith), arising out of Consultant' s performance of this Agreement, or Consultant' s failure to comply with any of its obligations contained in this Agreement; excluding, however, any claim arising out of the active negligence or willful misconduct of the City, its officers, agents, employees, or volunteers.

16. Insurance Requirements.

A. Job specific insurance requirements can be found on the attached Attachment

4. Other insurance provisions can be found below:

B. Endorsements. Each general liability and automobile liability insurance policy shall be with insurers possessing- ariA.Cl 1` Bes ' s- rating of no less than A:VII and shall be endorsed with language substantiallyal s follnws: U
1) The City, its elected and appointed officers, officials, employees, agents and volunteers are to be covered as additional insureds with 30 of 94
Exhibit "B" ATTACHMENT 3

ATTACHMENT- A

WASTEWATER MASTER PLAN & SEWER RATE STUDY

REQUEST FOR PROPOSALS
respect to liability arising out ofwork performed by or on behalf of the Consultant, including materials, parts, or equipment furnished in connection with such work.
2) The policy shall be considered primary insurance as respects the City, its elected and appointed officers, officials, employees, agents and volunteers. Any insurance maintained by the City, including any self-insured retention the City may have, shall be considered excess insurance only and shall not contribute with it. 3) The insurance shall apply to each insured and additional insured as though a separate policy had been written for each, except with respect to the limits of liability of the insuring company. 4) The insurer waives all rights of subrogation against the City, its elected and appointed officers, officials, employees, and agents. 5) Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the City, its elected and appointed officers, officials, employees, agents, or volunteers. 6) The insurance provided by the policy shall not be suspended, voided, canceled, or reduced in coverage or in limits except after 30 days written notice has been received by the City.
7) The City will not accept any endorsements that were issued in 2004. Acceptable endorsement forms are CG 20 10 11 85 or both CG20101001 and CG 20 37 10 01.

C. Deductibles and Self-Insured Retentions. Any deductibles or self-insured retentions must be declared to and approved by the City. At the City' s option, Consultant shall demonstrate financial capability for payment of those deductibles or self-insured retentions.

D. Certificates of Insurance. Consultant shall provide to City certificates of insurance with original endorsements as evidence of the required insurance coverage.

Certificates of insurance shall be filed with the City on or before commencement of performance of this Agreement. Current certification of insurance shall be kept on file with the City at all times during the term ofthis Agreement.

17. Notices. Any notice required to be given under this Agreement shall be in writing and either served personally or sent prepaid, first class mail. Any such notice shall be addressed to the other party at the address set forth_below._Notice-shall be deemed communicated within 48 hours from the time of mailing if inailed'as prvded 1n-1His section.

If to City: city fMantecal'
1001 W. Center Street
Manteca, CA 95337
Attention:
31 of 94
Exhibit "B" ATTACHMENT 3
ATTACHMENT— A

WASTEWATER MASTER PLAN & SEWER RATE STUDY

REQUEST FOR PROPOSALS
If to Consultant:

Attention:

18. Entire Agreement. This Agreement constitutes the complete and exclusive statement of Agreement between the City and Consultant. All prior written and oral communications, including correspondence, drafts, memoranda, and representations, are superseded in their entirety by this Agreement.

19. Amendments. This Agreement may be amended only by a written document executed by both Consultant and City and approved as to form by the City Attorney.

20. Assignment and Subcontracting. The parties recognize that a substantial inducement to City for entering into this Agreement is the professional reputation, experience, and competence of Consultant. Assignments of any or all rights, duties, or obligations of the Consultant under this Agreement will be permitted only with the express written consent of the City. Consultant shall not subcontract any portion of the work to be performed under this Agreement without the written authorization of the City. If City consents to such subcontract, Consultant shall be fully responsible to City for all acts or omissions of the subcontractor.

Nothing in this Agreement shall create any contractual relationship between City and subcontractor nor shall it create any obligation on the part of the City to pay any monies due to any such subcontractor other than as may be required by law.

21. Waiver. Waiver of any breach or default under this Agreement shall not constitute a continuing waiver of a subsequent breach or default of the same or any other provision under this Agreement.

22. Severability. If any provision of this Agreement is held to be invalid, illegal, or otherwise unenforceable by a court of competent jurisdiction, the remaining provisions of this Agreement shall continue in full force and effect.

23. Controlling Law; Venue. This Agreement and all matters relating to it shall be governed by the laws of the State of California, and any legal action relating to this Agreement shall take place in the Superior Court, County of San Joaquin.

24. Litigation Expenses and Attorneys' Fees. If either party to this Agreement commences any legal action against the other party arising out of this Agreement, the prevailing party shall be entitled to recover its reasonable litigation expenses, including court costs, expert witness fees, discovery expenses, and attorneys' fees.

25. Mediation. The parties- a--gree to- make a-good faith attempt to resolve any disputes arising out of this Agreement throuh mediatiorior to ' commencing litigation. The parties shall mutually agree upon the mediator and shall divide--the costs of mediation equally. If the parties are unable to agree upon a mediatothe r dispute shall be submitted to JAMS/ ENDISPUTE (" JAMS") or its successor in interest. JAMS shall provide the parties with the names of five qualified mediators. Each party shall have the option to strike two of the five 32 of 94
Exhibit "B" ATTACHMENT 3

ATTACHMENT- A

WASTEWATER MASTER PLAN & SEWER RATE STUDY

REQUEST FOR PROPOSALS
mediators selected by JAMS, and thereafter the mediator remaining shall hear the dispute. If the dispute remains unresolved after mediation, either party may commence litigation.

26. Execution. This Agreement may be executed in several counterparts, each of which shall constitute one and the same instrument and shall become binding upon the parties when at least one copy has been signed by both parties.

27. Authority to Enter Agreement. Consultant warrants that it has all requisite power and authority to conduct its business and to execute, deliver, and perform this Agreement. Each party warrants to the other that the signatories to this Agreement have the legal power, right, and authority to enter into this Agreement and to bind each party.

28. Prohibited Interests.

A. Consultant warrants that it has not employed or retained any person, other than a bona fide employee working solely for Consultant, to solicit or secure this Agreement.

Further, Consultant warrants that it has neither paid nor agreed to pay any person, other than a bona fide employee working solely for Consultant, any fee, commission, percentage, brokerage fee, gift, or other consideration contingent upon or resulting from the award or making of this Agreement. For any breach or violation of this warranty, City shall have the right to rescind this Agreement without liability.

B. For the term of this Agreement, no member, officer, or employee of City, during the period of his or her service with City, shall have any direct interest in this Agreement, or obtain any present or anticipated material benefit arising therefrom.

29. Equal Opportunity Employment. Consultant represents that it is an equal opportunity employer, and it shall not discriminate against any subcontractor, employee, or applicant for employment because of race, religion, color, national origin, handicap, ancestry, sex, or age. Such non- discrimination shall include, but not be limited to, all activities related to initial employment, upgrading, demotion, transfer, recruitment or recruitment advertising, layoff or termination.

30. Precedence. In case of conflict between Consultant' s Proposal/ Consultant' s attachments and the City' s Agreement/ City' s attachments, the City' s Agreement and City' s attachments shall take precedence over Consultant' s proposal/Consultant' s attachments. 33 of 94
Exhibit "B" ATTACHMENT 3
ATTACHMENT— A

WASTEWATER MASTER PLAN & SEWER RATE STUDY

REQUEST FOR PROPOSALS
This Space Purposely Left Blank
F=:: p
34 of 94
Exhibit "B" ATTACHMENT 3
ATTACHMENT— A

WASTEWATER MASTER PLAN & SEWER RATE STUDY

REQUEST FOR PROPOSALS
TO EFFECTUATE THIS AGREEMENT, each of the parties has caused this Agreement to be executed by its duly authorized representative as ofthe date set forth in the introductory paragraph on page 1 above.

CITY OF MANTECA: CONSULTANT:

M. G. Harden, Type name of Consultant/ forin oforganization) Interim City Manager
ATTEST: By:

Signature)
Cassandra Candini- Tilton, Type naine and title)
Director of Legislative Services
COUNTERSIGNED: By:

Signature)
Jared Hansen, Type name and title)
Acting Director ofFinance
COUNTERSIGNED: Address:

Aaron Slater,
Director of Employee Services& Engagement
Telephone:

APPROVED AS TO FORM:

F
I
L. David Nefouse,
City Attorney
35 of 94
Exhibit "B" ATTACHMENT 3
ATTACHMENT— A

WASTEWATER MASTER PLAN & SEWER RATE STUDY

REQUEST FOR PROPOSALS
NOTE: this Agreement for Professional Services would also include the attachments listed below.

ATTACHMENT 1: REQUEST FOR PROPOSAL
ATTACHMENT 2: CONSULTANT' S PROPOSAL
ATTACHMENT 3: SCHEDULE OF ACTIVITIES
F
r
36 of 94
Exhibit "B" ATTACHMENT 3
EXHIBIT 1
Insurance Requirements for Professional Services

INSURANCE REQUIREMENTS
Consultants shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder by the Consultant, his agents, representatives, employees or subcontractors.

Minimum Limits of Insurance: Coverage shall be at least as broad as:

Commercial General Liability
Commercial General Liability Insurance with$ 2, 000, 000 minimum limit per occurrence.

If a general aggregate limit applies, either the general aggregate limit shall apply separately to this project/ location or the general aggregate limit shall be twice the required occurrence limit.

Commercial General Liability Additional Insured Endorsement naming the following as insured on 2001 or earlier issued endorsement forms:

City of Manteca, its officers, officials, employees, agents, and volunteers".

Automobile Liability
If the vehicles are brought onto city facilities, covering any auto, or of Contractor has no owned autos, hired, and non- owned autos, the Contractor shall maintain automobile liability with limits no less than:

Automobile Liability Insurance with$ 1, 000,000 minimum limit per accident for bodily injury and property damage.

Automobile Liability Additional Insured Endorsement naming the following as additional insured:

City ofManteca, its officers, officials, employees, agents, and volunteers".

Worker' s Compensation
As required by the State of California, with Statutory Limits, and Employer' s Liability Insurance with limit of no less than$ 1, 000, 000 per accident for bodily injury or disease.

Professional Liability( Errors and Omissions)
Insurance appropriates to the Contractor' s profession, with limit no less than$ 2, 000,000 per occurrence or claim,$ 2, 000, 000 aggregate
Other Insurance Provisions.-
The insurance policies are to contain, or be endorsed to contain, the following provisions:

1. The City of Manteca, its officers, officials, employees, agents and volunteers are to be covered as insured' s as respect to: liability arising out of work or operations performed by or on behalf of the Consultant including materials, parts, or equipment furnished in connection with such work operations. General liability coverage can be provided in the form of an endorsement to the Consultant' s insurance at least as woad- as CG` 2010 nd-CG 20 37 if completed operations coverage is required.

2. For any claims related to this con acshe Cq nsultan' s insurance coverage shall be primary insurance as respects the City, its officers, offcials, employees, agents and volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, employees, agents or volunteers, shall be excess of the Consultant' s insurance and shall not contribute with it. 05/ 14
37 of 94
Exhibit "B" ATTACHMENT 3

3. The applicant' s insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer' s liability.

4. Each insurance policy required by this clause shall be endorsed to state that coverage shall not be suspended, voided, canceled by either party, reduced in coverage or in limits except after thirty( 30) days prior written notice by certified mail, return receipt requested, has been given to the City of Manteca.

Verification ofCoverage
Consultant shall furnish the City with original certificates and amendatory endorsements or copies of the applicable policy language effecting coverage required by this clause. All certificates and endorsements are to be received and approved by the Entity before work commences. However, failure to obtain the required documents prior to the work beginning shall not waive the Consultant' s obligation to provide them. The City of Manteca reserves the right to require complete, certified copes of all required insurance policies, including endorsements required by these specifications, at any time.

Notice ofCancellation
Each insurance policy required above shall provide that coverage shall not be canceled, except with notice to the Entity.

Acceptability ofInsurers
Insurance is to be placed with insurers with a current A. M. Best' s rating of no less than AXII, unless otherwise acceptable to the City of Manteca
Waiver ofSubrogation
Consultant hereby grants to The City of Manteca a waiver of any right to subrogation which any insurer of said Consultant may acquire against the Entity by virtue of the payment of any loss under such insurance.

Consultant agrees to obtain any endorsement that may be necessary to affect this waiver of subrogation, but this provision applies regardless of whether or not the Entity has received a waiver of subrogation endorsement from the insurer.

Subcontractors
Consultant shall require and verify that all subcontractors maintain insurance meeting all the requirements stated herein, and Contractor shall ensure that The City of Manteca is an additional insured on insurance required from subcontractors.

SPECIAL RISKS OR CIRCUMSTANCES
The City of Manteca reserves the right to modify these requirements based on the nature of the risk, prior events, insurance coverage, or other special circumstances. 05/ 14
38 of 94
Exhibit "B" ATTACHMENT 3

CITY OF MANTLCA
2021 WASTEWATER MASTER PLAN AND SEWER RATE STUDY RFP
ADDENDUM 1
DATED: September 7, 2021
This addendum forms part ofthe Contract Documents and modifies the original Request for Proposal ( RFP). Proposers shall acknowledge receipt of this Addendum by signing the attached acknowledgement and including the Acknowledgement in their RFP proposal.

Failure to include the Acknowledgement with their RFP proposal may subject the proposal to disqualification.

GENERAL:

The pages in this addendum DO NOT count towards total page count requirements.

The following changes, deletions, and additions shall be made to the following documents, as noted, and shall take precedence over the original Contract Documents. All other requirements remain the same.

Item Pa a Number Description

1. 1 3 The City ofManteca has extended the submittal deadline for the Wastewater Master Plan & Sewer Rate Study RFP to
the dates in the attached Table 1: RFP Deadlines (Revised per Addendum 1) ( seepage 2 this addendum).

F` F
39 of 94
Exhibit "B" ATTACHMENT 3

CITY OF MANTECA
2021 WASTEWATER MASTER PLAN AND SEWER RATE STUDY RFP
ADDENDUM 1
DATED: September 7, 2021
Table 1: RFP Deadlines ( Revised per Addendum 1)
Milestone Deadline 1- Week Extension
RFP Issued August 12, 2021 August 12, 2021
Deadline for SeptemberT29= 1 5: 0011: September 9, 2021 Clarifications/ Inquiries P-STDeadline for Proposal Submittal Sete er 13, 2021 5. 00 " n September 20, 2021
SeptembeF 21 22, 2021 September 28— 29
Interviews ( tentative)
fFB : 8: 00 am
t , 2: 30 .,.,, From 8: 00 am to 12: 30 pm
Award of Contract( tentative) Week of October 19tn
Issue Notice to Proceed
Week of Oetabe
Week of October 26tn
tentative)
R, , F
40 of 94
Exhibit "B" ATTACHMENT 3

CITY OF MANTLCA
2021 WASTEWATER MASTER PLAN AND SEWER RATE STUDY RFP
ADDENDUM 1
DATED: September 7, 2021
I acknowledge receipt of Addendum No. 1.

Company:

By:

Title:

Address:

Date:

F FF/
41 of 94
Exhibit "B" ATTACHMENT 3

CITY OF MANTECA
2021 WASTEWATER MASTER PLAN AND SEWER RATE STUDY RFP
ADDENDUM 2
DATED: September 15, 2021
This addendum forms part ofthe Contract Documents and modifies the original Request for Proposal ( RFP). Proposers shall acknowledge receipt of this Addendum by signing the attached acknowledgement and including the Acknowledgement in their RFP proposal.

Failure to include the Acknowledgement with their RFP proposal may subject the proposal to disqualification.

GENERAL:

The pages in this addendum DO NOT count towards total page count requirements.

The following changes, deletions, and additions shall be made to the following documents, as noted, and shall take precedence over the original Contract Documents. All other requirements remain the same.

Item Paize Number Description
N/ A 11 Task 7— Staffing Plan
Consultant shall evaluate current and future staffing needs at the WQCF and the Engineering Department ( engineering and inspection services). The evaluation shall identify when and what positions are needed under current conditions and as additional treatment systems, and/ or equipment are
added. Future staffing needs shall correlate with projects identified in the Wastewater Master Plan, and budgeted
along with capital improvement projects.

Staffing plan objectives shall include, but not limited to:

Identify the appropriate level of existing and future
staffing needs to complete day-to-day tasks, and
meet service levels needed to meet regulatory
requirements;
Define licensing, certification requirements, and the
skillset required of future City personnel;
Identify the employee positions needed to manage
future=c` pital improvement projects;
Identify emm& yee positions needed to carry out
maintenance and repair activities as additional
atmenY systems, and/ or equipment are added;
Succession planning to prepare for the retirement of
key personnel; and
2021 Wastewater Master Plan and Sewer Rate Stud RFP Addendum 2 Page 1 Y g September 15, 2021 42 of 94
Exhibit "B" ATTACHMENT 3
Item Pa a Number Description
Include estimated costs for staff time to manage,
oversee, inspect, and manage the construction of
projects.
e.
2021 Wastewater Master Plan and Sewer Rate Study RFP Addendum 2 Page 2 September 15, 2021 43 of 94
Exhibit "B" ATTACHMENT 3

CITY OF MANTLCA
2021 WASTEWATER MASTER PLAN AND SEWER RATE STUDY RFP
ADDENDUM 2
DATED: September 15, 2021
I acknowledge receipt of Addendum No. 2.

Company:

By:

Title:

Address:

Date:
2021 Wastewater Master Plan and Sewer Rate Study RFP Addendum 2 Page 3 September 15, 2021 44 of 94
Exhibit "B" ATTACHMENT 3
ATTACHMENT 2

CONSULTANT' S PROPOSAL AND SCOPE OF SERVICES
I
45 of 94
Exhibit "B" ATTACHMENT 3
Wastewater Master Plan and Sewer
Rate Study Proposal
i - _ Lei r.•" U
wf_=
qr J.
41 71
c
L
i ••
r
w+ a.• i. •
M+
A= i` Y '.— rrY ice.
w'
G
1 J ` (
l r
Manteca Water Quality Control Facility
SEPTEMBER 20, 2021 PREPARED FOR: PREPARED BY:

CITY OF MANTECA, CALIFORNIA STANTEC CONSULTING SERVICES INC.

Stantec
46 of 94
Exhibit "B" ATTACHMENT 3

1. COVER LETTER 1
Acknowledgments 2

2. ORGANIZATION CREDENTIALS, BACKGROUND 3

3. EXPERIENCE 4

4. PROJECT TEAM 6

4. 1 Lead Firm 6

4. 2 Project Manager, Principal- in- Charge 7

4. 3 Project Team 7
HERWIT 7
V& A Engineering 7
F3 and Associates 8
CV Strategies 8
PROPOSED TEAM MEMBERS 8
R6sum6s 8
Key/ Lead Team Members 8
Support Staff 9
ORGANIZATIONAL CHART 11

5. PROJECT UNDERSTANDING AND APPROACH 12
Project Goals 12
Project Understanding 12
Rate Studies 12
Water Quality Control Facility 12
Task 1 - Kick-Off Meeting 13
Task 2- Interim Sewer Rate Study 13
Task 3- Final Sewer Rate Study 15
Task 4- Wastewater Master Plan 17
Wastewater Collection System 17
Water Quality Control Facility 19
CIP Development and Final Report 21
PACP Grade 4 and 5 Defects Overview 22
Task 5- Hydraulic Models for Phased Buildout 23
Task 6- Wastewater Master Plan Environmental
Document 23
Task 7- Staffing Plan 23

6. COST PROPOSAL 23

7. SCHEDULE OF WORK 23

8. REVIEW OF AND EXCEPTIONS TO PROFESSIONAL
SERVICES AGREEMENT 23
47 of 94
Exhibit "B" ATTACHMENT 3
Stantec L . oval, Led'I'e'
Stantec Consulting Services Inc.
3875 Atherton Road
Rocklin, CA 95765
September 20, 2021
Attn: Elba Mijango, Associate Engineer
City of Manteca
1001 West Center Street
Manteca, CA 95337
Reference: Proposal for City of Manteca Wastewater Master Plan and Rate Study Dear Elba Mijango and Selection Committee Members,
The City of Manteca( City) has made a significant investment in its Water Quality Control Facility( WQCF) and wastewater collection system, including many miles of aging gravity sewer pipelines. Good practice calls for the City to have an updated and comprehensive Wastewater Master Plan and Capital Improvement Program. Having completed a Sanitary Sewer Condition Assessment for the City in 2017 and Secondary Treatment Capacity Assessment for the WQCF in 2021, Stantec Consulting Services Inc.( Stantec) understands many of the issues and challenges that are confronting the City. Our objective is to provide the City with a practical plan to assess and maintain this critical infrastructure and to establish updated sewer rates to enable the plan' s implementation.

We have assembled the right team for this important project. The proposed team routinely prepares wastewater master plans, condition assessments and( CIPs), and frequently pairs this analysis with comprehensive financial plans, sewer rate studies, and Proposition 218 support. Our operators and mechanics run wastewater treatment plants and sewer collection systems and help keep our engineering input practical, usable, and implementable. Of course, we can, and will, run sophisticated models and analyses of the sanitary sewer collection system, but we recognize that the City needs a Wastewater Master Plan that can be distilled down to usable project information— identifying project needs, risks, costs, and priorities.

Master Plan Team. We have recently completed wastewater master plans, condition assessments, and CIP plans for the Cities of Benicia, Grass Valley, Lincoln, Manteca, San Mateo, Placer County, and others. Two in-progress master plans include the Cities of Concord and Dixon. Steve Beck, PE, our proposed project manager for Manteca, was involved in most of them; and the client contacts identified in this proposal will provide excellent references attesting to our practical input. We encourage you to contact these satisfied clients. Steve has excelled at managing our wastewater planning teams with an aim at providing practical and clear direction for how to move forward with infrastructure planning and maintenance. He understands that analysis alone is not the goal, but rather good analysis provides the means to get to the best recommended CIP. With this perspective, Steve is well positioned to work with the City and the proposed team to complete this Wastewater Master Plan for the City.

To support this work effort, we have teamed with HERWIT Engineering. Teaming with HERWIT Engineering provides the unique advantage of allowing us to capture their institutional knowledge of the existing project work already completed at the WQCF.

Also on our team is V& A for flow monitoring and F3 and Associates for surveying. Together, with all of our teaming partners we' ll address the previously identified gaps in the existing master plan and capital improvement program.

