City of Manteca
Development Services Department
Conditions of Approval
AGS Apartments
General Plan Amendment GPA 23-68, Planned Development PD 23-69, Rezone REZ 23-67, and Site Plan Design Review 23-70 February 20, 2024
Project Name: AGS Apartments
Project Files: GPA 23-68, PD 23-69, REZ 23-67, and SPA 23-70 Applicant: AGS Family Holdings, LLC.
837 Kalthoff Common
Livermore, CA 94550
Project Location: 905 Davis Street
Manteca, CA 95337
APN: 217-600-05
This list of conditions is not intended to be a comprehensive list of City regulations. All conditions are referenced to the plans dated November 8, 2023 which are on file with the City of Manteca, Development Services Department.

Development Services Department: Planning
Approval. This Site Plan Review and Planned Development is approved subject to these specific conditions. Any variation from the approved plans, proposals, supporting documents or presentations is subject to review and approval prior to implementation.

Conformance to Plans. This approval is dependent upon and limited to the proposals and plans contained, supporting documents submitted, and presentations made to staff, the Planning Commission, and/or City Council as affirmed to by the applicant and presented on the plans dated November 8, 2023. Any variation from these plans, proposals, supporting documents or presentations is subject to review and approval prior to implementation.

Expiration. The Site Plan Review and Planned Development shall expire two years from this date on February 20, 2026, unless altered and/or extended per State law. Prior to expiration, the owner/developer may apply for an extension, to be approved by the Development Services Director, not to exceed a total of one (1) year from the original date of expiration.

Owner Obligation. All conditions of approval shall be satisfied by the owner/developer. If at any time, any of the Conditions of Approval are found to be in non-compliance, City enforcement action may be implemented pursuant to Manteca Municipal Code, Article 1, Chapter 1.10. All costs associated with compliance with the conditions shall be at the owner/developer’s expense.

Fees. The developer shall pay all applicable processing fees, permit fees, City development fees, fire fees, school fees, drainage fees, habitat conservation fees and other public entity fees in effect at the time of the issuance of the applicable permit.

CFD. CFD or other approved funding source shall be formed, at the developer’s expense, to provide for the maintenance of any park/basin, streetlights, open spaces and all streetscape/median landscape improvements and the negative fiscal impacts associated with the provision of police protection, fire suppression and road maintenance services for new development. Said CFD, or other funding sources, shall be in place prior to the issuance of the first building permit as further defined in the City of Manteca Parkland Construction Policy. Developer shall be responsible for maintenance of improvements until sufficient funding through the collection of full special tax revenue is available/collected for City to maintain. This may be accomplished through a maintenance agreement, direct payment to City or other means.

Utility Companies. The applicant is responsible for contacting all appropriate utility companies to obtain agreements for extension and/or relocation of services necessary for the proposed development.

Signs. No business identification signs or any advertising signs shall be installed or displayed without the review and approval of the Development Services Department, and all proposed advertising signs shall comply with Section 20.14.20 of the Zoning Ordinance.

Vested Rights. This approval does not vest applicant’s rights regarding future development. All ordinances, resolutions, rules, regulations and official policies governing design, improvement and construction standards and specifications applicable to the project and public improvements to be constructed by the Developer shall be those in force and effect at the time the applicable plan or permit approval is granted.

Responsible Agencies. The Developer is responsible for contacting all responsible and commenting agencies and ensuring compliance with any applicable fees and/or rules. This project is subject to the requirements of other agencies including but not limited to San Joaquin County Multi-Species Habitat Conservation & Open Space Plan, San Joaquin Valley Air Pollution Control District, and PG&E.

Subsequent Development. All activities undertaken in accordance with this approval shall comply with the City’s General Plan and Municipal Code. In cases of conflict between the City’s Municipal Code or map-specific conditions of approval, the governing priority shall be, to the extent legally permitted, as follows: 1) Municipal Code regulations, 2) project-specific conditions, and 3) standard conditions. The applicant shall comply with all regulations and code requirements of the Development Services Director, City Engineer, and Building Official, the Fire Chief, the Police Chief, and any other agencies requiring review of the project. If required, these agencies shall be supplied copies of the final maps, site plans, public improvement plans, grading plans, and building plans.