Rate Study Team. Our team of financial consultants, Matthew Freiberg, Sally Van Etten, and Benjamin Stewart, are joined by Tara Bravo of CV Strategies. This team specializes in utility rate making, stakeholder engagement, and Proposition 218 support, and have worked successfully together on multiple rate studies in California. We have recent and relevant experience conducting similar wastewater rate studies for utilities in California including:

West County Wastewater District, CA— wastewater rate study and capital improvement prioritization City of Palm Springs, CA— 10-year capital improvement plan and wastewater rate study City of Needles, CA— electric, water and wastewater rate studies including revenue sufficiency analyses for each utility and detailed wastewater cost-of-service and rate analysis
48 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL Exhibit "B" ATTACHMENT 3
City of Whittier, CA— water and sewer rate studies, and water and sewer connection fee updates.

City of Santa Ana, CA— water, recycled water, and wastewater rate study and connection fee development As part of this analysis, we will evaluate the City' s financial policies, create a customized financial model to evaluate multiple CIP scenarios, integrate our recommendations with the City' s billing process and procedures, and review the City' s rate structure. Our analysis will take into consideration changing funding requirements created by the ongoing COVID- 19 pandemic, regulatory compliance requirements, infrastructure investment needs, and suggested staffing levels consistent with the objectives of the City' s updated Wastewater Master Plan.

Our team has the right blend of national expertise combined with local knowledge to help the City establish an interim and final wastewater rate plan, an annual cash flow analysis, and provide Proposition 218 technical assistance. The outcomes of our analyses will be a plan to sustainably meet investment and operational needs, while meeting financial targets, and an updated rate structure that will equitably recover revenue from customers.

ACKNOWLEDGMENTS
Our proposal is signed by Steven Beck, authorized to enter into an Agreement with the City.

We acknowledge that proposals are in effect and legally binding for 120 days We acknowledge the resume requirements in the RFP, and resumes for each staff member are included as part of the proposal.

We acknowledge receipt of Addendum No. 1 dated September 7, 2021, and a signed acknowledgment is included at the back of our proposal.

We acknowledge receipt of Addendum No. 2 dated September 15, 2021, and a signed acknowledgment is included at the back of our proposal.

Our single exception to the City' s Agreement for Professional Services is provided in Section 8. We believe that should we be selected for this project, we will be able to come to a mutually agreeable contract.

By utilizing our local experience, technical qualifications, and full- service team, we look forward to helping you deliver this important project. The main contact for the remainder of the selection process is Steven Beck, who will be available through the below contact information.

Sincerely,
Stantec Consulting Services Inc.

Steven L. Beck Matthew Freiberg
PE Lead, Sewer Rate Studies
Principal- in- Charge/ Project Manager 1340 Treat Boulevard Suite 300, Walnut Creek CA 94597 3875 Atherton Road, Rocklin CA 95765 Mobile:( 925) 286- 7401 Mobile:( 916) 826- 3665 Matthew. Freiberg@stantec. com
Steven. Beck@stantec. com
The City of Manteca Water Quality
Control Facility Digester Improvement
Project received the prestigious Water
Environment Federation( WEF)
Excellence Award for innovative design.
49 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL z Exhibit "B" ATTACHMENT 3
tirch' aitus
F
I
a:

CA 65614 ate C
19i1 G l
mot'
L'/ a LI EC]1"'"1`.vLL Natural Gas Refueling Station
Manteca, CA
va 61(B n"d't a I s cic h, c)e Lic]
Established in 1954, the Stantec community unites approximately 22,000 employees working in over 350 locations across six continents. We collaborate across disciplines and industries to bring FIRM INFORMATION buildings, energy and resource, environmental, water, and infrastructure projects to life. We have a
long- term commitment to Numberbusiness
the people and places we serve. Communities are fundamental. preparing Whether around the corner or across the globe, they provide a Plans andSewer RateStudies '
foundation, a sense of place and of belonging. That' s why at Stantec, municipalts ' Sewer 67 we design with community in mind. We care about the communitiesagencies:
we serve— because they are our communities too. Preserving and Type of organization: Corporation
maintaining water and wastewater infrastructure is paramount to a community' s health and near- term/ long- term success. Location of the offices that will We participate in a wide spectrum of projects: from very small thepproject team and
maintenance projects to some of the world' s largest and most Rocklin and Walnut Creek technologically significant infrastructure projects. As such, we have developed industry- leading project teams; over the years, we have Personnel resources within continually refined and improved the services and products we provide to our clients. Moreover, there are no boundaries to our22,000 employees w, . .- accessibility and availability. 240 California Wastewater The individuals identified in Section 4 will be the same individuals Professionals
that complete the project work and meet/ communicate with City staff on an ongoing, consistent, and regular basis. The City shall be notified in writing of any change in staff members( including subconsultants) at least 30 days in advance. Changes in staff will be approved in writing by the City.
50 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL a Exhibit "B" ATTACHMENT 3
Manteca Sanitary Sewer Evaluation
Study I Manteca, California
Manteca Water Quality Control Facility
Digester Improvement Project Phase I Stantec was selected by the City of Manteca to lead and Compressed Biogas Fueling Facility, Sanitary Sewer Evaluation Study( SSES) field activities and Phase II 1 Manteca, California perform an Engineering Assessment on a portion of the City' s sanitary sewer system.

Manteca operates a water pollution control facility( WQCF) to treat City- generated wastewater.The plant has a
Stantec was responsible for all project- related work,
permitted capacity of 9. 87- mgd and is currently flowing including managing all field activities, developing and approximately 7. 5- mgd. The facility includes primary, managing project deliverables, reviewing and appending the secondary, and tertiary treatment to Title 22 standards and Portion of the City' s GIS database related to the project, data fully nitrifies and denitrifies to 10 mg/ I total nitrogen. The compilation and analysis, and performing the condition City recently prepared a Biosolids and Biogas Utilization assessment for the sewer lines and manholes.

Plan. The purpose of the plan was to identify the best way A detailed Work Plan, Health and Safety Plan, and Traffic to accommodate future plant needs with Assembly Bill Control Plan were all submitted to the City prior to 1826 concerning diversion of food waste from landfills. commencing the work. Pipe cleaning and CCTV inspections The Biosolids plan broke up facility improvements at the were performed by Stantec's subcontractor on 52,150 lineal WQCF into 2 phases. Phase I included a digester expansion feet of gravity sanitary sewer line ranging in size from and new digester control building with the latest energy 10-inch to 60-inch and visual inspection of 187 manholes. efficient technology. Phase II included a new facility to The IBAK Panoramo@ 3D Optoscanner was used for the convert biogas to renewable natural gas for fueling the City inspection of the sewer lines and the IBAK Panoramo@ Si garbage fleet and other City and public vehicles.
was used for the inspection of the manholes. Sewer line The biogas produced by the proposed facilities will be
inspections and manhole inspections were coded in
utilized to offset current use of diesel and gasoline in City accordance with the Pipeline Assessment Certification
garbage trucks and vehicles. The City has already begun Program @( PACP) and Manhole Assessment Certification
purchasing compressed natural gas( CNG) vehicles for the Program @( MACP) developed by the National Association garbage fleet as part of the Program. Using the City' s of Sewer Service Companies( NASSCO).
resources in this manner allows for a more economically Upon completion of the inspection and condition attractive project with greater environmental benefits than assessment, Stantec prepared detailed recommendations
just producing electricity from the biogas. for follow- up actions to address sewer repairs and Converting digester gas into renewable CNG( to fuel the City rehabilitations. Additionally, Stantec provided cost opinions vehicles) allowed the City to obtain grant funding. HERWIT and priorities for the recommended repairs and applied for and obtained grants from the San Joaquin Air rehabilitations. Recommendations, cost opinions, and
Pollution Control District($ 1. 89 million) and the California priorities will be used by the City for long-term planning and Energy Commission($ 3. 3 million), which help offset the scheduling of their CIP program and entering a preventative cost of the project. This project received the national Water maintenance schedule into their Computerized Maintenance Environment Federation( WEF) Project Excellence Award for Management System( CMMS).
2019, beating out all projects in the Nation. California State congressman also attended the grand opening of the PROJECT MANAGER: Steven Beck, PE, Principal- in- Charge project. COMPLETION DATE: 8/ 15/ 2017
CLIENT NAME AUD REPRESENTATIVE: City of Manteca// George PROJECT MANAGERS: Steven Beck, PE,( Stantec) and Greg Harris Montross, Operations Director//( 209) 456- 8468// gmontross@ HERWIT) ci. manteca. ca. us
COMPLETION DATE: June 2019 ORIGINAL PROJECT BUDGET:$ 365, 789. 00 CLIENT NAME AND REPRESENTATIVE: City of Manteca// George FINAL COST:$ 347,582. 07 Montross, Operations Director//( 209) 456- 8468// gmontross@ ORIGINAL PROJECT DURATION: 05/ 2016- 08/ 2017 ci. manteca. ca. us FINAL PROJECT DURATION: 05/ 3/ 2016- 8/ 15/ 2017 ORIGINAL PROJECT BUDGET:$ 30 Million for Phase 1 and 2 SUBCONSULTANT DETAILS: No subconsultants were used on this FINAL COST:$ 30 Million for Phase 1 and 2 project.

ORIGINAL PROJECT DURATION: 02/ 2015- 06/ 2019
FINAL PROJECT DURATION: 02/ 2015- 06/ 2019
SUBCONSULTANT DETAILS: The HERWIT/ Stantec team provided all master planning, design, construction services, startup services, and obtained all grant funding for Phase 1 and Phase 2 of the project. 51 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL a Exhibit "B" ATTACHMENT 3
City of Benicia Water and Wastewater Lincoln Server Wastewater Collection and Master Plan Update and Major Facility Treatment and Master Planning and Design Condition Assessment I Benicia, California Lincoln, California The City of Benicia water infrastructure includes a raw water In 1994, Lincoln had a population of only 6, 500 people and their supply pump station and 15- mile raw water main, 12- mgd wastewater was treated in a series of aerated ponds and water treatment plant, four storage tanks, three booster disposal was via evaporation, percolation, and irrigation. With pump stations and 165 miles of distribution system. All the significant City growth on the horizon and very limited capacity facilities operate acceptably, but much of the City and water in the existing system, Stantec was hired to complete a facilities were built in the 1960s and 1970s leaving some comprehensive master plan in 2016 to address service within critical infrastructure nearing the end of its useful life. The the legacy part of town and to serve the new General Plan, City' s wastewater infrastructure includes a 12- mgd which is set to accommodate a build- out population of 150, 000 wastewater treatment plant, 23 sewage lift stations, and people. 150 miles of sewer collection system with high flow
diversion facilities and an effluent outfall to the Carquinez This work included condition assessment work of the legacy Straight. part of the City, flow monitoring to identify sources of 1/ 1 and calibrate a hydraulic model of the existing collection system, This project physically inspected with discipline experts and then build upon, and expand it to identify service areas to structural, civil, mechanical, electrical, instrumentation, the new villages planned for in the General Plan. The data was SCADA) all accessible assets and ranked them based on compiled in a CIP that the City has used to develop user fees condition and risk and identified recommended and future connection fees. improvements. The project also modeled the water
distribution system and wastewater collection system to The City is now at a population of nearly 50,000 and our team identify capacity constraints and assess reliability and has helped plan, secure financing for, and design all of their sustainability improvements. Prospective water and major wastewater infrastructure improvements projects( in wastewater permit drivers for future improvements were
multiple expansion phases).
also identified along with possible funding programs. The Stantec also assisted the City with permitting, planning, project deliverables include water and wastewater master condition assessment, siting, design, and construction of the plan update documents, each compromised of thirteen original$ 61 M WWTRF. Our team conceived of the overall facility technical memorandums accessing and summarizing City' s approach, which included a combination of effluent discharge to assets with CIP. Auburn Ravine, storage, and reclamation. We also prepared the CIP projects were prioritized by risk, which was determined Master Reclamation Permit required to operate the recycled as the product of the risk of failure and the consequence of water system, arranged for the sale of recycled water to local failure. The risk of failure was determined based on
irrigators, and trained the new users to help ensure permit material, age, and standard infrastructure lifespans, compliance and protection of public health. adjusted based on condition. The consequence of failure In 2018, with continued growth occurring in the City, Stantec was ranked on the criticality of a specific infrastructure teamed with the City to design the WWTRF Phase I and II element and redundancy. Expansion projects. The expansion projects allow the City to continue to develop within the sphere of influence, while PRINCIAL- IN- CHARGE: Steven Beck, PE increasing flows in incremental stages at the treatment plant. In PROJECT MANAGER: Gabe Aronow, PE, Project Manager
2018, Stantec also completed a condition assessment and COMPLETION DATE: July 2020 wastewater master plan update.

CLIENT IIAME AND REPRESENTATIVE: City of Benicia// Kyle Ochendezko, PE, Deputy Public Works Director//( 707) 746- 4376// PRINCIPAL- IN- CHARGE: Steven Beck, PE, Principal- in- Charge kochenduszko@ci. benicia. ca. us PROJECT MANAGER: Gabe Aronow, PE ORIGINAL PROJECT BUDGET:$ 999, 013 PROJECT ENGINEER: Breanna Webb, EIT FINAL COST:$ 999, 013 SENIOR REVIEW: Mike Van Doorn, P. Eng., PMP ORIGINAL PROJECT DURATION: 05/ 2019- 07/ 2020 COMPLETION DATE: 05/ 2018 FINAL PROJECT DURATION: 05/ 2019- 07/ 2020 CLIENT NAME AND REPRESENTATIVE: City of Lincoln// Araceli Cazaraz, SUBCONSULTANT DETAILS: V& A for cathodic protection expertise. PE, Engineering Manager//( 916) 434- 2486// araceli. cazarez@lincolnca. gov NV5 for water system institutional knowledge. ORIGINAL PROJECT BUDGET:$ 258, 432 FINAL COST:$ 265, 000
ORIGINAL PROJECT DURATION: 05/ 2016- 12/ 2017
FINAL PROJECT DURATION: 05/ 2016- 05/ 2018
SUBCONSULTANT DETAILS: V& A Engineers
52 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL Exhibit "B" ATTACHMENT 3
West County Wastewater Rate City of Palm Springs Capital Repair and Study I Richmond, California Rehabilitation Plan Update and Wastewater West County Wastewater( WCW) owns and operates a
Rate Study I Palm Springs, California
wastewater collection system and water pollution. control The Palm Springs Wastewater Treatment Plant( WWTP) plant( WPCP), which currently provides wastewater was originally constructed in 1960 to treat 4. 15- mgd. Two treatment service to approximately 34, 900 accounts. Much facility expansions were completed in 1979 and 1983, of WCW' s infrastructure was built in the 1970s and is bringing 9 9 the total WWTP design9 capacity P Y to 10. 9- m 9 d for approaching or has exceeded its useful life. Stantec was average annual flow. Treated effluent is disposed of onsite hired by WCW to conduct a rate study to evaluate the in percolation ponds or is supplied to Desert Water Agency sufficiency of WCW' s existing rate revenues and to prepare for further treatment to meet reuse standards for off-site a ten-year financial plan with recommended rate irrigation. In recent years, increased water conservation and adjustments. The rate study included a revenue sufficiency re- use have resulted in lower flows to the WWTP and analysis( RSA), and the development of a
long- term increased Total Dissolved Solids( TDS). In addition to TDS financial plan and schedule of rates that enable WCW to management challenges, the State Water Resources Control fund system operations and priority capital improvement Board( Regional Board) has required the City to reduce the projects while meeting financial management policies and nutrient effluent from its discharge. targets.

The City contracted with Stantec to develop a ten- year CIP The proposed financial plan and associated rate revenue to bring the WWTP into compliance with the TDS and adjustments were based upon the revenue and expense nutrient effluent requirements, estimate the cost of information, beginning balances, financial reserve policies, implementing the plan, develop a strategy to fund the CIP, and CIP. A significant portion of the analysis focused on and propose a schedule of rates. The financial consulting evaluating alterative CIPs and capital funding strategies. team' s scope of work included developing a 10- year The proposed capital plan and rate structure have enabled financial plan to determine the annual rate revenue WCW to implement repair and rehabilitation projects and requirements, a cost- of- service analysis to evaluate cost catch up on years of deferred maintenance. allocation among customer classes, and a rate design study to evaluate alternative rate structures. As part of the Upon completion of the analysis, Stantec and CV Strategies financial planning process, we evaluated multiple CIPs and supported WCW through the procedural requirements of
their associated rate payer impacts, to support the City' s Proposition 218. Stantec presented the findings of the study negotiations with the Regional Board. This preliminary to the Board of Directors and CV Strategies prepared the scenario analysis and summary of rate payer impacts was Proposition 218 meeting notices and board packets to included in a white paper delivered to the City for use in their inform elected officials of the key elements of the Study. negotiations.

PROJECT MANAGER: Sally Van Etten, Financial Consultant
PROJECT LEAD: Matthew Freiberg, Financial Consultant PROJECT MANAGER: Venu Kolli, Principal- in- Charge COMPLETION DATE: May 2021 PROJECT TEAM: Matthew Freiberg, Benjamin Stewart, Sally Van Etten CLIENT NAME AND REPRESENTATIVE: West County Wastewater// COMPLETION DATE: April 2021 Justin Lovell, Director of Administrative Services//( 510) 222- 6700// CLIENT NAME AND REPRESENTATIVE: City of Palm Springs// Donn jlovell@wcwd. org Uyeno, Principal Engineer//( 760) 323- 8253 x8744// donn. uyeno@ ORIGINAL PROJECT BUDGET:$ 49, 907 palmspringsca. gov
FINAL COST:$ 49, 907 ORIGINAL PROJECT BUDGET: Master Plan$ 240, 000 ORIGINAL PROJECT DURATION: 11/ 2020- 11/ 2021 FINAL COST: Master Plan$ 240, 000// Rate Study$ 30, 000 FINAL PROJECT DURATION: 11/ 2020- 05/ 2021 ORIGINAL PROJECT DURATION: 03/ 2019- 04/ 2021 SUBCONSULTANT DETAILS: Stantec presented the findings of FINAL PROJECT DURATION: 03/ 2019- 04/ 2021 the study to the Board of Directors and CV Strategies prepared the SUBCONSULTANT DETAILS: No subconsultants were used on this Proposition 218 meeting notices and board packets to inform elected project. officials of the key elements of the Study.
53 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL Exhibit "B" ATTACHMENT 3
1 f
I multiple occasions. HERWIT has extensive experience with c voDe fl," ueC-)'L7J P P
the Manteca WQCF and has prepared the planning, design,

4. 1 LEAD FIRM and construction support for the following successful City of Manteca projects. No one has more knowledge and
understanding of the current operations and limitations of As the lead firm, Stantec will oversee the project, oversee the WQCF than HERWIT Engineering.
successful completion of the work, and coordinate efforts of all subconsultants. Stantec draws from a combined staff of 1, 300 professionals in California. Our key team members V& A ENGINEERING are based in Northern California( Rocklin, Walnut Creek, Sacramento and Nevada City). Manteca will benefit from a Stantec has partnered with V& A Engineering to provide highly- responsive team that values communication and sewer flow monitoring for the City' s collection system. The efficiency. The Stantec team for this contract is relatively goals of the flow monitoring effort will be to capture flow large to address the varied project requirements, including patterns from distinct land use types to develop service . team members from V& A, HERWIT, F3 and Associates, and demands, capture flow at critical points throughout the CV Strategies. The full team can be seen in the organization system for calibration of the model, and place enough chart and short resumes in section 4. 3. monitors to capture 1/ 1 contribution from different areas of the system. Stantec has planned for 17 flow monitoring

4. 2 PROJECT MANAGER PRINCIPALlocations and three rain gauges for a period of six weeks.

As presented in the Work Tasks and Additional Information IN- CHARGE sections of this proposal, there are options for reducing the Steven L. Beck, PE, will be the project flow monitoring effort to save costs or add refinement( and manager/ principal- in- charge, and he will be add costs), including figures illustrating the possible r the primary contact for the City. As a Stantec location of the monitors. Monitoring details will ultimately employee with 37 years of experience with be a City decision, however, based on our experience with Li :1 J
the preparation of wastewater master plans similarly sized systems, we feel the proposed number of and hydraulic studies and modeling, he monitors and duration will provide appropriate information meets and exceeds the requirements for his role in this for developing accurate flow projections and model project. Steve will manage the project throughout its calibration. Stantec will develop a refined list of suitable duration, and will see that the project performs within the locations for flow monitoring in concert with City staff, and agreed- upon scope, schedule, and budget. Should we be V&A will provide a desktop analysis( GIS, sewer plans, invited to an interview, Steve will conduct the presentation Google Earth, etc.) to verify suitability of primary and to the City staff. alternative manholes for flow meter installation.

Steve takes a" no surprises" approach to project F3 AND ASSOCIATES management. We will start the project out with a kick-off meeting and use that to establish the communications
strategy, as well as confirm we clearly understand the goals F3& Associates specializes in providing full land survey f
services in all rural, suburban, and urban areas throughout or the project and keep in regular contact throughout the California. They have multiple crews and support projects project. We will craft our communications approach to what meeting client needs and schedules.
best fits the City but at a minimum will have detailed
monthly meetings and progress reports.

CV STRATEGIES
Stantec is bringing CV Strategies to the project team to

4. 3 PROJECT TEAM develop public outreach materials, deliver a public Stantec is partnering with the following firms who will be information and messaging campaign, and to aid with the working on the project throughout its duration. Changes to Proposition 218 compliant noticing process. As presented the project team shall be approved by the City. in the project understanding and approach section, this work will include assessing current outreach content related HERWIT to sewer planning and rates, developing an outreach plan, hosting public workshops as needed, and preparing
HERWIT Engineering is a service focused engineering firm communication assets and Proposition 218 notices. with extensive experience in the design, planning, and
construction of all aspects of wastewater treatment plants PROPOSED TEAM MEMBERS and has been performing this work for more than 20 years.

During this time, HERWIT has designed and constructed The proposed team members, their roles, and their projects valued from$ 100, 000 to over$ 20, 000, 000 and won availability are as follows. We expect them to be involved CWEA and WEF Engineering Achievement awards on
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL Exhibit "B" ATTACHMENT 3
throughout the duration of the project. The full team can be design, biological nutrient removal. He has hands- on seen in the organizational chart at the end of this section. experience with BioWin process modeling, hydraulic

RESUMES
modeling, process optimization, troubleshooting, capacity assessment, and pilot studies. Akram also has experience with facilities planning, comprehensive evaluation, detailed REY/ LEAD TEAM LIEMBERS design of WWTPs, specification writing, and engineering services during construction. He has served as a lead
STEVEN BECK, PE design engineer of numerous WWTPs similar in size to Role: Project Manager, Principal- in- Charge Benicia. Akram recently performed a plant capacity Years of Experience: 37// Education: MS, assessment for Merced and South Truckee meadows Civil Engineering; BS, Civil Engineering and WWTPs and an overall condition assessment for Tuolumne Construction Management// Registrations:

PE# 43799 CA// Memberships: California Utilities District' s WWTP. Akram will assess the existing Water Environment Association, Water Environment Federation, WWTP needs of the Master Plan Update and develop American Society of Civil Engineers// Availability: 70% alternatives for deficiencies.

Steven has 37 years of experience and 21 years
with Stantec, most of which he has spent designing MIKE VAN DOORN, PMP, P. ENG. wastewater treatment plants and preparing wastewater
Role: Project Technical and Hydraulic Modeler
master plans and hydraulic modeling. He is a recognized Lead, Sewer Collection System Master Plan Project
leader in the wastewater design community. He has
Years of Experience: 23// Education: BS, Civil
Engineering// Registrations: PE# 43799 Alberta,
managed all phases of wastewater projects, including Canada; Project Management Professional( PMP)// Availability: 70% conceptual planning, feasibility studies, design, and
construction management. Steve has served as
Mike is a senior principal and operations leader for
principal- in- charge and/ or project manager for the City Stantec' s US Northwest Water Team in Oregon, Washington, of Lincoln WWTRF, City of Merced WWTF, City of Rio
and Idaho. He brings over 23 years of experience as a
civil engineer in the planning, design, and construction of Vista Northwest WWTF, and the Donner Summit Public water, wastewater, stormwater, and flood management Utility District WWTP Upgrade and Expansion, to name infrastructure for communities throughout North America. a few. Steve also provided support for HERWIT during
design of the Manteca WQCF Digester Improvement He has diverse experience leading teams as a Project project and Compressed Biogas Facility project:' Manager, Project Technical Lead, Senior Advisor, and Quality Manager, developing effective solutions to wet weather flow management, pipeline and pump station design, drainage
NOEL GUERCIO, PE systems, sanitary sewer overflows, water conveyance Role: Quality Assurance/ Quality Control( Sewer)// systems, and infrastructure replacement.

Years of Experience: 19// Education: MS, Construction
Management; BSc Civil Engineering// Registrations: His project experience includes more than 25 infrastructure PE# 89187 CA// Memberships: North American master planning and feasibility studies, design and hydraulic Society for Trenchless Technology, American
analysis of 15+ water and wastewater pumping stations
Society of Civil Engineers, New York Water Environment Association over 100 MGD capacity, over 100 miles of water pipeline Noel has over 19 years of experience in the review, design ranging from 1. 5" to 144" diameter, hydraulic design assessment, design, and rehabilitation of all components of of gravity sewers up to 66" diameter, numerous inverted underground water infrastructure in project engineer, project siphon systems designs with multiple barrel configurations management, and technical advisory positions. His up to 42" diameter, as well as asset management studies, experience includes all aspects of contract preparation, and other complex infrastructure projects. He is proficient contract administration, design, inspection, and with ESRI GIS software and hydraulic modeling software construction of water projects. Noel has a Master' s degree applications including MikeUrban, PCSWMM, EPA- SWMMS, in Construction Management with an emphasis on pipeline Infoworks ICM, SewerGems, WaterCAD, WaterGems, infrastructure assessment and trenchless pipeline EPAnet, and SWMHYMO. installation and rehabilitation.

AKRAM BOTROUS, PH. D., PE, BCEE
Role: Technical Lead, Water Quality Control
Facility Master Plan Project// Years of
Experience: 29// Education: Ph. D., Environmental
Engineering; MS, Sanitary Engineering; BS, Civil
Engineering// Registrations: PE# 68781 CA// Availability: 10% Akram has 29 years of wastewater treatment experience.

His areas of expertise include secondary treatment process Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL s Exhibit "B" ATTACHMENT 3
MATTHEW FREIBERG municipal fiscal analysis, and other analyses pertaining to Role: Technical Lead, Sewer Rate Study// infrastructure funding. She excels at public presentations Years of Experience: 11// Education: MESM, and explaining study findings in a way that effectively Environmental Science and Management,
informs decision- makers. Sally combines her public finance tr• - Water Resources// Memberships:

American Water Works Association// Availability: 50° consulting experience and business analysis skills to help improve service provision and to help solve pending
Matthew is a senior consultant with Stantec' s Financial infrastructure challenges from aging facilities to changing Services Practice in its San Francisco Bay Area office. environmental challenges. She recently oversaw the rates Matthew has an interdisciplinary background with an study for West County Wastewater and served as an advisor emphasis in water resources management. He blends his on Palm Springs wastewater capacity charges. environmental science background with his experience in stakeholder engagement, data management, policy
development, and financial analysis to deliver high quality

BEN STEWART
Role: Rates QA/ QC// Years of Experience: l2// Education. consultingservices to a wide rangeg of clientele. As a
MS, Environmental Engineering; BS, Civil Engineering//
financial consultant, Matthew brings expertise in developing Registrations: PE# 0050700 CO// Memberships: American financial plans, cost-of-service analyses, and designing rate Water Works Association// Availability: 25% structures for water, sewer, recycled water, stormwater, and solid waste utilities. Matthew draws his experience from Benjamin is a managing consultant in Stantec' s Financial completing over 30 studies across the United States, and Services group and is based out of the Sacramento, specializes in developing Proposition 218 compliant rates California office. He has worked with utilities throughout the for cities and utility districts in California. His recent state and nation developing long- term financial plans and wastewater rate experience includes establishing new rates cost- of- service based rates, assessing affordability impacts for West County Wastewater District; Palm Springs; to rate payers, and conducting advanced analyses of Needles; Santa Ana; and Whittier, California. Matthew is also customer characteristics and water demands. Ben is also presently engaged in an audit of a wastewater rate study Stantec' s lead consultant when addressing complex
completed for the City of San Diego. affordability issues with our enhanced Weighted Average Residential Index( WARi") methodology. His diverse
background in engineering and economics provides a
JEFF HAUSER well- rounded understanding of data analytics that is often Role: Quality Assurance/ Quality Control( WQCF)// Years integrated into economic evaluations, affordability of Experience: 43// Education: MS, Environmental
assessments, and financial planning studies.

Engineering; BS, Civil and Environmental Engineering
Registrations: PE# 31744 CA// Availability: 10%
Jeff has over 43 years of wastewater treatment plant

TARA BRAVO
planning and design experience. He has planned and
Role: Public outreach and 218 Notice and Communications Years of Experience: 11// Education: BS, Business
designed numerous wastewater treatment facilities of
Administration, Computer Arts// Availability: 25%
various complexities, including systems requiring advanced treatment( nutrient removal and membrane filtration) for Tara and her team have worked with Stantec on numerous reclamation and reuse or for discharge into environmentally wastewater rates implementation assignments, including sensitive surface waters. preparing rate payer education and Proposition 218 notices for the cities of Needles, Santa Ana, and Coachella and with In addition to completing his own planning studies and West County Wastewater. Tara excels in translating highly designs, Jeff frequently performs critical reviews and value technical information into visual materials that are engineering of studies and designs by others. He has accessible and compelling. She has served as the architect developed a high level of expertise in wastewater process of multiple, complex strategic outreach efforts that include modeling and simulation, which he employs on virtually enhanced website design and development and brand every wastewater treatment plant study and design. implementation. Her knack for designing public engagement material has created award- winning collateral SUPPORT STAFF and user- friendly government documents.

SALLY VAN ETTEN
Role: Rate Specialist// Years of Experience: 20// Education: MBA; MA, Regional and Community Planning; BA, Poli. Science// Availability: 25% Sally has researched and written over 60 economic studies for use by local government clients. Her specific past
expertise includes financial modeling and documentation of development impact fees, water and sewer rate studies,
56 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL e Exhibit "B" ATTACHMENT 3
GREGORY HARRIS ( HERWIT) TODD TILLOTSON ( F3 AND ASSOCIATES) Role: Technical Advisor// Years of Experience: 30 H Education: Role: Surveying// Years of Experience: 20 H MS, Mechanical Engineering; BS, Mechanical Engineering// Registrations: PLS# 8593 CA// Availability: 10% Registrations: PE# M028326 CA// Availability: 25%
Todd Tillotson, Survey Division Manager of F3& Associates, Gregory is a principal at HERWIT with 30 years of has over 20 years of land surveying experience. He mechanical experience in the planning and design of specializes in boundary retracement, preparing final maps, wastewater treatment systems, aeration systems, biosolids parcel maps, records of survey and corner records, as well handling and digestion, gas usage and handling, electrical as has expertise in preparing topographic surveys and cogeneration, centralized boilers, HVAC, and noise control control networks. Todd also supervises all professional facilities for municipal and industrial clients. Project survey operations assigned to government agency clients. experience with the City of Manteca WQCF includes project manager and design engineer for the WQCF Capacity KEVIN KRAJEWSKI ( V& A) Analysis, Bar Screen project, Digester Improvements
Role: Flow Monitoring// Years of Experience: 27
Project, Compressed Biogas Fueling Facilities, North and Education: BS, Mechanical Engineering// Registrations:

South Aeration Projects, and the Biosolids and Biogas Mechanical Engineer# M31744 CA// Availability: 10% Utilization Plan.

Kevin is a senior level project engineer, engineering
manager, division manager, practice leader and respected PATRICK LYTLE industry leader with over 27 years in the flow monitoring Role: Staffing Specialist// Years of Experience: 24 H Education: MBA; sector. Kevin' s expertise includes flow monitoring and MS Environmental Engineering; BS Physics// Memberships: PE# 36369 analysis of inflow and infiltration( 1/ 1) into collection WI; Project Management Professional( PMP) Availability: 10% systems, including development of synthetic 1/ 1 hydrographs Patrick has over 20 years of experience helping and estimation of peak wet weather flows for design storm organizations enhance business practices, effectiveness, events. and efficiency. He provides expertise in the areas of staffing assessments and benchmarking, strategic planning, best

EMILY EPPINGER
practice assessments, capital project and program delivery Role: Environmental Specialist// Years of Experience: 16 improvements, lifecycle planning, asset risk scoring, and Education: BS, Wildlife Management// Availability: 10%
performance management. He' s provided these services to municipal, federal, and industrial clients throughout the Emily specializes in the preparation, writing, and reviewing United States, Europe, Asia and the Middle East. of various documents including state and federal environmental permit applications, California Environmental

RICHARD STOWELL
Quality Act and National Environmental Policy documents, as well as biological resource evaluations and
Role: Permitting Specialist// Years of Experience: 48 H Education:
assessments. She has extensive experience performing
Ph. D., Civil Engineering; MS, Environmental Engineering; BS, Civil environmental compliance tasks in support of projects
Engineering// Registrations: PE# 38812 CA// Availability: 10°k associated with water conveyance and treatment, gas,
Since 1973, Dr. Richard Stowell has specialized in water electric, hydro, and wind power. quality related engineering since 1973. His experience
includes wastewater treatment, wastewater disposal, and the planning, environmental assessments, and permitting associated with wastewater projects of all types( municipal, industrial, commercial, and agricultural). Dr. Stowell
specializes in wastewater facilities permitting, planning, design, and preparation of environmental impact
assessments.

BREANNA WEBB
Role: Hydraulic Modeling// Years of Experience: 6
Education: BS, Civil and Environmental Engineering
Registrations: EIT# 154937 CA// Availability: 90%
Breanna has extensive hydraulic modeling experience and was the lead hydraulic modeler for the Lincoln, Merced and Dixon wastewater collection system sewer master plans.

She has experience in planning, permitting, and design of wastewater discharge and recycling projects, including
developing permit related studies and reports, recycled water feasibility studies, and alternatives analyses.
57 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL to Exhibit "B" ATTACHMENT 3
rJL' ? ejLI Zc):v10hI ol G C)7h' ll'
We have assembled a team of highly qualified professionals to achieve your project goals. The organizational chart presented below illustrates how our team will be organized and managed. Our team has been selected based on relevant experience and proven capabilities. We have also considered each team member' s time commitments and availability to perform their assigned tasks.

Resumes are provided for key staff, shown in bolded, orange text.

City of Manteca
Quality Assurance/ Principal- in- Charge Quality Assurance/ Quality Control ( WQCF) •••• Project Manager Quality Control ( Sewer) Jeff Hauser Steven Beck Noel Guercio
II
I
Water Quality Control Sewer Collection System Sewer Rate Study Lead Facility Master Plan Master Plan Matthew Freiberg
Project Technical Lead Project Technical and Rate Specialist Akram Botrous Hydraulic Modeler Lead Sally Van Etten
Permitting Specialist
Mike Van Doorn
Rates QA/ QC
Richard Stowell Hydraulic Modeling Ben Stewart
Technical Advisor
Breanna Webb
Public Outreach and
Gregory Harris( HERWIT) Flow Monitoring Prop 218 Assistance Staffing Specialist
Kevin Krajewski( V& A) Tara Bravo( CV Strategies)
Patrick Lytle Surveying
Environmental Specialist
Todd Tillotson( F3 and
Emily Eppinger
Associates)
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL Exhibit "B" ATTACHMENT 3
PROJECT GOALS information and understanding of the City' s scheduled CIP through 2026. In tandem with the completion of the
Stantec' s approach to wastewater master plans varies, Wastewater Master Plan, a final rate study will be prepared. depending on the City needs with respect to growth, phased The final rate study will include a cost- of-service analysis capacity improvements and/ or maintenance, and the City' s that will be informed by the findings of the master plan. The interests in collecting new data or making assessments City also desires support navigating the Proposition 218 based on existing data. Stantec' s team adjusts to the process. needs of the client and the City of Manteca has made their goal clear: The City seeks to develop a comprehensive
Wastewater Master Plan and Sewer Rate Study( Interim WATER QUALITY CONTROL FACILITY Final), with a focus on the sustainability of the City' s The most recent major expansion of the Water Quality capability and capacity to convey and treat incoming Control Facility( WQCF) was designed in 2001/ 2002 and wastewater flows. The Plan should provide approaches and built over the subsequent years through 2007. The design strategies that provide long- term reliability. It will anticipate capacity of the plant was 9. 87 Mgal/ d. At the time the plant and plan for, to the extent possible, effects on the City' s was designed, there was no permit requirement for effluent wastewater enterprise from changes in regulations, drought nitrogen( nitrate+ nitrite). Subsequently, an effluent nitrogen conditions, and increased labor, material, and construction limit was added to the permit and plant operations and
costs.
capacity have been greatly impacted in an effort to meet the With this understanding of the City' s goals, Stantec will new requirement. follow a systematic approach to completing the master plan and rate studies, resulting in a wastewater CIP and Stantec/ HERWIT have been assisting the City in the comprehensive financial analysis for the City. Our approach, evaluation and design of aeration and control modifications detailed further in this section of the proposal will begin to help meet the nitrogen limit since 2012. In July 2021, with confirmation of the final approach to this work with Stantec/ HERWIT completed a Final Draft Capacity City staff— it' s paramount that we're on the same page to Assessment for the WQCF. That report established that the control budget, schedule and to help ensure that City current facilities are overloaded with respect to nitrogen and expectations are met. We consider the approach described developed a comprehensive program of interim herein a template which will evolve to meet City needs. improvements that can be implemented in the immediate future( before Master Plan implementation) to improve
nitrogen removal performance and allow continued growth PROJECT UNDERSTANDING within the City from a current wastewater flow of 7. 13 Mgal/ d( as of August 30, 2020) up to 9. 23 Mgal/ d.

RATE STUDIES
The City of Manteca owns and maintains its sewer
The City' s existing permit for discharge into the San Joaquin collection system and treatment facility. Operations, River allows for flows up to 9. 87 Mgal/ d currently, with maintenance, and capital investment in infrastructure is provisions for increase to 17. 5 Mgal/ d upon approval of the funded predominately through collection of rate revenue. plant' s ability to comply with receiving water limitations However, the City' s last wastewater rate study was last mainly temperature impacts). At the current growth rate, completed in 2008 and the City has not adjusted rates since the 17. 5 Mgal/ d flow is estimated to be greater than what is 2010. The City desires an evaluation of its existing sewer required to serve the build out population estimated in the rates and recommendations for needed updates to verify
City' s General Plan.
rate revenues are sufficient to maintain system function and The following outlines our approach to the Tasks identified meet regulatory requirements. in the RFP. A detailed work breakdown structure( WBS) for We will use our industry- leading financial model, the these tasks is provided in the Cost Proposal.

Financial Analysis and Management System( FAMS), to TASK 1 - KICK- OFF MEETING conduct the financial analyses for the City' s wastewater enterprise. The City will benefit from Stantec' s use of this Stantec will conduct a project kickoff meeting with City staff unique proprietary tool to evaluate multiple CIP alternatives, to review the scope of work and the initial alternative optimize capital funding, and test various other scenarios process considerations. This meeting will be a collaboration as part of the rate studies. of ideas to solicit input and encourage a partnership Because the City will be concurrently developing a
between engineering and operations personnel on project wastewater master plan, the City has requested that the rate related topics. Stantec will develop and maintain a detailed study be delivered in two phases. First an interim rate study project schedule using MS Project and submit updates
will be prepared based on the City' s current financial monthly. Stantec will also conduct monthly progress 59 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL 12 Exhibit "B" ATTACHMENT 3
meetings with City staff. Meeting minutes will be prepared Capital Planning. The FAMS model provides a valuable and distributed to the meeting participants. capital planning tool which we will use to evaluate the City' s projections for capital improvements, and to
Stantec will provide quality assurance and quality for
evaluate the impacts of alternative projects, costs,
project, which includes peer review of all project schedules, and funding sources. One key feature of FAMS deliverables. Documents shall be reviewed for correctness, is a robust capital funding module that allows for detailed completeness, and coordination with other documents and analysis and user control over potential capital funding between disciplines.
options. This module allows the user to either specify
detailed funding rules for individual projects, or to
TASK 2 - INTERIM SEWER RATE STUDY generalize funding rules to calculate capital funding plans based on specified rate adjustments. Under both
The following section outlines our detailed approach for the approaches, the FAMS model will develop a funding plan, completion of the Interim Sewer Rate Study. The goal of this including identification of the amount, timing, and type of task is to establish a short- term rate plan that enables the borrowing required as appropriate. We will examine the City to maintain system functions and meet regulatory use of debt versus cash to fund capital improvements requirements while the Wastewater Master Plan is being and build a financing plan that adheres to existing developed. management targets and that supports a proper balance of debt coverage and rate stabilization over the planning Task Initiation and Review of Background Information period.

To initiate the Study, we will submit a data request to the Reserves. Adequate reserves are fundamental to
City, that will include all documentation that is needed to achieving financial stability and can help to avoid sudden develop an updated five year schedule of sewer rates. In or disruptive rate adjustments in the face of
addition to data acquired through the Wastewater Master unanticipated operating expense increases, capital needs, Plan development process, requested data will include but or changes in demand. We will examine the City' s current may not be limited to current sewer rates, prior rate study reserve policies and balances while considering financial documentation, the currently programmed CIP for sewer
objectives, the age and condition of the City' s
improvements through 2026, regulatory documents,
infrastructure, and industry best practices. This review is financial policy documents, bond official statements,
intended to prompt discussions with City staff and key
historic and projected budgets and actuals, customer billing decision makers about financial sustainability and will be information, an asset register, and any other pertinent data used to inform potential modifications and scenario
as needed.
analyses.

Shortly after reviewing these documents, we will conduct a Key Performance Indicators. Another important feature of Rate Study Kick- Off meeting( or conference call) with staff the financial model is the evaluation and visualization of to: financial key performance indicators( KPIs). We are very Confirm goals and objectives of the Study
Discuss key issues, roles, and responsibilities
Assemble and review the previously discussed data CIP Funding Sources Finalize the project schedule, including milestones and 70M deliverables 60M
50M
Follow- up calls will be coordinated with staff to help 40M L1fi-
establish a full understanding of all data received and to 30M identify any supplemental data requests.
20M I 1
Develop Short- Term Financial Plan
0M
We will use our industry- leading financial model, the
Financial Analysis and Management System( FAMS), to Debt Operating Capital Reserve Fund a Bond Proceeds develop an initial five- year financial management plan, run sensitivity analyses, calculate projected annual revenue Figure 1. CIP funding Sources
requirements, and determine proposed rate adjustments to meet near-term funding needs. As part of the analysis, we familiar with the criteria used by rating agencies, such as will examine historical operating expenses, growth and new matrices and scorecards to evaluate the financial water use trends( as available), alternative capital spending health of public utilities, and we can incorporate the KPIs levels and funding sources, debt service coverage ratios, of interest into the model. These KPIs will serve as levels of operating and capital reserves, and other financial important benchmarks in comparing scenarios and policies that drive the revenue requirements of the City. developing a well-informed, sustainable financial plan that meets City objectives.

I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER
60 RATE oSTUDY PROPOSAL 13
Exhibit "B" ATTACHMENT 3
Five- Year Rate Plan. After incorporating baseline data, meeting, we will incorporate feedback and prepare including budgeted revenues and expenses, existing debt modifications or alternative scenarios to be reviewed with service, and forecasted CIP, we will begin the process of Staff, as appropriate. We will then participate in a meeting developing the five- year plan by forecasting revenues with the City Council to clearly explain the findings and generated under the currently adopted rates. This recommendations of the Study, and to allow the Council diagnostic view will allow for evaluation of the to vote on proposed plans and rate structures. This will be sustainability of the plan without rate increases with a the City Council meeting wherein a vote will be held to focus on projected fund balances, debt service, and other distribute public notifications and commence the 45- day KPIs relative to established targets and existing bond public comment period. Finally, we will make a final covenants. This preliminary analysis will illustrate the presentation and answer questions at the Proposition 218 period over which the utility could continue to operate public hearing before protest votes are counted and City while meeting targets without needing immediate rate Council ultimately votes to approve or reject the increases. recommended rate schedule.

In the event that the revenue requirements identified in the model exceed projected revenues under current rates, we Interim Report Development will calculate an updated schedule of interim rate Our reports are written to be succinct, but also to include the adjustments over a five year period. The schedule of rate appropriate level of detail of the assumptions and adjustments will be developed through scenario analyses methodology used in our analysis so that our report can with City staff to meet the operating and capital needs of serve as an administrative record in the event that rates are the wastewater enterprise. The five- year rate plan will be ever challenged. The City will gain long-term value from a the key focus developing a schedule of interim rate
report that clearly and comprehensively documents the
adjustments for potential adoption with consideration of approach, methodologies, data, assumptions and results of the substantive and procedural requirements of
Proposition 218. the Study. We will prepare three report drafts for varying levels of review and comment, beginning with a preliminary Our project scope assumes that all data will be provided draft for staff comments and revisions. Once we incorporate by the City in a readily available electronic format. We also staff feedback, we will provide an administrative draft for assume that all revenues, expenses, capital plans, Council review prior to presenting final results and customer usage, billing, and other customer related data recommendations. Finally, we will incorporate additional will be provided in an editable digital format( e. g. staff feedback before submitting the final report.

Microsoft Excel, Microsoft Access, etc.).