Building Plans. The project developer shall write all conditions of approval for this project on all building permit plan check sets submitted for review and approval. These conditions of approval shall be on, at all times, all grading and construction plans kept on the project site. It is the responsibility of the building developer to ensure that the project contractor is aware of, and abides by, all conditions of approval. Prior approval from the Planning Manager must be received before any changes are constituted in site design, grading, building design, building colors or materials, etc.

Failure to Comply. Should the project be found, at any time, not to comply with any of the Conditions of Approval, or should the applicant construct or operate this development in any way other than as specified in the Application or Supporting documents or presentations to staff, the Planning Commission, or City Council, as modified by the Conditions of this Approval, then the terms of this Approval shall be considered to be violated.

Indemnification. The applicant shall indemnify and hold harmless the City, its council members and commissioners, officers, agents, employees, and representatives from liability for any award, damages, costs and fees, including without limitation attorneys’ fees, incurred by the City and/or awarded to any plaintiff in any action related to or arising out of the City’s approval of this project or subdivision Map or any environmental or other documentation related to this project or subdivision Map. The applicant further agrees to provide a defense for the City in any such action.

Limits of Approval. Approval of this application does not constitute approval of any other entitlement or any other necessary permit, license, or approval.

Compliance with Local and State Laws. The subject use shall be conducted in full compliance with all local and state laws. No part of this approval shall be construed to permit a violation of any part of the Manteca Municipal Code. This Site Plan and design Review shall be subject to revocation if the subject use is conducted in such a manner as to cause a nuisance.

Changes in Law. This approval shall not preclude the application to development of the property of changes in City laws, regulations, plans or policies, the term of which are specifically mandated and required by changes in State or Federal laws or regulations.

Other entitlements. Approval of this application does not constitute approval of any other entitlement or any other necessary permit, license, or approval.

Performance Standards. Developer shall ensure ongoing compliance with City of Manteca Performance Standards, pursuant to Manteca Municipal Code Chapter 17.58.

Parking, Loading Areas, On-Site Circulation. All on-site parking, loading areas, and on-site circulation shall conform to the approved plans dated November 8, 2023.

Landscaping. On-site landscaping shall conform to the approved plans dated November 8, 2023, and conform to the Manteca Municipal Code. Required planting areas shall be permanently maintained by water, clearing debris and litter, weeding, pruning, insect control, and replacement of plant materials and irrigation equipment as needed to preserve the health and appearance of plant materials. All landscaping shall be maintained in such a manner as to not restrict designated pedestrian access. All trees, shrubs, and plants which, due to accident, damage, disease, or other cause, fail to show a healthy growth shall be replaced, in kind, pursuant to the approved landscape plans within 30 days from the identified damage date.

Storage, Screening, and Fencing. All storage, screening, and fencing shall conform to the approved plans dated November 8, 2023, and conform to the Manteca Municipal Code.

Roof-mounted Equipment. Applicant/developer shall ensure all roof-mounted equipment shall remain screened from public street view.

Lighting. All on-site lighting for parking areas, pedestrian areas, and vehicular or pedestrian paths of travel shall be LED lighting. Any new lighting is required to submit a photometric plan for review showing it complies with section 17.50.060.D. of the Manteca Municipal Code.

Site maintenance. The site shall be permanently maintained in a neat and clean manner free of weeds, trash, and debris.

CPTED. Landscaping and lighting shall be maintained to compliance with Crime Prevention through Environmental Design (CPTED) guidelines. Shrubs shall be limited to two feet in height, and mature trees shall be limbed up to six feet above the ground. Dead or dying plants shall be replaced with materials of equal size and similar variety.

Planned Development Guidelines. All development on site shall conform to the approved Planned Development Guidelines Document on file with the City of Manteca Development Services Department.

Development Services Department: Building Safety Division Accessible parking spaces complying with Section 1109A shall be provided. Clearly specify on the site plan whether assigned or unassigned parking spaces are to be provided. CBC Sections 1109A.4 and 1109A.5.

When assigned parking spaces are provided for a resident or a group of residents, at least 2 percent of the assigned parking spaces serving covered multifamily dwelling units shall be accessible in each type of parking facility. At least one space of each type of parking facility shall be made accessible even if the number exceeds 2 percent. CBC Section 1109A.4.

When parking is provided for covered multifamily dwellings and is not assigned to a resident or a group of residents at least 5 percent of the parking spaces shall be accessible and provide access to grade-level entrances of covered multifamily dwellings and facilities (e.g., swimming pools, club houses, recreation areas and laundry rooms) that serve covered multifamily dwellings.