Sensitivity Analysis. We will also conduct sensitivity
Updated Rate Implementation
analyses based on alternative growth and usage
Upon completion of the interim rate study analysis, our team projections, price elasticity, cost escalation factors, will support the implementation of the proposed rates by borrowing costs, and other variables that could affect the working with City staff to confirm the adopted rates are financial performance of the City. These key scenario correctly loaded into the City's utility billing software. drivers will be incorporated based on our industry TASK 3 - FINAL SEWER RATE STUDY experience and discussions with City staff to identify the most important factors specific to your system. The The following section outlines our detailed approach for the FAMS model is uniquely equipped to enable dynamic completion of the Final Sewer Rate Study. The goal of this evaluations of what-if scenarios in an interactive manner task is to establish a long- term financial plan to integrate the to quickly evaluate and communicate the financial findings of the Wastewater Master plan, including impacts of alternative projections and financial decisions. implications for projected changes in customer account growth, change in water usage patterns, and any recent or Adoption of New Rates. Upon completion of the analysis, our pending state legislation into the financial plan that was team will assist the City in preparing the documentation, develop in Task 2. 0. Additionally, this task will include a notices, public presentations, and City Council hearings comprehensive review of the rate structure, a cost- ofconsistent with the procedural requirements of Proposition service analysis, and recommendations for updates to the 218 as described in Task 8. City's wastewater rate structure.

Presentations to Council. We will plan to present to City Updated Long- Term Financial Plan Council, and the public up to three times during the course In this task we will build off the financial model developed of the Interim Rate Study. Near completion of the Study, during the interim rate study to incorporate findings of the we will meet with City Council to present preliminary Wastewater Master Plan. The financial model will be recommendations regarding the financial plan and updated to reflect new projections of customer growth and proposed rate increases. This preliminary meeting will be any identified changes in wastewater production or
intended to inform the Council and to solicit feedback treatment requirements. We will work closely with Staff and regarding objectives, decisions, and policies that could the Engineering team to develop a capital plan that meets impact the final recommendations. Following this the City' s infrastructure needs but also considers the 61 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL la Exhibit "B" ATTACHMENT 3
recovery and this information will be used to inform the rate structure analysis in the subsequent task.
r
t T It
r Figure 3. Project Management Activities 9 1 9
3 a
Sewer Rate Design
Based upon the information gathered and the analysis done in the preceding tasks, our team will develop up to three rate Figure 2. Revenue Requirements
alternatives. We are well versed in the range of potential long- term impacts to rate payers and the political feasibility rate structures and will review the pros and cons of the of the adoption of the rate plan. The long- term plan will also proposed rate structure alternatives. Our rate structure incorporate the costs of any incremental 0& M or additional evaluation will include an examination of revenue volatility, staffing that were identified as part of the implementation customer ease- of understanding, affordability, of these capital projects.
administrative requirements, and potential limitations of the City' s billing system. We will provide an overall impact analysis for each customer class, as well as specific bill Cost- of-Service Analysis impacts at various. consumption levels for each rate The cost-of-service module of our modeling system allows structure alternative for which rates are calculated. Detailed for the revenue requirements of the sewer system to be customer impact analyses will be provided for all customer equitably allocated to each of the City' s customer classes. classes, and high- level result summaries will serve as The system' s costs are functionalized to defined processes, important informational materials in public presentations. which are then allocated to each customer class and/ or land use based upon the respective demand in terms of the Throughout this process, we will work closely with City staff average amount of flow or other system demand to determine the preferred approach to recover rate characteristics. This process is intended to evaluate inter revenues, while minimizing the impact to your customers. At and intra- class equity in accordance with the proportionality the end of this task we will produce a five- year schedule of requirements of Proposition 218. rates with the preferred rate structure escalated by the proposed rate adjustments developed in the updated
We will identify the most appropriate industry- accepted cost financial plan. Our recommendations and the presentation of service allocation methodologies, such as those defined of methodologies and results will give particular by the Water Environment Federation( WEF) Manual of consideration to the substantive and procedural Practice 27: Financing& Charges for Wastewater Systems requirements of Proposition 218.

MOP 27). Based on the available data and unique customer characteristics of the City, we will customize the cost-of- Rate Survey service analysis to employ the identified methodologies and To gain a better understanding of the regional rate market, concepts best suited to your system and operations.
our team will complete a rate survey, of six to eight other At the conclusion of the cost-of- service analysis, we will similar cities or agencies located in the Central Valley. This compare the resulting allocation of revenue requirements to analysis can help inform the customer acceptability of rate the revenue generated by the current rates for each increases and is often necessary to address questions from customer class. We will review these findings with City staff key stakeholders, including elected officials, related to how to confirm our understanding and analysis. In the event that your rates compare with peer communities. Additional
the current revenue recovery levels do not align with the state- wide comparisons will be incorporated into the survey results of the cost- of- service analysis, we will propose as appropriate.
changes to the class-specific allocations of revenue
Adoption of New Rate
We will build off the momentum from the interim rate study and implement the same process to present the findings of 62 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL 15 Exhibit "B" ATTACHMENT 3
the final rate study to City Council and deliver a similar defined set of users that are approved by the City. Given the Proposition 218 notification process. However, we online nature of the model, users can utilize the capabilities recommend hosting additional public outreach meetings in of the model without the risk of accidentally modifying advance of the Proposition 218 hearing for the final rates. formulas and producing erroneous results.

Given the likely expanded CIP and the updates to the rate structure, it is possible that the final rate study may include With the online version of FAMS, we are able to leverage more dramatic changes to customer rates. Holding 21 st century tools and technology to realize productivity additional public outreach workshops can help the City gains, reduce risk, enhance transparency, and keep pace demonstrate the need and benefit of the changes to the with current demands. This innovative tool provided by our rates, enhance public understanding, and ease the support team is easy to navigate and will allow your team to monitor of the proposed rates. financial performance, evaluate changes to your capital plan, and make adjustments to core assumptions that
Update of Municipal Code change over time, including shifting economic conditions, Our scope is limited to the update of the sewer rates. Upon revised industry standards and statutory/ regulatory completion of the rate study, our team will support the requirements, shifts in management and operations, and
update of the applicable section of the City of Manteca policy decisions by elected officials.

Municipal Code, Title 13, that pertain to sewer service TASK 4 - WASTEWATER MASTER PLAN charges( e. g., rates). This work will be subject to review by the City Attorney( Stantec does not provide legal advice). As The following section outlines our approach for completion part of this process, we will also provide assistance with of the Wastewater Master Plan. notification for public review, and assistance through the adoption process with the City of Manteca Planning Wastewater Collection System Commission and City Council.

Data Review& Collection
Final Report Development Complete an organized and systematic review of the The final report will be an update of the report from the existing data including the existing master plans, Interim Rate Study, using the same format, but will reflect condition assessment evaluations, WQCF evaluations, the changes to assumptions, the CIP, operating budget, and base maps, record drawings, GIs shape files and land use provide a new recommended schedule of rate increases. plans.

This report will also include new sections outlining the Collect and review system performance and condition approach and methodology used during the cost-of-service data including flow data, historical Sanitary Sewer analysis, the rate design, and the findings of the rate survey. Overflows( SSOs), Condition assessment data, 0& M maintenance records, sewer cleaning schedules, interior Updated Rate Implementation and exterior point repairs, etc.

Upon completion of the final rate study analysis, our team Perform field survey of approximately 50 sewer manholes will support the implementation of the proposed rates by more or less, depending on need and available budget) working with City staff to confirm the adopted rates are and capture missing information such as elevations, size, correctly loaded into the City' s utility billing software. material, condition photos, and GPS data points at each sewer manholes. Data from the surveys will be used as
Online Model development an important input to the hydraulic model, to update the Throughout the study, we will populate and customize our project GIS, and ultimately for the City to update their GIS online version of the FAMS financial modeling tool to match data. your data requirements and evaluate the appropriate" what Conduct limited site observations of the critical sewer ifs' as part of developing a sustainable financial plan with manholes on trunk lines and other critical sewer mains optimal capital funding strategies. Initial access to the for the assessment of constraints such as site model will be included through the end of the fiscal year of accessibility, environmental concerns, 0& M concerns and the final rate study portion of the analysis, subject to a design constraints. separate licensing agreement. Access will include training Conduct onsite comprehensive and detailed interviews and user support. Ongoing FAMS subscriptions for with City staff to capture their knowledge, needs, subsequent fiscal years are also available upon request. concerns and goals for the wastewater infrastructure.

This will be a key step, possibly the most important, to This easy to navigate online version of the model retains all completing the existing system performance and data, functionality, and capabilities of the underlying Excel developing updated O& M procedures. based model, to allow for additional performance
monitoring and scenario analysis to evaluate the potential Hydraulic Analysis& Model Development impacts of changes in revenues, expenses, capital Following data collection, the next critical steps of the spending, or any other variable included in our model. FAMS project are developing design flows, hydraulic criteria and also allows for simultaneous access to the model by a
land use followed by model software selection, build,

I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER
63 o
RATE STUDY PROPOSAL 16
Exhibit "B" ATTACHMENT 3
calibration and assessment of the system to both current discharge. Equivalent populations will be assigned to and future build out conditions. catchments. Stantec will review sub-basin boundaries with the City prior to allocating flows to the model. All Flow Monitoring. Stantec has partnered with V& A
facilities such as lift stations will be included in the model Consulting Engineers, Inc. to deliver the flow monitoring based on as- built drawings to reflect the physical system for the City of Manteca system. The goals of the flow
as close as possible. The Existing Model network will
monitoring effort will be to capture flow patterns from then be verified as well as the lift station components distinct land use types in order to develop demands, against available as-built drawings and other available capture flow at critical points throughout the system for data source. The downstream network tracing tool will be calibration of the model, and place enough monitors to used to confirm the connectivity. Using WQCF and Flow capture 1/ 1 contribution from different areas of the Monitoring data, Stantec develop sewers hed- specific system. Stantec has planned for 10 flow monitoring flow generation characteristics such as average dry locations and one rain au a gauge for a period of four months. weather flow( ADWF) sewage generation, diurnal sewage Based on our experience with similarly sized systems, we patterns for weekdays and weekends, basef low and feel this number of monitors and duration will provide groundwater infiltration( GWI), rainfall dependent inflow ample information for demand development and and infiltration( RDII) and peak wet weather flow( WWF) calibration. Stantec will develop a list of suitable rates throughout the system. We will utilize this locations for flow monitoring in concert with City staff, information to assign the Dry weather flow( DWF) unit and V&A will provide desktop analysis( GIS, sewer plans, hydrographs for each catchment applied on a per capita Google Earth, etc.) to verify suitability of primary and basis into the model. Once the initial model structure is alternative manholes for installation of a flow meter. developed, the model will then be debugged until it can Design Flows and Hydraulic Criteria. Hydraulic criteria iterate successfully to a valid solution within numerical set the metrics by which the collection system is solution tolerance limits. evaluated and dictates the requirements for both the Model Calibration. It is always necessary to verify current and future infrastructure of the system. It model simulations match actual sewer performance by includes determine dry and wet weather flow conditions, properly calibrating any model intended to assess the design storms from historical rainfall data and estimates hydraulic capacity of an existing system. This is even for inflow and infiltration into the sewer system. Stantec more so when such a tool will form the basis of will leverage design criteria and lessons learn from significant investment and asset management decisions. across the US to aid in the selection of the best criteria for the City. Once the model is built, we can also help the The first calibration efforts will involve dry weather flows, City to determine the most cost- effective level of services where the unit hydrographs( diurnal coefficients) are for future updates. For example, we can determine routed through the system and compared to measured improvements required that no SSO occurs during 2- year, flow data for different stations in flow monitoring report. 5- year, and 10- year storms. That will help City to In areas of high groundwater table fluctuations, there can determine which criteria is the most cost- effective level be differing degrees of" dry weather flow"—so Stantec will of services for their rate payers. pay heed to this.

Land Use. To understand current conditions and to plan The DWF is characterized by base flow loading and by for future conditions it is important to understand the diurnal residential/ commercial wastewater generation. current and future land uses. Stantec will work with the The base flow sewage is dependent upon the land area of City to identify areas of new development and other new each catchment and has constant loading throughout the developments. In addition, we will use local planning day, while residential/ commercial wastewater sewage documents, general land use, and other information generation are based on per capita( equivalent collected to assess potential growth and apply that to population) loads within each catchment. Catchments projected sewer flows and the hydraulic model. will be assigned the equivalent population value, an amalgamation of residential and employment
Wastewater Model Development. This task will involve
populations.
developing a wastewater model to simulate the To distinguish between the loading characteristics of performance of the existing sanitary system. The model weekdays and weekends, different diurnal patterns will be will be constructed by importing the available GIS- based applied in the model. The calibration of the model is an system data and newly collected survey data into the iterative process, the accuracy of each iteration being selected software package. Sub- basins will be re- determined qualitatively by a visual inspection and delineated along parcel boundaries as to accurately quantitatively through an analysis of the minimum, define the areas tributary to flow meter locations. These maximum, and average flows for the period. Once the catchments will be linked to the network at the nearest modeled flow for DWF is calibrated to within acceptable downstream manhole that conveyed the catchment' s full
64 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL l7 Exhibit "B" ATTACHMENT 3
tolerances, flow depths and velocities from the flow 11 ' .. 1•_ l.. I .. t 14tl3 monitor data will be compared to the modeled results.

AO I-_ -
pMN
The second stage of the calibration will deal with II calibration of the model to rainfall wet weather flow conditions. These situations often represent the most
t
extreme cases of system loading. Extraneous flows, l
depths, and volumes will be determined from the
The
volume
as
estimated
a
effective
percentage
data
to
flow
the
by
for
determining
area
total
monitoring
each
of
for
the
rainfall
wet
each
physical
weather
data,
the
volume
manhole
ratio
as
sewershed
flow
well
from
of
will
extraneous
as
event
flow
be
cor
area(
established
monitoring
recorded.
initially
flow
i It4
r j
data). V
The WWF model will be calibrated using Initial values and I 1 adjusted for each flow monitor sewershed individually, in LJ an iterative process. Different catchment areas will be Figure 4. Example Model Calibration calibrated to reflect different RDII responses. Other
hydrologic parameters will then be modified until the Future System Assessment and Master Servicing model matches the total volume and shape of the Plan. The existing system assessment represents the monitoring data during the storm event based upon current state of the collection system. This will change available flow monitoring data. Once the modeled flow over time through the influences of component for WWF is calibrated to within acceptable tolerances, deterioration, capital investment, changing usage flow depths and velocities from the flow monitor data will patterns, and ongoing growth and development. Once the be compared to the modeled results.Several graphs and existing system model has been developed, calibrated, figures will be presented in the report to summarize the and reviewed, Stantec will begin the process of extending calibrated dry weather flow( DWF) and WWF model of the model to account for future scenarios and buildresults for major stations in flow monitoring report. out. The existing model will be further developed into a Future System model to represent sanitary catchments
Existing System Assessment. The calibrated model for build- out future development, using population will then be used to evaluate the level of service( LOS) densities and projections in the City's Land Use Plan. performance of the existing sewer system under Dry DWF patterns and rates will be applied, and WWF Weather Flow( DWF) and Wet Weather Flow( WWF) parameters will be established based on industry conditions using the selected design storm event flow standards for I& I in new developments. Servicing scenarios. We will discuss and confirm the system infrastructure will be added to the model, necessary to performance metrics or LOS criteria that will be used to convey future flows to the City's WQCF, either through examine the system performance( metrics that assess existing infrastructure or via new conveyances. The initial pipe capacity, manhole surcharging, lift station capacity, servicing strategy for future growth will align growth etc). Analysis of the existing system hinges on two areas with logical servicing points in the City's existing important factors: 1) Identifying issues and deficiencies system. The model will then be run as an initial scenario in the current system 2) Optimizing overall operation of for DWF and WWF to" test" the impacts of growth on the the current system. Identifying current issues is
existing system.
predicated upon clear and frequent communication
between Stantec and City engineering and operations Stantec will develop a future scenario that captures all staff. Stantec will identify all current deficiencies based expected growth and identifies the improvements necessary on the established planning criteria and develop to serve that growth, while identifying the reasoning and improvement projects to address each deficiency. GIS recommended timing for each improvement. Stantec will information such as pipe material and age will also be identify drivers for improvements, and prioritize the CIP used to recommend a rehabilitation and replacement based on the most likely asset to fail. For these program in conjunction with available condition improvements, it is important the true driver is identified, assessment and CCTV investigation. Beyond an issue- by- and timing is based on that trigger event. By identifying issue recommendation schedule to address current triggers, the City will be able to pinpoint which areas or deficiencies, the existing system analysis will include a pipes may need additional investigation. This will allow the system-wide look at how flow is conveyed and how one City to have a full assessment of the needs for a future sub basin relates to the next. system, while still having a prioritized list of improvements that can be implemented or studied further given specific growth or development.

I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER
65 o
RATE STUDY PROPOSAL la
Exhibit "B" ATTACHMENT 3
Water Quality Control Facility affordable and sustainable wastewater management solutions is needed.

Key Issues
Approach
Key issues that must be addressed in the Master Plan are In the Capacity Assessments mentioned above, Stantec/ summarized below:

HERWIT recommended interim improvements to allow
1) A critical criterion for developing the Wastewater Master flows up to 9. 23 Mgal/ d. Therefore, the Master Plan will Plan is the average wastewater flow when the City is fully primarily address expansion beyond that capacity. Although built out. According to the City' s General Plan, the buildout previous planning and the existing discharge permit population is expected to be around 206, 000. With a 2020 envisioned the next expansion would be to a capacity of population of about 87, 000, the average wastewater flow 17. 5 Mgal/ d, that capacity is not likely to be required within was 7. 18 Mgal/ d, indicating a possible buildout flow of twenty years and may exceed the City buildout flow. around 17 Mgal/ d, which is slightly less than the 17. 5 Because of the high costs of building and then maintaining Mgal/ d limit indicated in the existing discharge permit. facilities before they are needed, Stantec would work with Therefore, if current growth rates continue, the buildout the City to define an affordable phasing plan. The phasing condition could be reached in about 20 years. Since 14. 7% plan will be dependent on planned growth rates within the of the current capacity of the WQCF is contracted to the City City, City of Lathrop participation, and confirmation of the of Lathrop, the 20 year horizon is contingent on the extent buildout flow. Stantec will work with City staff to develop the City of Lathrop participates in expansion of the WQCF. appropriate planning criteria, including a possible range of Appropriate planning criteria must be developed for City growth rates. Our approach is to focus the planning on the growth rate and the timing and amount of flow occurring at 17. 5 Mgal/ d permitted expansion with coincidentally buildout to be used as the basis of the Master Plan. A range accommodates to approximately the General Plan buildout of possible growth rates and City of Lathrop participation population of 206, 000. can be considered.

The Master Plan will be based on wastewater flows and
2) Plant design and operation are governed by permit loads to be determined for existing and future development. requirements for effluent disposal and/ or reuse. The current Having just completed a flows and loads analysis for the permit for discharge into the San Joaquin River requires Capacity Assessment, Stantec will be poised to efficiently effluent cooling for discharges over 9. 87 Mgal/ d. Since extend this evaluation for the purposes of the Master Plan, effluent cooling would have high capital and operating costs including more detailed evaluation of flows and loads due and take up significant land area, and since wastewater to dwelling units, businesses, and other development. reuse is highly beneficial in California, a reuse alternative Future flow and load projections will consider alternative should be considered( see below). scenarios based on levels of water conservation. 3) The Public Project Infrastructure Group( PPIG) has Each portion of the WQCF will be analyzed separately with proposed and previously entered an Exclusive Negotiating respect to existing issues( based on input from City staff), Agreement with the City to discharge WQCF effluent to the capacity, alternatives for expansion, and appropriate Delta Mendota Canal for subsequent agricultural reuse. The phasing. Improvements to correct existing issues, enhance Department of Water Resources is in support of this project. reliability, and extend the capacities of existing facilities will This option would eliminate the need for effluent cooling be developed. Alternatives for expansion will include and the costs and land requirements associated with it. expansion in- kind as well as potentially more reliable, costeffective, and/ or smaller footprint options. Differences in 4) Regardless of discharge or reuse option, nitrogen facilities requirements for the respective disposal/ reuse removal will remain a key concern for the WQCF. options will be identified. Primary, secondary, and tertiary treatment facilities and solids handling facilities are 5) There is pressure for development and other possible discussed briefly below. The scope and fee section uses for lands that may be needed for WQCF expansion.
attached to this proposal provides additional detail.

Therefore, a small footprint for WQCF expansion would be highly beneficial. The WQCF currently uses primary clarifiers for removal of settleable solids in the raw wastewater. Because of the 6) Wastewater flows and loads from equivalent dwelling relatively large footprint and cost of primary clarifiers, units and other types of development as well as City of Stantec proposes to consider alternatives for filtering the Lathrop participation must be defined to allow appropriate raw wastewater for flows beyond the capacity of the
planning.
7) A plan for the logical expansion of the WQCF in phases that protect the City' s long- term needs while providing 66 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL 19 Exhibit "B" ATTACHMENT 3
existing clarifiers. There are several proprietary filtration disinfection( UV) doses are needed, saving footprint and systems available for this use. power costs. Another very important benefit of the MBR is that it provides the pretreatment needed for subsequent The secondary treatment system includes aeration basins, reverse osmosis( RO), which could be important for future secondary clarifiers, and ancillary facilities. Stantec/ HERWIT salinity control. presented a detailed evaluation of these facilities in the Capacity Assessment. Capacities were determined and For the secondary treatment alternatives not involving MBR, improvements were recommended that could be expansion of the existing tertiary filtration system would be implemented relatively quickly without new structures or required. major new mechanical equipment systems. The Master Plan analysis will consider additional alternatives for The existing UV system has not performed well, causing improvement and expansion, which will require new several permit violations. The existing system is difficult to structures and mechanical systems. Four main alternatives clean, operate, and maintain. Alternative UV designs will be will be considered: 1) expand in- kind, 2) intensification of evaluated, noting that lower UV dosing would be required existing facilities to increase capacity and improve after MBR secondary treatment. performance followed by expansion with the same type of The solids handling system includes thickening, anaerobic facilities, 3) expand with membrane bioreactors( MBRs), and digestion, and sludge dewatering using centrifuges. The 4) intensify existing facilities and expand with MBRs. In each centrifuges are costly to operate and maintain, so other case, the impacts of future importation of food waste to the dewatering alternatives will be evaluated. Stantec/ HERWIT WQCF anaerobic digesters and the use of sidestream
designed the existing compressed natural as CNG
treatment to remove nitrogen from the sludge dewatenn
9 9 P 9 ( )
9 9 9
facilities that make beneficial use of the anaerobic digester return flow will be considered.
gas and would evaluate the best means of expansion.