One in every eight accessible spaces, but not less than one (1), shall be van accessible.

Access aisle shall be on the passenger’s side.

At least one accessible route shall be provided within the site from accessible parking spaces and accessible passenger loading zone; public streets and sidewalks; and public transportation stops to the accessible building or facility entrance they serve. Where more than one route is provided, all routes must be accessible. CBC Section 1110A.1.1.

At least one accessible route shall connect accessible buildings, accessible facilities, accessible elements, and accessible spaces that are on the same site. CBC Section 1110A.1.2.

An accessible route shall connect at least one accessible entrance of each multifamily dwelling unit with exterior spaces and facilities that serve the dwelling unit. CBC Section 1110A.1.4.

All ground-floor dwelling units in non-elevator buildings shall be accessible and adaptable. CBC Section 1104A.1.

Separate building permits shall be required for the apartment building, trash enclosure, signs etc.) per CBC Admin 104.

The Developer shall submit a certification prepared by a licensed land surveyor or registered civil engineer to the Chief Building Official, certifying that the building location (setbacks) is pursuant to the approved plans prior to receiving a foundation inspection.

Developer shall provide bike parking spaces in accordance with California Green Building Standards Code 4.106.9 for number and distance to the entrance.

Provide permanently anchored bicycle racks within 100 feet of the visitor’s entrance, readily visible to passers-by, for 5 percent of visitor motorized vehicle parking capacity with a minimum of one two-bike capacity rack. CGBSC Section 4.106.9.1 Provide on-site bicycle parking for at least one bicycle per every two dwelling units. CGBSC Section 4.106.9.2 Multifamily development projects with 20 or more dwelling units shall be subject to the following: CGBSC Section 4.106.4.2.2.

EV Capable – Ten (10) percent of the total number of parking spaces on a building site, provided for all types of parking facilities, shall be electric vehicle charging spaces (EV spaces) capable of supporting future Level 2 EVSE. Electrical load calculations shall demonstrate that the electrical panel service capacity and electrical system, including on-site distribution transformer(s), have sufficient capacity to simultaneously charge all EV’s at all required EV spaces at a minimum of 40 amperes.

EV Ready – Twenty-five (25) percent of the total number of parking spaces shall be equipped with low power Level 2 EV charging receptacles.

EV Chargers – Five (5) percent of the total number of parking spaces shall be equipped with Level 2 EVSE.

Construction documents shall indicate the location of proposed EV capable, ready and chargers.

The EV space shall be located adjacent to an accessible parking space meeting the requirements of the California Building Code, Chapter 11A, to allow use of the EV charger from the accessible parking space.

One in every 25 EV spaces, but not less than one, shall also have an 8-foot wide minimum aisle. A 5-foot wide minimum aisle shall be permitted provided the minimum width of the EV space is 12 feet.

The project shall comply with the more restrictive of the outdoor potable water reduction requirements of the California Green Building Standards Code 4.304 and the Manteca Water Efficient Landscape Ordinance. Please note this on the plans.

At time of building permit, submittal the developer shall incorporate all Conditions of Approvals from all departments and imprint into the submittal set of construction documents/plans.

City of Manteca Engineering Department
General
All improvements shall comply with the City of Manteca Standard Plans and Specifications. Improvement plans shall be submitted to the City Engineer for approval. An encroachment permit is required for all work within the public right-of-way.

Developer shall provide easements, requested by the respective utility companies, within the project subdivision. Any existing facilities within or adjacent to the project that are affected by this project shall be relocated and placed underground at the Developer’s expense.

Developer shall dedicate ten-foot (10’) wide public utility easements along the Walnut Street frontage for underground facilities and appurtenances.

Developer shall indicate on the improvement plans topographical information which shall include one-foot (1’) contour intervals and benchmark data based on City datum.

During all construction phases, the developer shall comply with City Laws regarding dust control. The developer shall also comply with San Joaquin Valley Unified Air Pollution Control District Regulation VIII (Fugitive Dust Prohibitions) in an effort to reduce the amount of fine particulate matter (PM10) entrained into the ambient air from man-made sources.

Prior to the start of construction, all survey monuments that have the possibility of being damaged, destroyed or covered over during the course of construction for this project, shall be located and referenced by a licensed land surveyor and a corner record or record of survey shall be filed with the county surveyor. Survey monuments which are damaged, destroyed or covered over during the course of construction must be re-set at the original location with a new monument and monument box and another corner record or record of survey shall be filed with the county surveyor. All work in this condition shall be done by a licensed land surveyor.

Prior to, or with, the Building Permit plan set the following shall be submitted. Review and approval of these items by the Engineering Department must occur prior to or with the issuance of the first building permit associated with this project:

On-site grading and drainage plan,
On-site utility (sanitary sewer, water and storm drain) plan, Off-site improvement plan,
Erosion control plans,
Stormwater Pollution Prevention Plan (SWPPP),
Documentation, as required in the Post-Construction Stormwater Standards Manual, showing compliance with WQO NPDES 2013-0001-DWQ, Joint Trench Intent plans, and
Dedication of required rights-of-way and easements to the City.

The plans specified in (a), (b) and (c) above shall be prepared by a Registered Civil Engineer.

The items in (d), (e) and (f) above shall be prepared by a Qualified SWPPP Developer (QSD).

Joint trench utility installation shall be in accordance with Manteca Municipal Code Chapter 13.34 and City Standards.

All address numbers shall be plainly visible from the street fronting the property. Said numbers/letters shall contrast with background.

If required by the City Engineer, the developer shall enter into an Improvement Agreement for construction of the roadway and utility improvements which will be dedicated to the City. The agreement will require posting a Performance Bond in the amount of one-hundred percent (100%), posting a Labor-Material Bond in the amount of fifty percent (50%), and payment of all required plan check, testing and inspection fees.

Improvements which will be dedicated to the City must use a benchmark on the City of Manteca Vertical Control Network to establish the elevations of the improvements. The benchmark used shall be noted on the Improvement Plans.

Site
On-site parking area pavement surface drainage slope shall be as follows: Minimum cross-slope on asphalt concrete is 2% or concrete is 1% with a maximum of 5%. Concrete valley or curb gutters shall have a minimum slope of 0.25%. The pavement slope in ADA areas shall be in accordance with the California Building Code, Chapter 11B.

Provide City Standard Refuse/Recycling Enclosures on-site at the locations shown on the site plan. Sizing shall be in accordance with City Standards.

The refuse enclosure shall be graded so there is no storm drain or other flow run-on or run-off from the enclosure area. The enclosure area shall have a connection to the storm system, in compliance with the City’s Post-Construction Manual.

On-site curbing shall conform to City of Manteca Standard ST-35, "Parking Area Curbs”.

Curbing shall be painted red, as require by the Fire Department, to restrict parking.

Developer shall ensure no buildings are constructed across property lines.

Landscape planting at driveway entrances/exits shall be maintained to a maximum height of three and one-half feet (3.5’).

Streets
The street pavement structural design shall conform to City of Manteca Resolution R-5633, “Street Structural Design Policy”. The minimum traffic indices shall be as follows:
60’ rights-of-way: 8.0
50’ rights-of-way: 6.0
No driveway shall be closer than twenty-feet (20’) to a curb return. Driveway locations shall be shown on Improvement Plan submittals.

Existing driveways which are not to be used by this project shall be removed and replaced with sidewalk, vertical curb and gutter.

Developer shall contact the local post office for direction regarding placement of mail receptacles or any other type of mail delivery proposed.

Developer shall ensure the structural sections of the existing roadways which are adjacent to this project are in accordance with the traffic indices in these conditions. The developer may remove and replace the existing pavement with a new structural section, in accordance with the specified traffic index or the Developer may core the existing pavement and submit the results to the City Engineer for approval to leave the existing structural section in place. The surface of the roadway where the existing pavement structural section is approved to remain shall be removed and replaced with an overlay, which is done at the same time as the adjacent new pavement.

The electrolier locations shall be finalized during the Improvement Plan review process. Electroliers shall maintain an average foot candle coverage of 0.40, with a minimum allowable foot candle at any location of 0.07, within the City’s right-of-way along the frontage of the project. Electrolier photometric plan, showing the foot candle coverage, shall be submitted with the Improvement Plans.

The thickness of all sidewalks installed with the project shall be six inches (6”).

Developer shall remove and replace the existing sidewalk, curb and gutter, and accessible ramps along the frontage of this project which is dilapidated, cracked or creates a tripping hazard. Sidewalk installed with this project shall be six inches (6”) thick.