Intensification alternatives for the existing secondary Evaluation of sidestream treatment systems to remove
treatment system would include: nitrogen from the sludge dewatering return flow would be coordinated with any evaluation and design occurring on an 1) Membrane Aerated Biofilm Reactors( MABRs). This would expedited basis as previously recommended in the Capacity involve enlarging existing anoxic basins to improve Assessment completed by Stantec/ HERWIT. denitrification, while at the same time increasing nitrification capacity via attached growth on the membranes to offset CIP Development and Final Report the loss of aerobic volume.

We propose to redo and/ or repackage the existing master 2) Integrated Fixed Film Activated Sludge( IFAS). Plastic plan material, resolving the existing plan deficiencies biofilm carriers and retaining screens would be added to the identified in the RFP, adding the new condition assessment existing aeration basins to provide for attached growth in data and results, incorporating the results of this condition addition to suspended growth microorganisms.
assessment, all bundled together with the new CIPs. This would provide a new consolidated and integrated" new
3) Selective Sludge Wasting. The proprietary inDENSETM edition" of the master plan to serve the City' s needs going process uses hydrocyclones to selectively retain heavier forward. microbial flocs that settle well in the secondary clarifiers, while wasting filamentous organisms that cause sludge CIP Development bulking, thereby increasing clarifier capacity. We propose that the CIP be developed as a document that 4) Ballasted Flocs. The proprietary BioMag@ system uses can both be integrated into the Master Plan Study and magnetite particles to ballast microbial flocs causing rapid standalone. We will confirm this approach with you and are settling, thereby increasing clarifier capacity.
confident this approach— with a standalone CIP— will provide the most utility.

The MBR alternative for expansion uses membrane filtration instead of secondary clarifiers. This allows higher mixed Based on the results of the existing master plan deficiencies liquor solids concentrations in the reactor basins. and the condition assessment, projects will be identified Additionally, the membrane filtration system eliminates the with a brief description, cost estimates and relative need for subsequent tertiary filtration. MBR technology importance based on the condition assessment results. With provides a higher level of treatment and higher reliability City concurrence on the analysis results and project ranking, than conventional activated sludge followed by tertiary this will allow repair, rehabilitation or replacement capital filtration. The footprint of an MBR system is much smaller projects to be spread over time for implementation and than that for conventional treatment because the reactor budgeting, and ultimately incorporated into a rate structure basins can be much smaller, while clarifiers and tertiary to support reliable infrastructure. filters are eliminated altogether. Additionally, because of the superior effluent provided by the MBR, lower ultraviolet 67 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL 20 Exhibit "B" ATTACHMENT 3
Master Plan Report TASK 7 - STAFFING PLAN
In preparing the Master Plan Study document, Stantec will work with the City to incorporate the goals, policies and Stantec will prepare a staffing report to help estimate the programs of the General Plan and GIS Base Map such that the appropriate level of staffing required to adequately operate documents are internally consistent. We will also develop a and maintain the WQCF and Sewer collection System. For the plan to align improvement plans with upcoming/ anticipated WQCF, the report will include the current and anticipated future regulations and address sustainability issues, including facility classification and required minimum certification grade potential impacts of climate change and sea level rise. level of the chief plant operator and designated operator in charge, based on Section 13626 of the California Water Code.

TASK 5 - HYDRAULIC MODELS FOR It will further define the experience and education PHASED BUILDOUT requirements mandated by the State Water Resources Control Board for each operator certification grade level, as well as Stantec has a specialized, integrated team of hydraulic typical responsibilities associated with each grade level. For modelers with significant experience in developing, calibrating, the City engineering and sewer collection operations staff, testing, and analyzing computer models that simulate the Patrick Lytle, a staffing specialist with Stantec will utilize hydraulics of wastewater collection systems. Our nominated industry benchmarking data and develop a metrics team has experience in the development, calibration and use comparison ranges against the current City staffing. The of several different modeling platforms, including( but not evaluation will be focused on understanding staffing numbers, limited to): DHI Mike+( i. e., MikeUrban); Innovyze Infoworks ICM; CHI PCSWMM and other potential model platforms. levels, ratios, and structures relative to the other industry Stantec regularly examines commercially available software benchmarking data. The staffing report will include on behalf of our clients, so we propose to review a model recommendations on staffing levels needed to manage the selection matrix( which scores candidate model capabilities future WQCF and sewer collection system infrastructure, and according to client requirements such as suitability to will also include succession planning to prepare for the modeling objectives, ease of use, GIS integration, and cost) retirement of key personnel. and conduct a Model Selection Workshop to ensure the right tool is deployed. We will review the available model software TASK 8 - COMMUNICATION STRATEGY options with you, using the comparison matrix of software capabilities, licensing requirements, training needs, and costs, Public Outreach and Education and select the best fit for Manteca' s needs.

Public outreach and education will begin with a deep dive TASK 6 - WASTEWATER MASTER PLAN assessment of current outreach, media, and public perception ENVIRONMENTAL DOCUMENT and existing collateral and website content related to sewer planning and rates. Following this audit, Stantec will conduct To fulfill the requirements under California Environmental an outreach meeting with CV Strategies and staff to determine Quality Act( CEQA), the City' s existing Environmental Impact goals, priorities, target audiences, and a timeline. Stantec and Report( EIR) prepared for the City' s 2007 Wastewater Master CV Strategies will host a web site and use this information to Plan must be amended or updated to a programmatic EIR develop key messages and an outreach plan designed to help based on the infrastructure improvements recommended in the City consistently and effectively communicate details of the new Wastewater Master Plan. Under this Task, Stantec will the interim and final rate studies and the master plan to build review and evaluate the City' s existing 2007 Wastewater public understanding and confidence in the need for rate Master Plan, including the associated EIR and other relevant increases.
environmental documents. Following this evaluation, Stantec Proposition 218 Notification will prepare a technical memorandum that outlines the costs and schedule for preparing and completing the required Stantec, with the support of CV Strategies, will develop environmental documentation through the duration of the Proposition 218 notifications for both the interim and the final Project. This effort will be led by Stantec Regulatory Specialist, rate studies. The notifications will demonstrate the need and Emily C. Eppinger, with support from Stantec' s Environmental benefit of the rates, explain the proposed rates and rate Services staff. structure, provide a high- level summary of how the new funds will be used, identify when public meetings and the
Proposition 218 hearing will be held, and demonstrate how the City is operating in compliance with all the requirements of Proposition 218. Our scope and budget assume the City will Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL 21 Exhibit "B" ATTACHMENT 3
L P
N.

MILES
0 0. 1 0. 2 . 3 .. 4 0. 5
1,-^ I
r
r.
r _
tJ
I• -
r...., 1 1 1. rrr lr
r rr1
I\
I _. 1 ^-
Ln
L LvW,.- U-'. t Av,
Fto
7 V
An
z
P" i
d
a
t. u_.l i' yClin_. t
fl.>_ L 11 _ t:. l<. 1' rr4. ir l••
99 LA—. LA-"
Od"
Utt.).

L, t,-
West r.1 an teca Ve A, i1,, A11IL11V1
WeM-1 rn IM. In
St
O.

Aq120
Legend
C"
7 Pipe w/ PACP
Z Cr, Grade 5 Defect
I". t. C
ly Pipe w/ PACP
Alt- 1— ur
C120j Grade 4 Defect
Rehab Threshold
Scare( RTS)

5. 1 Exceeded
Pipe was CCTV' d
but no Grade 4/ 5
defects were
gravity sewer can replace
F present and/ or RTS this pump station) notexceeded
St
A- 4 Pump Station/
V; V- a, J-- 1 A,, J.' j A
51 L. I.--, A
Lift Station
EMU=
A", 0 Inspected Manhole
City of Manteca
Wastewater Master Plan and PACP Grade 4 & 5 Defects Overview Sewer Rate Study Proposal
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL 69 of 94 n22 Exhibit "B" ATTACHMENT 3
provide legal review of the rate notifications, translation into additional languages( if desired), and a verified list of addresses for the Proposition 218 notification mailings.

Our cost proposal reflects accomplishing work in the most efficient manner while preserving the highest standards of professionalism and quality. Our pricing comes from
practical experience with other similar projects. As
instructed in the RFP, we have included our cost proposal in a separate PDF file named" WastewaterMasterCostStantec". y. Sc Gh( a col uIa (3 V VeQL, CIlk
The timeline on the next page provides an approximation mation of time needed to complete key projects tasks.

Interim Rate Study: 10 months from Notice to Proceed
NTP)
Draft Wastewater Master Plan: 14 months from NTP
Final Rate Study: 18 months from NTP
Final Wastewater Master Plan: 26 months from NTP
Stantec and our subconsultants meet the insurance
coverage and limits outlined in the RFP.

Stantec requests the following revision to Article 15,
Indemnification and Hold Harmless, specifically adding the following sentence to the end of the clause:

Notwithstanding the foregoing, Consultant shall have no obligation to defend, indemnify or hold harmless the
aforementioned indemnitees against customer claims,
demands, or actions challenging utility rates implemented by the City as a result of Consultant' s performance of the services hereunder."
The reason for our requested change is that the indemnity is broadly written and could capture routine customer rate challenges that the City is more equipped to handle than Stantec.
70 of 94
Stantec I CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROPOSAL 23 Exhibit "B" ATTACHMENT 3

CITY OF MANTECA
2021 WASTEWATER MASTER PLAN AND SEWER RATE STUDY RFP
ADDENDUM 1
DATED: September 7, 2021
I acknowledge receipt of Addendum No. 1.

Company: Stantec Consulting Services Inc.

By: Steven Beck
Title: Principal- in- Charge
Address: 3875 Atherton Road, Rocklin, CA 95765
Date: September 20, 2021
2021 Wastewater Master Plan and Sewer Rate Study RFP Addendum 1 Page 3 71 of 94
Exhibit "B" ATTACHMENT 3

CITY OF MANTUCA
2021 WASTEWATER MASTER PLAN AND SEWER RATE STUDY RFP
ADDENDUM 2
DATED: September 15, 2021
I acknowledge receipt of Addendum No. 2.

Company: Stantec Consulting Services Inc.

By: Steven Beck
Title:
principal- in- Charge
Address: 3875 Atherton Road, Rocklin, CA 95765
Date:

September 20, 2021
2021 Wastewater Master Plan and Sewer Rate Study RFP Addendum 2 Page 3 September 15, 2021
72 of 94
Exhibit "B" ATTACHMENT 3
Stantec Design with community in mind
Mi
Exhibit "B" ATTACHMENT
3 Stantec Stantec Consulting Services Inc.
3875 Atherton Road, Rocklin, California 95765
October 7, 2021
Attention: Elba Mijango, Associate Engineer
City of Manteca
1001 West Center Street
Manteca, CA 95337
Reference: Proposal for the City of Manteca Wastewater Master Plan and Rate Study Dear Elba Mijango and Selection Committee Members,
As requested, please find enclosed our revised cost proposal for the City of Manteca Wastewater Master Plan and Sewer Rate Study. Our cost proposal includes the estimated labor hours and costs for each task, subconsultant fees and other direct costs based on our understanding of the scope of work provided in the RFP. Also included is a description of the tasks in our fee estimate spreadsheet. The total estimated time and expense fee for all tasks is $ 1, 048, 000.

Should you have any questions, please call me at( 916) 826- 3665. 1 am authorized to negotiate and approve any requested changes to or scope and fee estimate.

Regards,
Stantec Consulting Services, Inc.

Steven L. Beck PE
Senior Principal, Principal- in- Charge
Stantec Consulting Services Inc.
3875 Atherton Road, Rocklin CA 95765
Phone: ( 916) 826- 3665
steven. beck@stantec. com
74 of 94
Exhibit "B" ATTACHMENT 3
FEE ESTIMATE- City of Manteca Wastewater Master Plan and Rate Study a
d
xd` • A
age•
4 y
BaOt Sean Heiser, Jea Gunn, Hml BLws awan 9wwa, Pen Cmm. gem Van Dora 4u am. 6urN H9. Y Lwp Paoea. YepM 4cGanW.• eav Etpper, Ensry LYOe. PYau Ymq Mir. Ler. rvl am) Vm Enea Sery 9awl tleryemn Sz60w f2ww ] 259w f: 59. f: s9w f: 50w 325pw fleew ]: sOw 3+) s. fl) sw " n. 3260w 319aw 31s9w S2t0. e
f, 50. 3260w f2] 5. ilw f, w 3t 10 ft to 3+ 10 fa. SOx SOw > D. e 21e ne xe se 29 n : te Iw x9 310w shoo xzxo s) 9+> c2. s1s 305 szw Seaw t 06 boaw x 1Oe0w JI60.
f.
2w . 00w + 4s60. saw . w e15. ' sec. 9,) e) x15geex
WDS Cafe Tast Cale l. 0 Hme Surf Dne End D. 1e nr i. sk Tpav Hays la6ur E. pmsa Subs Tgal R m tpna9amem. M Mrnmgs 41. fe as 4)) 0w f, 2} 65
a 500 Trmen Malwa 3B „ fax96 SSS. f: z0. 11 St6x
12 o-ea C. nanaran 230 359 e. w Sax Spw fs9B..
1J 1JLON Sap T me6 twb m ai 129 3] t) Mw ft Soo. SsSa. fJl labx I. T m. a Malmrar 11.. ip. 112
Trme a e f: 9. e9
2 1 321 a e SaerS, Oraa a• a Ex. vxa r- bma m e 2 Sao Tema a Ma f2] 80. f5. w
Sow 3' Eap x
z: xx _ zz }) e s rrman
2B
man MMMalmn,,mr
n s.
133..
1Wsw
ssoa ww wfwo. L.
5-
1Hs.
3 lr in Ss2010. w flw. w SOw ...

J1 31
M14
lJJz]
l3J z.J nePLa•
y
r Couac
e1
152xI1
xw TTrrmmmeeeaaba MMW6laaallrrannnrrrrmaaarlrl
3 111
1 PS.1 6aJ9s'
5s0w.. f]
wS0pC.
ffS0a0
sfSftps.

Il Bw6aJ95w1o5a0.
3 3
e)
6 3e
l35M 36r
10 1
m s
S
sw.
3,
s
xwx.
w
30x ssi0x
fsle ea6w )• pen
41 aaer pmeocrem r m. a 2a90 s+ 99 s. ax S1. i aea $ loe wlw atvmC asCoreean e• a Pme. 24 505 21090 mea M,+anal 21. I] 2. f5o5. 12.. 2aB. 339 p9aw 41 3 .
11 Trma n at rerur 9 s1p x f U, 1a x
4 13f. t,. a Fro„ aw r« aa:, cmm. e w m. aw, anm oJx 13sow

1. nm. a Malena 9± to wow to ao.
t 6 au oN. t o..- t w 1w Trm.. Mirenal 1. 11314 Ow
1 B . l e Deer U ealan 12. T.- aMa, ma1 fJl show .. Sp. $

1. w 60 w T msa Marew zl lepw 32. x 50x . 2156aww
1e . la ra 5.+ c. 2w Trmea Malenal 15. f3f) 16x iww So. S3f 916. 42 43 T. mea Malenal Sz 6a0. J.. wx w.

42. 1 421 one Gnoaai era Permm 1 J 2w Trmen Wrmal 11n f+]' 6. ex f2w zz . x2 s 3 1. T m. nwrwr. r sz s+ J azfix s: wx 1, wx $ t.) Bw 23 . IJ 1 J 10 J 2w Trmea WI- 1 lw $ 35031x slopes f+ t. sm 33> w

2. . 2. s e1 3 Iw r m. n Mannar f26o]] w 3:.. ttxx ] 2aJ31. w 415 .: 5 3 ei B 3 s:. e79. f2 . ,.,.. szfi t39.
26 42e 3 3 3 2. Time alWrenar let f20 on.

12..
11w. s1+ l1Tm
2r 1} M 3 x. topo fie 6J3. 32w. fl tw. Sz993. 1. w
42a . 3e _ s3 3 2. T- a- 1- 1 10) 3, 9lslw 32. f, 1w f2065xx 429 429 aem CmerancWeu iL, s. osa Fanrnes fi 3 10 3w Sz1. 9fi. $ zw. S11w 122) 96.

2. 11 . 210 m6: em S W 3w T medlWlma 1eo Sz. ft, w. 139tbw 4211 s 3 a10 2. 21Jw T. 42 f92ww 52w J $ 32-
212 4211 snema 5 3 36 w Tmea lWrnul x96} ft9. s9fi. Szw. ' f0 $ 19. x 113 . 21J viOCFNav .e+ Pano'tSums 32 3 e4 1. 42w 9 f, 1e.. f2. SD OJ f+aw0w 3 3
n M tzz 124 2.. 11.-
431
w
e z fe 6w. K- Se. wD.
33 432 MEu' 1 4 12 Turo6Malenar 30 w. $ 3610.

J e. areCw Es. van era rcw.. mc.>! m I SJfiw. foes W 3350.

J. . 3. ewtpocu. ry fi a 26 42. Tnn. n Malmul 1 Sa. 1. 6w fzw. f0 Poeear. Pwam fzJ 152. f6ao fp. fn.Sea.7ws2x6
CPpreawrcm a 1. Tmaa Malmar e0 t1. tw. 3,. Sp tTiww

44. 2 442 ecv. CrPCxinmre a 26 f6 we. sw Sa
s 45 e. ar,-
451
Tr ennMlenm tw ww fi.. x
452
E, enx.,< samr-. a. x x n fs s16. stw spa ss 6lfiw
sx s a. z man DPe mr• n
6oao nm. n Ma1an. IN sw tza. sfi opo sa sJe 1ze x
s Hyer. almdwe. a ra n,,. e eanaar„ 11W.

T.
so s e
S1 51 oae+ 5ned 1/ sn a Tmsa Mauro fbOpa w Sa. fS Ooe.
sz sz a sz) sx. sx sa. $ z aszw
T mme s2 s sow s, a. l
em+ cumeme
R
T SI e. foes 30
63 61 o. n EnvaK• m 5 33 T m.
rma
a Malenal 3) sl6. x f+w Saes ]) 6J6w
f. Si. 1t

1. 1 1 _ ae Cunm, ara Fu1.. e Sa^ r 1 2fi T ma a Malerur S92e0 w S
W
w
SD x f93e0. w
22 2 20 T. mea Mmnul s9 f1!) 38w S1ww ip. St. elfiw
Tr a So Sto Ow. w ) am S59, IOO. w f6a I60. w
a1 was or-. ra Ee... a• e 1 2ao. Trme 3J 3' v. Jwx Sp 112- 12IJw. e3 a3 cn 3+ 8 rvorxalan 12 e J 2 JpoO T.- aMa' enal 23 S. AW. x 097ox 75 of 94
Exhibit "B" ATTACHMENT 3
Fee Estimate Task Descriptions for
City of Manteca Wastewater Master Plan and Sewer
Rate Study
Introduction
The City of Manteca has selected Stantec Consulting Services Inc. (Stantec) to develop the City' s Wastewater Master Plan and Sewer Rate Study ( Project). The focus of this Project is to develop a comprehensive plan that will enable the City to maintain the capability and capacity to convey, treat, and dispose of the City' s wastewater. The plan will provide approaches and strategies that enable long- term reliability to the General Plan build- out and provide sufficient conservatism in the design to prepare, to the extent possible, for future regulations, drought conditions, and increased labor, material, and construction costs.

The primary objectives of the Sewer Rate Study include the following:

Develop a financial plan that will generate sufficient revenue to meet current and future operating costs, debt obligations, and capital program needs factoring in infrastructure condition and the feasibility and timing of receiving funding and grants
Establish an interim schedule of rate adjustments that achieve the City' s near- term financial needs Establish a final schedule of rate adjustments that incorporate the findings of the Wastewater Master Plan
Establish wastewater utility rate structure that adheres to the requirements of Proposition 218 and are fair, equitable, and easy for the City to implement
The main objectives of the Wastewater Master Plan include:

Operation of a sewer system that is sustainable, reliable, and efficient Improve resiliency and minimize the effects of outside forces such as drought, changing regulatory requirements, and increasing maintenance and operations costs Strategize planning and budgeting efforts to implement sewer system enhancements Maintain a high level of system reliability and efficiency for current and future demands during normal, drought, and emergency situations
Develop the City' s sewer system hydraulic model from the pipe network design selected that incorporates phasing of capital projects
Develop a Capital Improvement Program ( CIP) and implementation schedule based on sewer capacity and condition of assets
76 of 94
Exhibit "B" ATTACHMENT 3
Task Descriptions
The following describes the tasks included in Stantec' s fee estimate spreadsheet.

Task 1 — Project Management and Meetings
Task 1. 1 - Project Kickoff Meeting
Stantec will conduct a project kickoff meeting with City staff to review the scope of services. This meeting will be a collaboration of ideas to solicit input and encourage a partnership between engineering and operations personnel on project related topics.

Task 1. 2 - Project Coordination
Throughout the project, Stantec' s project manager we will regularly communicate our progress, assumptions, opportunities, and challenges with the City. In addition, we will facilitate and conduct a monthly progress meeting with the project team and City staff. In addition, regular, ongoing, and ad- hoc project communication will be via conference calls and emails.

Stantec will develop and maintain a detailed project schedule using MS Project and submit updates monthly.

Stantec will provide quality assurance and quality control for the project, which includes peer review of project deliverables. Documents will be reviewed for correctness, completeness, and coordination with other documents and between disciplines.

Task 1. 3 - Progress Meetings and Workshops
Stantec will conduct virtual monthly progress meetings with City staff. Meeting minutes will be prepared and distributed to the meeting participants.

Task 1. 4 - Public Meetings / City Council Presentations Stantec will prepare presentations for public meetings using PowerPoint file format. Stantec' s project manager and support staff, as needed, will participate in a maximum of 19 public meetings and City Council Presentations.

Task 1 Submittals and Deliverables
Submittals
Meeting agendas and follow- up meeting minutes
Monthly progress reports and invoices
PowerPoint presentations
Deliverables
Draft documents
One( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format 77 of 94
Exhibit "B" ATTACHMENT 3
One ( 1) electronic version in PowerPoint file format( applies to presentations) Final documents
One ( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format One ( 1) electronic version in PowerPoint file format( applies to presentations) Task 2 — Interim Sewer Rate Study
Task 2. 1 - Rate Study Initiation and Review Background Information To initiate the Study, Stantec will submit a data request to the City that will include documentation that is needed to develop an updated five- year schedule of sewer rates. Shortly after receiving the completed data requests, Stantec will conduct a Rate Study Kick-Off meeting ( or conference call) with staff to:

Confirm goals and objectives of the Study
Discuss key issues, roles, and responsibilities
Assemble and review the previously discussed data
Finalize the project schedule, including milestones and deliverables Follow-up calls will be coordinated with staff to help establish a full understanding of all data received and to identify any supplemental data requests.

Task 2. 2 - Develop Short-Term Finance Plan
We will use our industry- leading financial model, the Financial Analysis and Management System FAMS), to develop an initial five- year financial management plan. This model will be populated with the City' s financial data from the initial data request. As part of the analysis, Stantec will examine historical and budgeted operating expenses and revenues, growth, and water use trends ( as available), alternative capital spending levels, reserve targets, debt service requirements, and other financial policies that drive the revenue requirements of the City.

With baseline data incorporated in the model, we will evaluate the sufficiency of the City' s current rate revenues over the next five years. In the event that revenue requirements identified in the model exceed projected revenues under current rates, Stantec will calculate an updated schedule of interim rate adjustments over a five- year period. The schedule of rate adjustments will be developed through scenario analyses with City staff to meet the operating and capital needs of the wastewater enterprise.

Stantec assumes that all data will be provided by the City in a readily available electronic format. Stantec also assumes that all revenues, expenses, capital plans, customer usage, billing, and other customer related data will be provided in an editable digital format( e. g., Microsoft Excel, Microsoft Access, etc.). 78 of 94
Exhibit "B" ATTACHMENT 3
Task 2. 3 - Adoption of New Interim Rates
Upon completion of the analysis, Stantec will present the findings of the interim rate study at four public meetings. Specifically, we plan to present to City Council, and the public, at up to three Council Meetings and at one additional public workshop during the course of the Interim Rate Study. Near completion of the Study, Stantec will meet with City Council to present preliminary recommendations regarding the financial plan and proposed rate increases. This preliminary meeting will be intended to inform the Council and to solicit feedback regarding objectives, decisions, and policies that could impact the final recommendations.

Following this meeting, Stantec will incorporate feedback and prepare modifications or alternative scenarios to be reviewed with Staff, as appropriate. Stantec will then participate in a meeting with the City Council to clearly explain the findings and recommendations of the Study, and to allow the Council to vote on proposed plans and rate structures. This will be the City Council meeting wherein a vote will be held to distribute public notifications and commence the 45- day public comment period. Between the second City Council presentation and the Prop 218 hearing, Stantec will hold one public outreach workshop to provide a venue to explain the need and benefit of the proposed rate and capital investment plan. The final public presentation will be the Proposition 218 public hearing, where protest votes are counted, and City Council ultimately votes to approve or reject the recommended rate schedule.

Upon completion of the interim rate study analysis, Stantec will support the implementation of the proposed rates by working with City Staff to ensure that the adopted rates are correctly loaded into the CitY' s utilitybilling9 software.

Task 2. 4 - Development of Interim Rate Study Report
Stantec will prepare a final report defining the assumptions and methodology used in our analysis along with the findings of the study. Stantec will prepare three report drafts for varying levels of review and comment, beginning with a preliminary draft for staff comments and revisions. Once staff feedback is incorporated, Stantec will provide an administrative draft for Council review prior to presenting final results and recommendations. Finally, Stantec will incorporate additional staff feedback before submitting the final report.

Task 2 Submittals and Deliverables
Submittals
Preliminary draft report for internal review
Administrative draft for Council' s review
City municipal code update support
Deliverables
Draft documents
One ( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format Final documents
One ( 1) PDF copy
79 of 94
Exhibit "B" ATTACHMENT 3
One( 1) electronic version of the complete document in Word 2010 file format Task 3 —Final Sewer Rate Study
Task 3. 1 - Updated Long- Term Financial Plan
In this task Stantec will build off the financial model developed during the interim rate study to incorporate the necessary wastewater system improvements as described in the updated Wastewater Master Plan.

The financial model will be updated to reflect new projections of customer growth and any identified changes in wastewater production or treatment requirements. Stantec will work closely with Staff and the Engineering team to develop a capital plan that meets the City' s infrastructure needs but also considers the long- term impacts to rate payers and the political feasibility of the adoption of the rate plan. The longterm plan will also incorporate the costs of any incremental O& M or additional staffing that were identified as part of the implementation of these capital projects.

Task 3. 2 - Cost of Service Analysis
The cost- of-service analysis allows for the revenue requirements of the sewer system to be equitably allocated to each of the City' s customer classes. To achieve this, the system' s costs will be functionalized to defined processes, which are then allocated to each customer class and/ or land use based upon the respective demand in terms of the average amount of flow or other system demand characteristics. This process is intended to evaluate inter- and intra- class equity in accordance with the proportionality requirements of Proposition 218.

At the conclusion of the cost- of-service analysis, Stantec will compare the resulting allocation of revenue requirements to the revenue generated by the existing rate structure and current rates for each customer class. Stantec will review these findings with City staff to confirm our understanding and analysis. In the event that the current revenue recovery levels do not align with the results of the cost- of-service analysis, Stantec will propose changes to the class- specific allocations of revenue recovery and this information will be used to inform the rate structure analysis in the subsequent task.

Task 3. 3 - Wastewater Rate Design
Based upon the information gathered and the analysis done in the preceding tasks, Stantec will develop up to three rate alternatives. The rate structure evaluation will include an examination of revenue volatility, customer ease- of understanding, affordability, administrative requirements, and potential limitations of the City' s billing system. Stantec will provide an overall impact analysis for each customer class, as well as specific bill impacts at various consumption levels for each rate structure alternative for which rates are calculated. Detailed customer impact analyses will be provided for all customer classes, and high- level result summaries will serve as important informational materials in public presentations.

Throughout this process, Stantec will work closely with City staff to determine the preferred approach to recover rate revenues, while minimizing the impact to your customers. At the end of this task, Stantec will produce a five- year schedule of rates with the preferred rate structure, escalated by the proposed rate adjustments developed in the updated financial plan.
80 of 94
Exhibit "B" ATTACHMENT 3
Task 3. 4 - Rate Study
To gain a better understanding of regional wastewater rates, Stantec will complete a rate survey of six to eight other similar cities or agencies located in the Central Valley. This analysis can help inform the customer acceptability of rate increases and is often necessary to address questions from key stakeholders, including elected officials, related to how your rates compare with peer communities.

Additional state- wide comparisons will be incorporated into the survey as appropriate.

Task 3. 5 - Adoption of New Rate / City Council Presentation Stantec will build off the momentum from the interim rate study and implement the same process to present the findings of the final rate study in a series of four public meetings and deliver a similar Proposition 218 notification process as for the interim rates. This will include a presentation to City Council to review the preliminary findings of the final rate study, a second presentation to Council with the final findings, a public workshop, and our participation at the Proposition 218 public hearing.

Upon completion of the final rate study analysis, Stantec will support the implementation of the proposed rates by working with City Staff to ensure that the adopted rates are correctly loaded into the City' s utility billing software.

Task 3. 6 - Update of Municipal Code
Upon completion of the rate study, Stantec will support the update of the applicable section of the City of Manteca Municipal Code, Title 13, that pertain to sewer service charges ( e. g., rates). This work will be subject to review by the City Attorney ( Stantec does not provide legal advice). As part of this process, Stantec will also provide assistance with notification for public review, and assistance through the adoption process with the City of Manteca Planning Commission and City Council.

Task 3. 7 - Development of Reports
The final report will be an update of the report from the Interim Rate Study, using the same approach and format, but will reflect the changes to assumptions, the CIP, operating budget, and provide a new recommended schedule of rate increases. This report will also include new sections outlining the approach and methodology used during the cost- of-service analysis, the rate design, and the findings of the rate survey.

Task 3. 8 - Online Model Development
At the conclusion of the Study, Stantec will provide the City with access to an online version of the FAMS model developed for the wastewater utility during the Study. Initial access to the model will be included through the end of the fiscal year of the final rate study portion of the analysis, subject to a separate licensing agreement. Access will include training and user support. Ongoing FAMS subscriptions for subsequent fiscal years are also available upon request. An Excel version of the FAMS model is not included as part of this scope of work.

Task 3 Submittals and Deliverables
Submittals
Up to three alternative rate structures for staff to evaluate Preliminary draft report for internal review
Administrative draft for Council' s review
81 of 94
Exhibit "B" ATTACHMENT 3
Deliverables
Draft documents
One ( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format Final documents
One ( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format Online version of FAMS with access until the end of the fiscal year.

Task 4 — Wastewater Master Plan
Task 4. 1 - Hydraulic Analysis and Model Development
Subtask 4. 1. 1 — Perform Data Collection and Review
Stantec will complete an organized and systematic review of the existing data including the existing master plans, condition assessment evaluations, Water Quality Control Facility ( WQCF) evaluations, base maps, record drawings, GIS shape files, and land use plans.

Stantec will collect and reviews Y stem performance P and condition data including9 flow data historical Sanitary Sewer Overflows ( SSOs), condition assessment data, O& M maintenance records, sewer cleaning schedules, interior and exterior point repairs, etc.

F3 and Associates will perform field survey of approximately 50 sewer manholes ( more or less, depending on need and available budget) and capture missing information such as elevations, size, material, condition photos, and GPS data points at each sewer manholes. Data from the surreys will be used as an important input to the hydraulic model, to update the project GIS, and ultimately for the City to update their GIs data.

Stantec will conduct limited site observations of the critical sewer manholes on trunk lines and other critical sewer mains for the assessment of constraints such as site accessibility, environmental concerns, O& M concerns and design constraints.

Stantec will conduct onsite comprehensive and detailed interviews with City staff to capture their knowledge, needs, concerns and goals for the wastewater infrastructure. This will be a key step, possibly the most important, to completing the existing system performance and developing updated O& M procedures.

Subtask 4. 1. 2— Flow Monitoring
Following data collection, the next critical steps of the project are developing design flows, hydraulic criteria, and land use followed by model software selection, build, calibration, and assessment of the system to both current and future build out conditions.

Stantec has partnered with V&A Consulting Engineers, Inc. to deliver the flow monitoring for the City of Manteca system. The goals of the flow monitoring effort will be to capture flow patterns from distinct land use types to develop demands, capture flow at critical points throughout the system for calibration of the 82 of 94
Exhibit "B" ATTACHMENT 3
model and place enough monitors to capture 1/ 1 contribution from different areas of the system. Stantec has planned for 10 flow monitoring locations and one rain gauge for a period of four months. Based on our experience with similarly sized systems, we feel this number of monitors and duration will provide ample information for demand development and calibration. Stantec will develop a list of suitable locations for flow monitoring in concert with City staff, and V&A will provide desktop analysis ( GIS, sewer plans, Google Earth, etc.) to verify suitability of primary and alternative manholes for installation of a flow meter.

Subtask 4. 1. 3— Design Flows and Hydraulic Criteria
Hydraulic criteria set the metrics by which the collection system is evaluated and dictate the requirements for both the current and future infrastructure of the system. It includes determination of dry and wet weather flow conditions, design storms from historical rainfall data, and estimates for inflow and infiltration into the sewer system. Stantec will leverage design criteria and lessons learned from across the US to aid in the selection of the best criteria for the City. Once the model is built, Stantec can also help the City to determine the most cost- effective level of services for future updates. For example, Stantec can determine improvements required such that no SSO occurs during 2- year, 5- year, and 10- year storms.

That will help City to determine which criteria is the most cost- effective level of services for their rate payers.

Subtask 4. 1. 4— Land Use Development
To understand current conditions and to plan for future conditions it is important to understand the current and future land uses. Stantec will work with the City to identify areas of new development and other new developments. In addition, we will use local planning documents, general land use, and other information collected to assess potential growth and apply that to projected sewer flows and the hydraulic model.

Subtask 4. 1. 5— Wastewater Model Development
This task will involve developing a wastewater model to simulate the performance of the existing sanitary system. The model will be constructed by importing the available GIS- based system data and newly collected survey data into the selected software package. Sub- basins will be re- delineated along parcel boundaries to estimate the areas tributary to flow meter locations. These catchments will be linked to the network at the nearest downstream manhole that conveyed the catchment' s full discharge. Equivalent populations will be assigned to catchments. Stantec will review sub- basin boundaries with the City prior to allocating flows to the model. Facilities such as lift stations will be included in the model based on as- built drawings to reflect the physical system as close as possible. The Existing Model network will then be verified as well as the lift station components against available as- built drawings and other available data source. The downstream network tracing tool will be used to confirm the connectivity. Using WQCF and Flow Monitoring data, Stantec will develop sewers h ed- specific flow generation characteristics such as average dry weather flow( ADWF) sewage generation, diurnal sewage patterns for weekdays and weekends, baseflow and groundwater infiltration ( GWI), rainfall dependent inflow and infiltration ( RDII), and peak wet weather flow( WWF) rates throughout the system. Stantec will utilize this information to assign the Dry weather flow( DWF) unit hydrographs for each catchment applied on a per capita basis into the model. Once the initial model structure is developed, the model will be debugged until it can iterate successfully to a valid solution within numerical solution tolerance limits.

Subtask 4. 1. 6— Model Calibration
It is always necessary to verify model simulations match actual sewer performance by properly calibrating any model intended to assess the hydraulic capacity of an existing system. This is even more so when such a tool will form the basis of significant investment and asset management decisions. 83 of 94
Exhibit "B" ATTACHMENT 3
The first calibration efforts will involve dry weather flows, where the unit hydrographs ( diurnal coefficients) are routed through the system and compared to measured flow data for different stations in flow monitoring report. In areas of high groundwater table fluctuations, there can be differing degrees of" dry weather flow"—so Stantec will pay heed to this.

The dry weather flow is characterized by base flow loading and by diurnal residential/ commercial wastewater generation. The base flow sewage is dependent upon the land area of each catchment and has constant loading throughout the day, while residential/ commercial wastewater sewage generation are based on per capita ( equivalent population) loads within each catchment. Catchments will be assigned the equivalent population value, an amalgamation of residential and employment populations weekdays and weekends, different diurnal patterns will be applied in the model. The calibration of the model is an iterative process, the accuracy of each iteration being determined qualitatively by a visual inspection and quantitatively through an analysis of the minimum, maximum, and average flows for the period. Once the modeled flow for DWF is calibrated to within acceptable tolerances, flow depths and velocities from the flow monitor data will be compared to the modeled results.

The second stage of the calibration will address calibration of the model to rainfall wet weather flow conditions. These situations often represent the most extreme cases of system loading. Extraneous flows, depths, and volumes will be determined from the available flow monitoring data, as well as corresponding rainfall data for each wet weather flow event recorded.

The effective area for each manhole will be established as a percentage of the physical sewershed area initially estimated by determining the ratio of extraneous flow volume to the total rainfall volume from flow monitoring data).

The WWF model will be calibrated using initial values and adjusted for each flow monitor sewershed individually, in an iterative process. Different catchment areas will be calibrated to reflect different RDII responses. Other hydrologic parameters will then be modified until the model matches the total volume and shape of the monitoring data during the storm event based upon available flow monitoring data. Once the modeled flow for WWF is calibrated to within acceptable tolerances, flow depths and velocities from the flow monitor data will be compared to the modeled results. Several graphs and figures will be presented in the report to summarize the calibrated dry weather flow( DWF) and WWF model results for major stations in flow monitoring report.

Subtask 4. 1. 7 — Existing System Assessment
The calibrated model will then be used to evaluate the level of service ( LOS) performance of the existing sewer system under Dry Weather Flow( DWF) and Wet Weather Flow ( WWF) conditions using the selected design storm event flow scenarios. We will discuss and confirm the system performance metrics or LOS criteria that will be used to examine the system performance ( metrics that assess pipe capacity, manhole surcharging, lift station capacity, etc.). Analysis of the existing system hinges on two important factors: 1) Identifying issues and deficiencies in the current system 2) Optimizing overall operation of the current system. Identifying current issues is predicated upon clear and frequent communication between Stantec and City engineering and operations staff. Stantec will identify all current deficiencies based on the established planning criteria and develop improvement projects to address each deficiency. GIS information such as pipe material and age will also be used to recommend a rehabilitation and replacement program in conjunction with available condition assessment and CCTV investigation.

Beyond an issue- by- issue recommendation schedule to address current deficiencies, the existing system analysis will include a system- wide look at how flow is conveyed and how one sub basin relates to the next.
84 of 94
Exhibit "B" ATTACHMENT 3
Subtask 4. 1. 8— Future System Assessment and Servicing Plan The existing system assessment represents the current state of the collection system. This will change over time through the influences of component deterioration, capital investment, changing usage patterns, and ongoing growth and development. Once the existing system model has been developed, calibrated, and reviewed, Stantec will begin the process of extending of the model to account for future scenarios and build- out. The existing model will be further developed into a Future System model to represent sanitary catchments for build- out future development, using population densities and projections in the City' s Land Use Plan. DWF patterns and rates will be applied, and WWF parameters will be established based on industry standards for I& I in new developments. Servicing infrastructure will be added to the model, necessary to convey future flows to the City' s WQCF, either through existing infrastructure or via new conveyances. The initial servicing strategy for future growth will align growth areas with logical servicing points in the City' s existing system. The model will then be run as an initial scenario for DWF and WWF to" test" the impacts of growth on the existing system.

Stantec will develop a future scenario that captures all expected growth and identifies the improvements necessary to serve that growth, while identifying the reasoning and recommended timing for each improvement. Stantec will identify drivers for improvements, and prioritize the CIP based on the most likely asset to fail. For these improvements, it is important the true driver is identified, and timing is based on that trigger event. By identifying triggers, the City will be able to pinpoint which areas or pipes may need additional investigation. This will allow the City to have a full assessment of the needs for a future system, while still having a prioritized list of improvements that can be implemented or studied further given specific growth or development.

Task 4. 2 - WQCF Expansion Phasing
Key issues that must be addressed in the Master Plan are summarized below:

A critical criterion for developing the Wastewater Master Plan is the average wastewater flow when the City is fully built out. According to the City' s General Plan, the buildout population is expected to be around 206, 000 by the year 2050. With a 2020 population of about 87, 000, the average wastewater flow was 7. 18 Mgal/ d, indicating a possible buildout flow of around 17 Mgal/ d, which is slightly less than the 17. 5 Mgal/ d limit indicated in the existing discharge permit. Therefore, if current growth rates continue, the buildout condition could be reached in about 29 years. Since 14. 7percent of the current capacity of the WQCF is contracted to the City of Lathrop, the 29- year horizon is contingent on the extent the City of Lathrop participates in expansion of the WQCF. Appropriate planning criteria must be developed for City growth rate and the timing and amount of flow occurring at buildout to be used as the basis of the Master Plan. A range of possible growth rates and City of Lathrop participation can be considered.

Plant design and operation are governed by permit requirements for effluent disposal and/ or reuse.

The current permit for discharge into the San Joaquin River requires effluent cooling for discharges over 9. 87 Mgal/ d. Since effluent cooling would have high capital and operating costs and take up significant land area, and since wastewater reuse is highly beneficial in California, a reuse alternative should be considered.

Regardless of discharge or reuse option, nitrogen removal will remain a key concern for the WQCF.

There is pressure for development and other possible uses for lands that may be needed for WQCF expansion. Therefore, a small footprint for WQCF expansion would be highly beneficial. 85 of 94
Exhibit "B" ATTACHMENT 3
Wastewater flows and loads from equivalent dwelling units and other types of development as well as City of Lathrop participation must be defined to allow appropriate planning.

A plan for the logical expansion of the WQCF in phases that protect the City' s long- term needs while providing affordable and sustainable wastewater management solutions is needed.

A draft capacity assessment of the secondary treatment process prepared by Stantec/ HERWIT recommended interim improvements to allow flows up to 9. 23 Mgal/ d. Therefore, the Master Plan will primarily address expansion beyond that capacity. Although previous planning and the existing discharge permit envisioned the next expansion would be to a capacity of 17. 5 Mgal/ d, that capacity is not likely to be required within twenty years and may exceed the City buildout flow. Because of the high costs of building and then maintaining facilities before they are needed, Stantec would work with the City to define an affordable phasing plan. The phasing plan will be dependent on planned growth rates within the City, City of Lathrop participation, and confirmation of the buildout flow. Our approach is to focus the planning on the 17. 5 Mgal/ d permitted expansion which coincidentally accommodates the General Plan buildout of 206, 000 people.

Subtask 4. 2. 1 — Evaluate Permitting Requirements
Stantec will review the current NPDES permit and provide an assessment of the probable future permitting requirements and level of treatment required for the effluent disposal alternatives considered in this study.

Subtask 4. 2. 2— Existing and Future Flows and Loads
The Master Plan will be based on wastewater flows and loads to be determined for existing and future development. Having just completed a flows and loads analysis for the Capacity Assessment, Stantec will extend this evaluation for the purposes of the Master Plan, including more detailed evaluation of flows and loads due to dwelling units, businesses, and other development. Future flow and load projections will consider alternative scenarios based on levels of water conservation.

Subtask 4. 2. 3— Influent Pump
The influent pump station will be evaluated with respect to existing issues ( based on input from City staff), capacity, alternatives for expansion, and appropriate phasing. Improvements to correct existing issues, enhance reliability, and extend the capacities of existing facilities will be developed.

Subtask 4. 2. 4— Influent Screening
The influent screening will be evaluated with respect to existing issues ( based on input from City staff), capacity, alternatives for expansion, and appropriate phasing. Improvements to correct existing issues, enhance reliability, and extend the capacities of existing facilities will be developed.

Subtask 4. 2. 5— Grit Removal
The grit removal facilities will be evaluated with respect to existing issues ( based on input from City staff), capacity, alternatives for expansion, and appropriate phasing. Improvements to correct existing issues, enhance reliability, and extend the capacities of existing facilities will be developed.

Subtask 4. 2. 6— Primary Clarifiers
The WQCF currently uses primary clarifiers for removal of settleable solids in the raw wastewater.

Because of the relatively large footprint and cost of primary clarifiers, Stantec will evaluate filtering the raw 86 of 94
Exhibit "B" ATTACHMENT 3
wastewater for flows beyond the capacity of the existing clarifiers using alternative treatment technologies.

Subtask 4. 2. 7— Secondary Treatment
The secondary treatment system includes aeration basins, secondary clarifiers, and ancillary facilities.

Stantec/ HERWIT presented a detailed evaluation of these facilities in the Capacity Assessment.

Capacities were determined and improvements were recommended that could be implemented relatively quickly without new structures or major new mechanical equipment systems. The Master Plan analysis will consider additional alternatives for improvement and expansion, which will require new structures and mechanical systems. Four main alternatives will be considered: 1) expand in- kind, 2) intensification of existing facilities to increase capacity and improve performance followed by expansion with the same type of facilities, 3) expand with membrane bioreactors ( MBRs), and 4) intensify existing facilities and expand with MBRs. In each case, the impacts of future importation of food waste to the WQCF anaerobic digesters and the use of sidestream treatment to remove nitrogen from the sludge dewatering return flow will be considered.

Subtask 4. 2. 8— Effluent Filtration
The effluent filters will be evaluated with respect to existing issues ( based on input from City staff), capacity, alternatives for expansion, and appropriate phasing. Improvements to correct existing issues, enhance reliability, and extend the capacities of existing facilities will be developed.

Subtask 4. 2. 9— Effluent Conveyance/ Reuse/ Disposal Facilities The effluent conveyance, reuse, and alternative disposal methods will be evaluated with consideration to the level of treatment required for compliance with existing and probable future permitting requirements.

Subtask 4. 2. 10— UV Disinfection System
The existing UV system has not performed well, causing several permit violations. The existing system is difficult to clean, operate, and maintain. Alternative UV designs will be evaluated, noting that lower UV dosing would be required after MBR secondary treatment.

Subtask 4. 2. 11 — Solids Handling
The solids handling system includes thickening, anaerobic digestion, and sludge dewatering using centrifuges. The centrifuges are costly to operate and maintain, so other dewatering alternatives will be evaluated. Stantec/ HERWIT designed the existing compressed natural gas ( CNG) facilities that make beneficial use of the anaerobic digester gas and would evaluate the best means of expansion. Evaluation of sidestream treatment systems to remove nitrogen from the sludge dewatering return flow would be coordinated with any evaluation and design occurring on an expedited basis as previously recommended in the Capacity Assessment completed by Stantec/ HERWIT.

Subtask 4. 2. 12— Ancillary and Support Systems
Ancillary and support system include electrical will be evaluated with respect to existing issues ( based on input from City staff), capacity, alternatives for expansion, and appropriate phasing. Improvements to correct existing issues, enhance reliability, and extend the capacities of existing facilities will be developed.
87 of 94
Exhibit "B" ATTACHMENT 3
Subtask 4. 2. 13 — WQCF Expansion Phasing Plan
Stantec will develop an expansion phasing plan for future development growth along with accompanying recommended improvements needed to support future growth.

Task 4. 3 - Evaluate Operations and Maintenance Program Subtask 4. 3. 1 — Review Current O& M Practices
Using annual operating expense documentation, Stantec will review historic operations and maintenance demands for the WQCF and sewer collection system. The historical data will be compared with the expected costs of operation based on O& M programs of similarly sized facilities with similar treatment and discharge requirements ( including anticipated number of personnel to successfully meet the NPDES permit requirements and projected major equipment maintenance needs).

Subtask 4. 3. 2— Assess Need for Additional Resources and Equipment The comparison with other utilities will be used to assess whether additional resources and associated costs ( for personnel and/ or equipment) are necessary to reliably, successfully, and safely meet the service goals of the City.

Subtask 4. 3. 3— Prepare Cost Estimates and Recommendations Based on the results of the evaluation, Stantec will include a recommendation for annual operating expenses for future budgeting purposes.

Subtask 4. 3. 4— Prepare Report Document
Stantec will submit draft and final documents in PDF and raw file format( see Deliverables below).

Task 4. 4 - Capital Improvement Program
We propose to redo and/ or repackage the existing master plan material, resolving the existing plan deficiencies identified in the RFP, adding the new condition assessment data and results, incorporating the results of this condition assessment, all bundled together with the new CIPs. This would provide a new consolidated and integrated " new edition" of the master plan to serve the City' s needs going forward.

Subtask 4. 4. 1 — CIP Development
We propose that the CIP be developed as a document that can both be integrated into the Master Plan Study and standalone. We will confirm this approach with you and are confident this approach— with a standalone CIP— will provide the most utility.

Based on the results of the existing master plan deficiencies and the condition assessment, projects will be identified with a brief description, cost estimates and relative importance based on the condition assessment results. With City concurrence on the analysis results and project ranking, this will allow repair, rehabilitation or replacement capital projects to be spread over time for implementation and budgeting, and ultimately incorporated into a rate structure to support reliable infrastructure.

Subtask 4. 4. 2— Prepare CIP Document
In preparing the Wastewater Master Plan document, Stantec will work with the City to incorporate the goals, policies, and programs of the General Plan and GIS Base Map such that the documents are internally consistent. Stantec will also develop a plan to align improvement plans with upcoming/ anticipated regulations and address sustainability issues, including potential impacts of climate change and sea level rise.
88 of 94
Exhibit "B" ATTACHMENT 3
Stantec will prepare a draft and final document in accordance with submittal and deliverable requirements of the RFP.

Task 4. 5 - Master Plan Document
Subtask 4. 5. 1 — Prepare Executive Summary
Stantec will prepare an executive summary of the major findings and recommendations in the Wastewater Master Plan.

Subtask 4. 5. 2— Prepare Report Document
Stantec will draft and final documents in PDF and raw file format( see deliverables below).

Task 4 Submittals and Deliverables
Submittals
Draft version of each document for internal review
Second draft version prior to public review
Third draft version for public review
Final version, which incorporates comments from the public, and comments from City staff.

Deliverables
Draft documents
One( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format One ( 1) electronic version in PowerPoint file format( applies to presentations) One ( 1) AutoCAD version of figures and exhibits, where needed Final documents
One( 1) PDF copy
One( 1) electronic version of the complete document in Word 2010 file format One ( 1) electronic version in PowerPoint file format( applies to presentations) One ( 1) AutoCAD version of figures and exhibits, where needed Task 5 — Hydraulic Models for Phased Buildout
Task 5. 1 - Prepare Hydraulic Model Selection Matrix
Stantec has experience in the development, calibration, and use of several different modeling platforms, including ( but not limited to): DHI Mike+ ( i. e., MikeUrban); Innovyze Infoworks ICM; CHI PCSWMM and other potential model platforms. Stantec regularly examines commercially available software on behalf of 89 of 94
Exhibit "B" ATTACHMENT 3
our clients, so we propose to review a model selection matrix( which scores candidate model capabilities according to client requirements such as suitability to modeling objectives, ease of use, GIs integration, and cost) and conduct a Model Selection Workshop to ensure the right tool is deployed. Stantec will review the available model software options with you, using the comparison matrix of software capabilities, licensing requirements, training needs, and costs, and select the best fit for Manteca' s needs.

Task 5. 2 - Prepare Hydraulic Model Technical Memorandum Stantec will prepare a draft and final technical memorandum.

Task 5 Submittals and Deliverables
Submittals
Draft version of each document for internal review
Final version, which incorporates comments from City staff.

Deliverables
Draft documents
One ( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format Final documents
One( 1) PDF copy
One( 1) electronic version of the complete document in Word 2010 file format Task 6 — Wastewater Master Plan Environmental
Task 6. 1 - Review Existing Environmental Documents
To fulfill the requirements under California Environmental Quality Act( CEQA), the City' s existing Environmental Impact Report( EIR) prepared for the City' s 2007 Wastewater Master Plan must be amended or updated to a programmatic EIR based on the infrastructure improvements recommended in the new Wastewater Master Plan. Under this Task, Stantec will review and evaluate the City' s existing 2007 Wastewater Master Plan, including the associated EIR and other relevant environmental documents. Following this evaluation, Stantec will prepare a technical memorandum that outlines the costs and schedule for preparing and completing the required environmental documentation through the duration of the Project. This effort will be led by Stantec Regulatory Specialist, Emily C. Eppinger, with support from Stantec' s Environmental Services staff.

Task 6. 2 - Prepare Environmental Report
Stantec will prepare a draft and final report.

Task 6 Submittals and Deliverables
Submittals
Draft version of each document for internal review
90 of 94
Exhibit "B" ATTACHMENT 3
Final version, which incorporates comments from City staff.

Deliverables
Draft documents
One ( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format Final documents
One ( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format Task 7 — Staffing Plan
Task 7. 1 — Review Current and Future Staffing Needs
Stantec will prepare a staffing report to help estimate the appropriate level of staffing required to adequately operate and maintain the WQCF and Sewer Collection System. For the WQCF, the report will include the current and anticipated future facility classification and required minimum certification grade level of the chief plant operator and designated operator in charge, based on Section 13626 of the California Water Code. It will further define the experience and education requirements mandated by the State Water Resources Control Board for each operator certification grade level, as well as typical responsibilities associated with each grade level. For the City engineering and sewer collection operations staff, Patrick Lytle, a staffing specialist with Stantec will utilize industry benchmarking data and develop a metrics comparison ranges against the current City staffing. The evaluation will be focused on understanding staffing numbers, levels, ratios, and structures relative to the other industry benchmarking data. The staffing report will include recommendations on staffing levels needed to manage the future WQCF and sewer collection system infrastructure and will also include succession planning to prepare for the retirement of key personnel.

Task 7. 2 Prepare Staffing Report
Stantec will prepare a draft and final report.

Task 7 Submittals and Deliverables
Submittals
Draft version of each document for internal review
Final version, which incorporates comments from City staff.

Deliverables
Draft documents
One ( 1) PDF copy
One ( 1) electronic version of the complete document in Word 2010 file format Final documents
91 of 94
Exhibit "B" ATTACHMENT 3
i
One( 1) PDF copy
One( 1) electronic version of the complete document in Word 2010 file format Task 8 — Communication Strategy
Task 8. 1 - Public Outreach and Education
Public outreach and education will begin with a deep dive assessment of current outreach, media, and public perception and existing collateral and website content related to sewer planning and rates.

Following this audit, Stantec will conduct an outreach meeting with CV Strategies and staff to determine goals, priorities, target audiences, and a timeline. Stantec and CV Strategies will host a web site and use this information to develop key messages and an outreach plan designed to help the City consistently and effectively communicate details of the interim and final rate studies and the master plan to build public understanding and confidence in the need for rate increases.

Task 8. 2 - Proposition 218 Notification
Stantec, with the support of CV Strategies, will develop Proposition 218 notifications for both the interim and the final rate studies. The notifications will demonstrate the need and benefit of the rates, explain the proposed rates and rate structure, provide a high- level summary of how the new funds will be used, identify when public meetings and the Proposition 218 hearing will be held, and demonstrate how the City is operating in compliance with all of the requirements of Proposition 218. Our scope and budget assume the City will provide legal review of the rate notifications, translation into additional languages ( if desired), and a verified list of addresses for the Proposition 218 notification mailings.

Task 8 Submittals and Deliverables
Submittals
Outreach Plan
o Audience identification
o Key messages
o Asset development
Design elements including infographics
Flyers
Mailers
Website, social media, and newsletter content
Public presentation design
Public meeting support
Proposition 218 notice, upon approval from the City, this will be printed and mailed by CV Strategies 92 of 94
Exhibit "B" ATTACHMENT 3
ATTACHMENT 3

SCHEDULE OF ACTIVITIES
93 of 94
Exhibit "B" ATTACHMENT 3
ID Task Name Duration Start Finish Predecessors Hall t, 2022 Halt 2, 2022 Hall t, 2023 Halr Z, 2023 Half t, 2024 N__ J J F M A M 1 I 1 A S O _ t4 I 1 F M A I M 1 I 1 A I S I O N._ p F 1 Award of Contract 0 days Tue 10/ 12/ 21 Tue 10/ 12/ 21 10/ 12 bl
2 Notice to Proceed 0 days Tue 10/ 19/ 21 Tue 10/ 19/ 21 10/ 19 3 1- Project Management and Meetings 550 days Tue 10/ 19/ 21 Tue 12/ 26/ 23 2 4 1. 1- Project Kickoff Meeting 0 days Thu 10/ 28/ 21 Thu 10/ 28/ 21 4 10/ 28 5 1. 2- Project Administration 550days Tue 10/ 19/ 21 Tue 12/ 26/ 23 6 1. 3- Progress Meetings( Monthly) 499 days Tue 1112121 Tue 10/ 31/ 23 0 O O O O O O O O O O O O O O O O O O O O O O O O O O 34 1. 4- City Council Presentations 0 days Mon 11/ 27/ 23 Mon 11/ 27/ 23 108FS+ 21 days 11/ 27 35 2- Interim Sewer Rate Study 190 days Thu 10/ 28/ 21 Thu 8/ 4/ 22 4 36 2. 1- Rate Study Initiation and Review Background Information 15 days Thu 10/ 28/ 21 Wed 11/ 17/ 21 4 1 37 2. 2- Develop Short- Term Financial Plan 120 days Thu 11/ 18/ 21 Tue 5/ 17/ 22 36 i-------'- ----- s 38 2. 3- Adoption of New Interim Rates 135 days Wed 1/ 26/ 22 Thu 8/ 4/ 22 3755+ 40 days I 39 2. 4- Development of Interim Rate Study Report 70 days Wed 2/ 23/ 22 Wed 6/ l/22 37SS+ 60 days 40 Interactive Work Sessions( 1- 3) 73 days Tue 12/ 7/ 21 Tue 3/ 29/ 22 I O O O
44 Public Outreach Plan 0 days Tue 2/ 8/ 22 Tue 2/ 8/ 22 37SS+ 50 days 2/ 8 i
45 Presentation to City Council 30 days Tue 3/ 15/ 22 Tue 4/ 26/ 22 O O 48 Public Rates Workshop 0 days Tue 5/ 24/ 22 Tue 5/ 24/ 22 49FS+ 20 days 5/ 24 49 Proposition 218 Notification 0 days Tue 4126/ 22 Tue 4/ 26/ 22 47FS+ 1 day 26 So Proposition 218 Hearing 0 days Wed 6/ 29/ 22 Wed 6/ 29/ 22 49FS+45 days ( 6/ 29 51 3- Final Rate Study 158 days Wed 5/ 17/ 23 Fri 12/ 22/ 23 35FS+ 40 days 52 3. 1- Updated Long-Term Financial Plan 30 days Fri 5/ 26/ 23 Thu 7/ 6/ 23 35, 101, 117 5------ 53 Interactive Work Sessions( 4- 6) 90 days Wed 5/ 17123 Wed 9/ 20/ 23 O O O 57 3. 2- Cost- of-Service Analysis 4S days Fri 6/ 16/ 23 Thu 8/ 17/ 23 52FS- 15 days t58 3. 3- Sewer Rate Design 45 days Tue 7/ 11/ 23 Mon 9/ 11/ 23 63FF+ 5 days 59 3. 4- Rate Survey 7 days Tue 7/ 18123 Wed 7/ 26/ 23 58SS+ 5 days 60 3. 5- Adoption of New Rate 90 days Tue 8/ 15/ 23 Mon 12/ 18/ 23 58FS- 20 days 61 Public Rates Workshop 0 days Tue 11/ 14/ 23 Tue 11/ 14/ 23 60FS- 10 days V 114 62 Presentation to City Council 30 days Tue 9/ 5/ 23 Tue 10/ 17/ 23 O O 65 Proposition 218 Notification 0 days Wed 10/ 18/ 23 Wed 10/ 18/ 23 64F5+ 2 days 66 Proposition 218 Hearing 0 days Wed 12/ 20/ 23 Wed 12/ 20/ 23 65F5+ 45 days i II72/ 20 67 3. 6- Update of Municipal Code 20 days Mon 11/ 27/ 23 Fri 12/ 22/ 23 60FF+4 days I 68 3. 7- Development of Reports 70 days Tue 7/ 11/ 23 Tue 10/ 17/ 23 64FF 1 69 3. 8- Online Model Development 49 days Tue 10/ 17/ 23 Fri 12/ 22/ 23 68 70 4- Wastewater Master Plan Sol days Thu l0/ 28/ 21 Frl 10/ 27/ 23 4 71 4. 1- Hydraulic Analysis and Model Development 285 days Thu 10/ 28/ 21 Tue 12/ 20/ 22 4 11 1
72 4. 1. 1- Perform Data Collection and Review 25 days Thu 10/ 28/ 21 Fri 12/ 3/ 21 4 73 4. 1. 2- Flow Monitoring 70 days Thu 11/ 11/ 21 Tue 3/ l/ 22 7255+ 10 days 74 4. 1. 3- Design Flows and Hydraulic Criteria 30 days Wed 2/ 2/ 22 Tue 3/ 15/ 22 73FS- 20 days I I 75 4. 1. 4- Land Use Development 40 days Mon 12/ 6/ 21 Tue 2/ 8/ 22 72 I 7 76 4. 1. 5- Wastewater Model Development 80 days Wed 2/ 9/ 22 Wed 6/ l/ 22 75, 111 1 77 4. 1. 6- Model Calibration 40 days Thu 6/ 2/ 22 Thu 7/ 28/ 22 76 i t
78 4. 1. 7- Existing System Assessment 50 days Fri 7129/ 22 Fri 10/ 7/ 22 77 1 79 4. 1. 8- Future System Assessment and Servicing Plan 50 days Mon 10/ 10/ 22 Tue 12/ 20/ 22 78 80 4. 2- WQCF Expansion Phasing 220 days Wed 3/ 16/ 22 Thu 2/ 2/ 23 81 4. 2. 1- Evaluate Disposal Options and Permitting Requirements 30 days Wed 3/ 16/ 22 Tue 4/ 26/ 22 74 82 4. 2. 2- Existing and Future Flows and Loads 30 days Wed 4127/ 22 Wed 6/ 8/ 22 81 83 4. 23- Influent Pump Station 15 days Thu 6/ 9/ 22 Wed 6/ 29/ 22 82 84 4. 2. 4- Influent Screening 15 days Thu 6/ 9/ 22 Wed 6129/ 22 82 1 85 4. 2.5- Grit Removal 20 days Thu 6/ 30/ 22 Thu 7/ 28/ 22 84 86 4. 2. 6- Primary Clarifers 10 days Thu 6/ 30/ 22 Thu 7/ 14/ 22 84 87 4. 2.7- Secondary Treatment 20 days Fri 7/ 15122 Thu 8/ 11/ 22 86 p1 88 4. 2. 8- Effluent Filtration 20 days Fri 8/ 12/ 22 Fri 9/ 9/ 22 87 89 4. 2. 9- Effluent Conveyance/ Reuse/ Disposal Facilities 15 days Mon 9/ 12/ 22 Fri 9/ 30/ 22 88 90 4. 2. 10- UV Disinfection System 2D days Mon 10/ 3/ 22 Fri SO/ 28/ 22 89 T. 1 91 4. 2. 11- Solids Handling 10 days Mon 10/ 31/ 22 Frill/ 11/ 22 90 L 92 4.2. 12- Ancillary and Support Systems 20 days Mon 11/ 14/ 22 Tue 12/ 13/ 22 91 93 4. 2. 13- WQCF Master Plan Summary 30 days Wed 12/ 14/ 22 Thu 2/ 2/ 23 92 94 4.3- Evaluate Operation and Maintenance Program 90 days Wed 11/ 30/ 22 Thu 4/ 13/ 23 95 4. 3. 1- Review Current Operation and Maintenance Practices 30 days Wed 11/ 30/ 22 Thu 1/ 19/ 23 93FS- 40 days Trot 96 4. 3. 2- Assess Need for Additional Resources and Equipment 15 days Fri 1/ 20123 Thu 2/ 9/ 23 95 97 4. 33- Prepare Cost Estimates and Recommendations 15 days Fri 2/ 10/ 23 Thu 3/ 2/ 23 96 98 4. 3. 4- Prepare Draft Report 15 days Fri 3/ 3/ 23 Thu 3/ 23/ 23 97 99 4. 3. 5- Prepare Final Report 15 days Fri 3/ 24/ 23 Thu 4/ 13/ 23 98 100 4. 4- CIP Development 71 days Fri 4/ 14/ 23 Fri 7/ 21/ 23 tot 4. 4. 1- Prepare Draft CIP 30 days Fri 4/ 14/ 23 Thu 5/ 25/ 23 79, 93, 99 102 Review Workshop 1 day Fri 6/ 9/ 23 Fri 6/ 9/ 23 101F5+ 10 days 103 4. 4. 2- Prepare Final CIP 30 days Mon 6/ 12/ 23 Fri 7/ 21123 102 T 1D4 4. 5- Final Report Document 70 days Mon 7/ 24/ 23 Fri 10/ 27/ 23 i
105 4.5. 1- Prepare Executive Summary 10 days Mon 7/ 24/ 23 Fri 8/ 4/ 23 103 L-7t 106 4. 5. 2- Prepare Draft Report Document 20 days Mon 8/ 7/ 23 Fri 9/ l/ 23 105 107 Master Plan Review 20 days Mon 9/ 4/ 23 Fri 9/ 29/ 23 106 E
108 4.5. 3- Prepare Final Report Document 20 days Mon 10/ 2/ 23 Fri 10/ 27/ 23 107 ic Models for Phased Mon 6/ 21 Thu
10 Mon 6/ 21 Fri 1 72
1011
S
S. 2- Pelpare Model Recommendation TM 5daysss Mon 12/20/ 21 Mn21/ 3/22 110 T, 112 5. 3- Hydraulic Model Training 5 days Wed 12/ 21/ 22 Thu 1/ 5/ 23 79 113 6- Wastewater Master Plan Environmental Document 30 days Fri 3/ 3/ 23 Thu 4/ 13/ 23 114 6. 1- Review Documents 10 days Fri 3/ 3/ 23 Thu 3/ 16/ 23 93FS+ 20 days 115 6. 2- Prepare Draft TM 10 days Fri 3/ 17/ 23 Thu 3/ 30/ 23 114 116 6. 3- Prepare Final TM 10 days Fri 3/ 31/ 23 Thu 4/ 13/ 23 115 7 117 7- Staffing Plan 35 days Fri 3/ 17/ 23 Thu 5/ 4/ 23 J120

7. 1- Evaluate Current and Future Staffing Needs 15 days Fri 3/ 17/ 23 Thu 4/ 6/ 23

7. 2- Prepare Draft TM 10 days Fri 4/ 7/ 23 Thu 4/ 20/ 23 93FS+
118
30 days1
L71

7. 1- Prepare Final TM 10 days Fri 4/ 21/ 23 Thu 5/ 4/ 23 119 8- Communications Strategy 350 days Thu 10/ 28/ 21 Wed 12/ 20/ 23 CIA_

Page 1 ends

Exhibit "B" ATTACHMENT 3
ATTACHMENT 4

INSURANCE
Exhibit "B" ATTACHMENT 3

ACORV CERTIFICATE OF LIABILITY INSURANCE

DATE( MM/ DD/ YYYY)

16. 5/ 1/ 2022 1 10/ 14/ 2021
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS

CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER( S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.

IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy( ies) must have ADDITIONAL INSURED provisions or be endorsed.

If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement( s).

CONTACT PRODUCER Lockton Companies NAME:
444 W. 47th Street, Suite 900 PHONE FAX
Kansas City MO 64112- 1906 MAIL Ext: A/ C No
816) 960- 9000
ADDRESS:

INSURERS AFFORDING COVERAGE NAIC#
INSURER A: Berkshire Hathaway Specialty Insurance Company 22276

INSURED
STANTEC CONSULTING SERVICES INC. INSURER B: Travelers Property Casualty Co Of America 25674 1415077
370 INTERLOCKEN BOULEVARD, SUITE 300 INSURER C:

BROOMFIELD CO 80021- 8012 INSURER D:

INSURER E:

INSURER F
COVERAGES CERTIFICATE NUMBER: 17946129 REVISION NUMBER: XXXXXXX

THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS

CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.

INSR

TYPE OF INSURANCE

ADDL SUER POLICY EFF POLICY EXP

LTR LIMITS IN SD WVD POLICY NUMBER MM/ DD/ YM MM/ DD/ YYYY A X

COMMERCIAL GENERAL LIABILITY
y Y 47- GLO- 307584 5/ 1/ 2021 5/ 1/ 2022 EACH OCCURRENCE 21000, 000

CLAIMS- MADE

DAM GE O RENTED
X OCCUR PREMISES Ea occunence $ 1, 000, 000
X CONTRACTUAL/ CROSS MED EXP( Any one person) $ 25, 000 X XCU COVERED PERSONAL& ADV INJURY $ 21000, 000
GEN' L AGGREGATE LIMIT APPLIES PER: GENERAL AGGREGATE $ 4, 000, 000 POLICY
PROX LOC PRODUCTS- COMP/ OP AGG $ 2 00O 000
OTHER: I
AUTOMOBILE LIABILITY y y
TC2J- CAP- 8E086819 AOS Ea accident$/ I/ 2021 $/ 1/ 2022 COMBINED SINGLE LIMIT $ 1 B TJ- BAP- 8E086820 5/ l/ 2021 5/ 1/ 2022
000 000
B X
ANY AUTO TC2J- CAP- 8E087017( NJ) 5/ 1/ 2021 5/ 1/ 2022 BODILY INJURY( Per person) $ Y' {XXXXX

OWNED SCHEDULED

ATOS ONLY AUTOS
BODILY INJURY( Per accident) $ XXXXXXX

HIRED NON- OWNED PROPERTY DAMAGE
AUTOS ONLY AUTOS ONLY Per accident XXXXXXX

XXXXXXX
A X

UMBRELLA LIAB F
OCCUR N N 47- UMO- 307585 l/ 2021 5/ 1/ 2022 EACH OCCURRENCE 5, 000, 000 X
EXCESS LIAB CLAIMS- MADE AGGREGATE 5, 000, 000
DIED RETENTION$ XXXXXXX

WORKERS COMPENSATION Y X
PER OTHB AND EMPLOYERS' LIABILITY UB- 3P635310 AOS) 5/ 1/ 2021 5/ 1/ 2022 STATUTE ER BANY
Y/ N
UB- 3P533004( MA, WI) 5/ 1/ 2021 5/ 1/ 2022
B OFFICER/ MEMBPROPRIETER EXCLUDED?

ECUTIVE

N N/ A EXCEPT FOR OH ND A WY
E. L. EACH ACCIDENT 1 OOO OOO
Mandatory In NH) E. L. DISEASE- EA EMPLOYEE $ 1, 000, 000 If yes, describe under
DESCRIPTION OF OPERATIONS below E. L. DISEASE- POLICY LIMIT $ 1, 000, 000 DESCRIPTION OF OPERATIONS/ LOCATIONS/ VEHICLES ( ACORD 101, Additional Remarks Schedule, may be attached if more space is required) PROJECT#: 184031483. PROJECT NAME: THE CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROJECT. CITY OF MANTECA, ITS

OFFICERS, OFFICIALS, EMPLOYEES, AGENTS AND VOLUNTEERS ARE ADDITIONAL INSUREDS AS RESPECTS GENERAL LIABILITY AND AUTO LIABILITY, AND THESE COVERAGES ARE PRIMARY AND NON- CONTRIBUTORY, IF REQUIRED BY WRITTEN CONTRACT. WAIVER OF SUBROGATION APPLIES TO GENERAL

LIABILITY,AUTO LIABILITY AND WORKERS COMPENSATIONIEMPLOYER' S LIABILITY WHERE ALLOWED BY STATE LAW AND IF REQUIRED BY WRITTEN CONTRACT.

CERTIFICATE HOLDER CANCELLATION See Attachments
17946129

CITY OF MANTECA SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE ATTN: ELBA MIJANGO, ASSOCIATE ENGINEER

THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN 1001 W. CENTER STREET
ACCORDANCE WITH THE POLICY PROVISIONS.

MANTECA CA 95337

AUTHORIZED REPRESENTATI
1988 015 ACORD CORPORATION. All rights reserved.

ACORD 25( 2016/ 03) The ACORD name and logo are registered marks of ACORD Exhibit "B" ATTACHMENT 3
Attachment Code: D564542 Master ID: 1415077, Certificate ID: 17946129 Lockton Companies
444 W. 47th Street, Suite 900
Kansas City, MO 64112
STANTEC CONSULTING SERVICES INC..; 1415077

ROCKTIM
17946129

CITY OF MANTECA
1001 W. CENTER STREET,
MANTECA, CA 95337
Dear Valued Client:

In our continuing effort to provide timely certificate delivery, Lockton Companies is utilizing paperless delivery of Certificates of Insurance.

To ensure electronic delivery for future renewals of this certificate, we need your email address. Please contact us via the email below and reference Certificate ID: 17946129. You must reference this Certificate ID number in order for us to complete this process. o Certificate ID: 17946129
o Email: lcctsu@locicton. com
o Subject Line: TSU E- Delivery
If you received this certificate through an internet link where the current certificate is viewable, we have your email and no further action is needed.

Please note that after February 2022, printed certificates will no longer be available.

If you no longer need this certificate, please contact us at the email address above, reference the Holder ID number and use this subject line: " Certificate Removal" NOTE. The above email is a collector email regarding electronic delivery of certificates only. Please do NOT send certifica to requests or other insurance inquiries to this inbox as responses will be delayed or missed.

Thank you for your cooperation and willingness in reducing our environmental footprint.

Lockton Companies
Technical Services Unit
Email/ Mailing Update- Liability Certificates
Exhibit "B" ATTACHMENT 3
Attachment Code: D522032 Certificate ID: 17946129
POLICY NUMBER: 47- GLO- 307584 COMMERCIAL GENERAL LIABILITY CG 20 10 0413
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

ADDITIONAL INSURED - OWNERS, LESSEES OR

CONTRACTORS - SCHEDULED PERSON OR

ORGANIZATION
This endorsement modifies insurance provided under the following:

COMMERCIAL GENERAL LIABILITY COVERAGE PART

SCHEDULE
Name Of Additional Insured Person( s)
Or Organization( s) Locations Of Covered Operations

ALL LOCATIONS COVERED UNDER THIS POLICY, FOR

ANY SUCH PERSON OR ORGANIZATION BUT ONLY TO LIABILITIES ARISING OUT OF OUR NAMED INSURED' S HE EXTENT REQUIRED BY A WRITTEN CONTRACT ACTIVITIES ONLY.

EXECUTED PRIOR TO THE" OCCURANCE" FOR OFFENSE.

Information required to complete this Schedule, if not shown above, will be shown in the Declarations.

A. Section If — Who Is An Insured is amended to B. With respect to the insurance afforded to these include as an additional insured the person( s) or additional insureds, the following additional organization( s) shown in the Schedule, but only exclusions apply:
with respect to liability for" bodily injury", " property This insurance does not apply to " bodily injury" or damage or personal and advertising injury 11property damage" occurring after:
caused, in whole or in part, by:

1. Your acts or omissions; or

1. All work, including materials, parts or
equipment furnished in connection with such

2. The acts or omissions of those acting on your work, on the project ( other than service, behalf; maintenance or repairs) to be performed by or
in the performance of your ongoing operations for on behalf of the additional insured( s) at the the additional insured( s) at the location( s)
location of the covered operations has been
designated above.
completed; or
However: 2. That portion of " your work" out of which the injury or damage arises has been put to its

1. The insurance afforded to such additional intended use by any person or organization insured only applies to the extent permitted by other than another contractor or subcontractor law; and engaged in performing operations for a

2. If coverage provided to the additional insured principal as a part of the same project. is required by a contract or agreement, the
insurance afforded to such additional insured
will not be broader than that which you are
required by the contract or agreement to
provide for such additional insured.

CG 20 10 04 13 Insurance Services Office, Inc., 2012 Page 1 of 2 Exhibit "B" ATTACHMENT 3
Attachment Code: D522032 Certificate ID: 17946129
C. With respect to the insurance afforded to these 2. Available under the applicable Limits of additional insureds, the following is added to Insurance shown in the Declarations; Section III— Limits Of Insurance: whichever is less.

If coverage provided to the additional insured is This endorsement shall not increase the required by a contract or agreement, the most we applicable Limits of Insurance shown in the will pay on behalf of the additional insured is the Declarations. amount of insurance:

1. Required by the contract or agreement; or
CG 20 10 04 13 Insurance Services Office, Inc., 2012
PAGE 2 of 2
Exhibit "B" ATTACHMENT 3
Attachment Code: D522054 Certificate ID: 17946129
POLICY NUMBER: 47- GLO- 307584 COMMERCIAL GENERAL LIABILITY CG 20 37 04 13
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

ADDITIONAL INSURED - OWNERS, LESSEES OR

CONTRACTORS - COMPLETED OPERATIONS
This endorsement modifies insurance provided under the following:

COMMERCIAL GENERAL LIABILITY COVERAGE PART

PRODUCTS/ COMPLETED OPERATIONS LIABILITY COVERAGE PART

SCHEDULE
Name Of Additional Insured Person( s)
Or Organization( s) Location And Description Of Completed Operations

ANY LOCATION OR PROJECT WHERE YOU ARE

ANY SUCH PERSON OR ORGANIZATION REQUIRED TO PROVIDE ADDITIONAL INSURED

BUT ONLY TO THE EXTENT REQUIRED BY STATUS IN A WRITTEN CONTRACT OR WRITTEN

A WRITTEN CONTRACT EXECUTED

AGREEMENT, EXCEPT WHERE SUCH CONTRACT OR
PRIOR TO THE " OCCURANCE" FOR

AGREEMENT IS PROHIBITED BY LAW
OFFENSE.

Information required to complete this Schedule, if not shown above, will be shown in the Declarations.

A. Section II — Who Is An Insured is amended to B. With respect to the insurance afforded to these include as an additional insured the person( s) or additional insureds, the following is added to organization( s) shown in the Schedule, but only Section III— Limits Of Insurance:
with respect to liability for " bodily injury" or If coverage provided to the additional insured is property damage" caused, in whole or in part, by required by a contract or agreement, the most we your work" at the location designated and will pay on behalf of the additional insured is the described in the Schedule of this endorsement amount of insurance:
performed for that additional insured and
included in the " products- completed operations 1. Required by the contract or agreement; or hazard". 2. Available under the applicable Limits of
However: Insurance shown in the Declarations;

1. The insurance afforded to such additional whichever is less. insured only applies to the extent permitted by This endorsement shall not increase the applicable law; and Limits of Insurance shown in the Declarations.

2. If coverage provided to the additional insured
is required by a contract or agreement, the
insurance afforded to such additional insured
will not be broader than that which you are
required by the contract or agreement to
provide for such additional insured.

CG 20 37 04 13 Insurance Services Office, Inc., 2012 Page 1 of 1 Wolters Kluwer Financial Services I Uniform FormsTM
Exhibit "B" ATTACHMENT 3
Attachment Code: D522252 Certificate ID: 17946129
Notification to Others of Cancellation
Policy No. Eff. Date of Pol. Exp. Date of Pol. Eff. Date of End. Producer No. Add' l. Prem Retum Prem. 47- GLO- 307584 5/ 1/ 2021 5/ 1/ 2022
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

This endorsement modifies insurance provided under the:

Commercial General Liability Coverage Part
Liquor Liability Coverage Part
Products/Completed Operations Liability Coverage Part
A. If we cancel this Coverage Part( s) by written notice to the first Named Insured for any reason other than nonpayment of premium, we will mail or deliver a copy of such written notice of cancellation:

1. To the name and address corresponding to each person or organization shown in the Schedule below; and

2. At least 10 days prior to the effective date of the cancellation, as advised in our notice to the first Named Insured, or the longer number of days notice if indicated in the Schedule below.

B. If we cancel this Coverage Part( s) by written notice to the first Named Insured for nonpayment of premium, we will mail or deliver a copy of such written notice of cancellation to the name and address corresponding to each person or organization shown in the Schedule below at least 10 days prior to the effective date of such cancellation.

C. If notice as described in Paragraphs A. or B. of this endorsement is mailed, proof of mailing will be sufficient proof of such notice.

SCHEDULE
Name and Address of Other Person( s)/ Organization( s):

Those
Cancellation.

Insurance,
persons
on
and
file
organizations
with the insurer,
as stated
as of
in
the
a
date
certificate
of
of 30
Number
Notice:

All other terms and conditions of this policy remain unchanged.

Includes copyrighted material of Insurance Services Office, Inc., with its permission.

Exhibit "B" ATTACHMENT 3
POLICY NUMBER: TC2J- CAP- 8E086819 ( AOS); TJ- BAP- 8E086820; TC2J- CAP- 8E087017 NJ)
ILT4001209
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

DESIGNATED ENTITY - NOTICE OF

CANCELLATIONMON RENEWAL PROVIDED BY US
This endorsement modifies insurance provided under the following:

ALL COVERAGE PARTS INCLUDED IN THIS POLICY

SCHEDULE
CANCELLATION NUMBER OF DAYS NOTICE OF CANCELLATION:
30 NONRENEWAL NUMBER OF DAYS NOTICE OF
NONRENEWAL: 30
PERSON OR ORGANIZATION: Where Required By Written Contract ADDRESS:

PROVISIONS:

A. If we cancel this policy for any statutorily permitted reason other than nonpayment of premium, and a number of days is shown for cancellation in the schedule above, we will mail notice of cancellation to the person or organization shown in the schedule above. We will mail such notice to the address shown in the schedule above at least the number of days shown for cancellation in the schedule above before the effective date of cancellation.

B. If we decide not to renew this policy for any statutorily permitted reason, and a number of days is shown for nonrenewal in the schedule above, we will mail notice of nonrenewal to the person or organization shown in the schedule above. We will mail such notice to the address shown in the schedule above at least the number of days shown for nonrenewal in the schedule above before the expiration date.

ILT4001209
Attachment Code: D522107
Certificate ID: 17946129
Exhibit "B" ATTACHMENT 3

WORKERS COMPENSATION
AND

EMPLOYERS LIABILITY POLICY
ENDORSEMENT WC 99 06 R3 ( 00)
POLICY NUMBER: UB- 3P635310 ( AOS); UB- 3P533004 ( MA, WI)

NOTICE OF CANCELLATION

TO DESIGNATED PERSONS OR ORGANIZATIONS
The following is added to PART SIX - CONDITIONS:

Notice of Cancellation To Designated Persons Or Organizations If we cancel this policy for any reason other than non- payment of premium by you, we will provide notice of such cancellation to each person or organization designated in the Schedule below. We will mail or deliver such notice to each person or organization at its listed address at least the number of days shown for that person or organization before the cancellation is to take effect.

You are responsible for providing us with the information necessary to accurately complete the Schedule below. If we cannot mail or deliver a notice of cancellation to a designated person or organization because the name or address of such designated person or organization provided to us is not accurate or complete, we have no responsibility to mail, delivery or otherwise notify such designated person or organization of the cancellation.

SCHEDULE
Name and Address of Designated Persons or Organizations:

WHERE REQUIRED BY WRITTEN CONTRACT.

Number of Days Notice: 30
ALL OTHER TERMS AND CONDITIONS OF THIS POLICY REMAIN UNCHANGED.

Attachment Code: D522110
Certificate ID: 17946129
Exhibit "B" ATTACHMENT 3

DATE( MM/ DD/ YYYY)
ACOR" CERTIFICATE OF LIABILITY INSURANCE 16.. 10/ 1/ 2022 10/ 14/ 2021 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS

CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER( S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.

IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy( ies) must have ADDITIONAL INSURED provisions or be endorsed.

If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement( s).

CONTACT PRODUCER Lockton Companies NAME:
444 W. 47th Street, Suite 900 PHONE
fA
FAX
City MO 64112- 1906 E- MAIL
Ezt: AIC No
816) 960- 9000
ADDRESS:

INSURERS AFFORDING COVERAGE NAIC#
INSURER A: Berkshire Hathaway Specialty Insurance Company 22276

INSURED
STANTEC CONSULTING SERVICES INC. INSURER B: AIG Specialty Insurance Company 26883 1414100
370 INTERLOCKEN BOULEVARD, SUITE 300 INSURER C:

BROOMFIELD CO 80021- 8012 INSURERD:

INSURER E:

INSURER F:

COVERAGES CERTIFICATE NUMBER: 17946135 REVISION NUMBER: XXXXXXX

THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS

CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.

INSR

TYPE OF INSURANCE

ADDL SUBR POLICY EFF POLICY EXP

LTR LIMITS IN D WVD POLICY NUMBER MM/ DD/ YYYY MM/ DD/ YYYY

COMMERCIAL GENERAL LIABILITY

NOT APPLICABLE EACH OCCURRENCE XXXXXXX
CLAIMS- MADE F1 OCCUR

DAMAGE TO RENTED
PREMISES Ea occunence $ XXXXXXX
MED EXP( Any one person) $ XXXXXXX
PERSONAL& ADV INJURY $ XXXXXXX
GEN' L AGGREGATE LIMIT APPLIES PER: GENERAL AGGREGATE $ XXXXXXX POLICY NI PECOT- X LOC PRODUCTS- COMP/ OP AGG $ XXXXXXX OTHER:

AUTOMOBILE LIABILITY NOT APPLICABLE
Ea aBINEDtSINGLE LIMIT $

XXXXXXX
ANY AUTO BODILY INJURY( Per person) $ XXXXXXX
OWNED SCHEDULED BODILY INJURY( Per accident) $

AUTOS ONLY AUTOS XXXXXXX

HIRED NON- OWNED PROPERTY DAMAGE
AUTOS ONLY AUTOS ONLY Per accident XXX CSOO
XXXXXxx

UMBRELLA LIAB OCCUR NOT APPLICABLE EACH OCCURRENCE XXXXXXX

EXCESS LIAB CLAIMS- MADE AGGREGATE XXXXXXX
DED RETENTION$ XXXXXXX

WORKERS COMPENSATION NOT APPLICABLE
PER OTHAND EMPLOYERS' LIABILITY STATUTE ER
YIN
ANY PROPRIETOR/ PARTNER/ EXECUTIVE E. L. EACH ACCIDENT XXXXXXX OFFICER/ MEMBER EXCLUDE D? N f A
Mandatory In NH) E. L. DISEASE- EA EMPLOYEE $ }{{}}{ X'} X If yes, describe under
DESCRIPTION OF OPERATIONS below E. L. DISEASE- POLICY LIMIT $ XXXXXXX A Professional Liab N N 47- EPP- 308810 10/ 1/ 2021 10/ 1/ 2022 $ 3, 000, 000 PER CLAIM/ AGG

A NO RETROACTIVE DATE INCLUSIVE OF COSTS
B Contractors Pollution Liab CP08085428 10/ 1/ 2021 10/ 1/ 2023 $ 3, 000, 000 PER LOSS/ AGG DESCRIPTION OF OPERATIONS/ LOCATIONS/ VEHICLES ( ACORD 101, Additional Remarks Schedule, may be attached if more space is required) PROJECT#: 184031483. PROJECT NAME: THE CITY OF MANTECA WASTEWATER MASTER PLAN AND SEWER RATE STUDY PROJECT.

CERTIFICATE HOLDER CANCELLATION See Attachment
17946135

CITY OF MANTECA SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE ATTN: ELBA MIJANGO, ASSOCIATE ENGINEER

THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN 1001 W. CENTER STREET
ACCORDANCE WITH THE POLICY PROVISIONS.

MANTECA CA 95337

AUTHORIZED REPRESENTA
1988 015 ACORD CORPORATION. All rights reserved.

ACORD 25( 2016/ 03) The ACORD name and logo are registered marks of ACORD Exhibit "B" ATTACHMENT 3
Attachment Code: D522052 Certificate ID: 17946135
Policy No: 47- EPP- 308810 , NO RETROACTIVE DATE
Named Insured: See Attached Certificate

PROFESSIONAL LIABILITY

NOTICE OF CANCELLATION FOR THIRD PARTIES
This contract is amended as follows:

In consideration of the premium charged, it is hereby understood and agreed as follows:
1 Underwriters authorize Lockton Com anies/ BFI Canada the " Certificate Issuer" to issue Certificates of Insurance at the request or direction of the Insured. It is expressly understood and agreed that, subject to Paragraph ( 2) below, any Certificate of Insurance so issued shall not confer any rights upon the Certificate Holder, create any obligation on the part of the Underwriters, or purport to, or be construed to, alter, extend, modify, amend, or otherwise change the terms or conditions of this Policy in any manner whatsoever. In the case of any conflict between the description of the terms and conditions of this Policy contained in any Certificate of Insurance on the one hand, and the terms and conditions of this Policy as set forth herein on the other, the terms and conditions of this Policy as set forth herein shall control. 2) Notwithstanding Paragraph ( 1) above, such Certificates of Insurance as are authorized under this endorsement may provide that in the event the Underwriters cancel or non- renew this Policy or in the event of a Material Change to this Policy, Underwriters shall mail written notice of such cancellation, non- renewal, or Material Change to such Certificate Holder 30 days prior to the effective date of cancellation, non- renewal, or a Material Change, but 10 days prior to the effective date of cancellation in the event the Assured has failed to pay a premium when due. The Insured shall provide written notice to the Underwriters of all such Certificate Holders, if any, specified in each Certificate of Insurance ( i) at inception of this Policy, (ii) 90 days prior to expiration of this Policy, or ( iii) within 10 days of receipt of a written request from Underwriters. Underwriters' obligation to mail notice of cancellation, non- renewal, or a Material Change as provided in this paragraph shall apply solely to those Certificate Holders with respect to whom the Assured has provided the foregoing written notice to the Underwriters.
3) It is further understood and agreed that Underwriters' authorization of the Certificate Issuer under this endorsement is limited solely to the issuance of Certificates of Insurance and does not authorize, empower, or appoint the Certificate Issuer to act as an agent for the Underwriters or bind the Underwriters for any other purpose. The Certificate Issuer shall be solely responsible for any errors or omissions in connection with the issuance of any Certificate of Insurance pursuant to this endorsement. 4) As used in this endorsement:
1) Certificate of Insurance means a document issued for informational purposes only as evidence of the existence and terms of this Policy in order to satisfy a contractual obligation of the Assured.
2) Material Change means an endorsement to or amendment of this Policy after issuance of this Policy by the Underwriters that restricts the coverage afforded to the Assured.

All other terms and conditions remain unchanged.