Driveway(s) and accessibility ramps installed with this project shall follow the latest revision of the California Building Code, Chapter 11B and Caltrans Standard Plans, detail A88A.

Water
Improvements shall be constructed in conformance with the latest version of the City Water Master Plan.

The City’s Water Master Plan and User Rate Charges are currently being analyzed and updated by HydroScience. The update of the Master Plan is anticipated to be completed in late 2023. The Water Master Plan will identify improvement projects that need to be engineered and constructed for both the distribution system and the treatment systems. As the needed projects, both distribution and treatment, are identified, and associated costs estimated, user rates, connection charges, and Public Facilities Implementation Plan (PFIP) fees will likely increase. New development projects will have to pay the following fees, as adopted by the City Council, that are in place at the time of development/permit issuance: (1) User Rate Charges, (2) Connection Charges, and (3) PFIP fees.

A minimum ten-foot (10’) separation, from outside of pipe to outside of pipe, shall be maintained between water mains and parallel sanitary sewer, storm drain, and irrigation lines.

Existing wells within the boundary of the proposed development which are not approved for use by the City, shall be abandoned in accordance with San Joaquin County Public Health Services requirements.

Fire hydrant locations shall be as approved by the Fire Department and finalized during the Improvement Plan Building Permit review process. Developer shall provide and install fire hydrant “blue dot” reflective markers prior to issuance of the first building permit.

Water meters for each building shall be placed directly adjacent to the existing right-of-way.

Developer shall install a backflow prevention device immediately downstream of the water meters. The backflow prevention device shall be maintained by the Property Owner.

Developer shall install double check detector check valves (DCDCV) where the fire hydrant/fire service line enters the site from the public water system. The DCDCV shall be installed on private property immediately adjacent to the City right-of-way or a dedicated City access easement and shall be maintained by the property owner.

Existing service connections to the City’s water mains which will not be used by this project shall be abandoned, as directed by the City of Manteca.

Landscape irrigation water system shall be designed to operate from a single point of connection. Irrigation water from potable system shall be delivered via a single meter which is no larger than two (2) inch. Piping which is installed from the potable water system for the purposes of irrigation shall be purple pipe. This includes the valve boxes. Irrigation water from the potable system shall be protected with a reduced pressure backflow device.

Storm Drainage
Improvements shall be constructed in conformance with the latest edition of the Storm Drain Master Plan, the City’s Post-Construction Manual and City Standards.

A preliminary storm drainage plan shall be submitted to the City Engineer for approval concurrently with the first improvement plan submittal accompanied calculations for peak flows, total runoff, pipe sizes, bio retention volume and evidence of historical groundwater depth.

This project’s storm drain connection to the storm drainage system at Center Street and North Sun Haven Place. Provide verification that the existing storm drain connection has capacity for the project.

This project shall submit calculations, per Chapter 3, Section 3.1 of the City’s Storm Drain Master Plan, showing attenuation of the storm drain flows for this project is not required.

All drain inlets shall be marked "No Dumping - Drains to River". Drain markers shall be purchased from the City of Manteca at cost plus 15% administrative charge, and installed by the Developer prior to acceptance of the improvements.

Developer shall incorporate appropriate site design measure(s) and submit the results of the Post-Construction Runoff Standards Manual. The City of Manteca approval of the proposed measures is precedent to issuance of any building, grading or construction permits.

Developer shall develop and submit a Project Stormwater Plan that identifies the methods to be employed to reduce or eliminate stormwater pollutant discharges through the construction, operation and maintenance of source control measures, low impact development design, site design measures, stormwater treatment control measures, and hydromodification control measures. Design and sizing requirements shall comply with the 2015 Post – Construction Stormwater Standards Manual. City of Manteca approval of the Project Stormwater Plan is precedent to issuance of any building, grading, or construction permits. Two paper copies and an electronic copy of the Project Stormwater Plan shall be provided to the City of Manteca.

Developer shall develop and submit an Operations and Maintenance Plan that identifies the operations, maintenance, and inspection requirements of all stormwater treatment and baseline hydromodification control measures identified in the approved Project Stormwater Plan. City of Manteca approval of the preliminary Operations and Maintenance Plan is precedent to issuance of any building, grading, or construction permits. Two paper copies and an electronic copy of the Maintenance Plan shall be provided to the City of Manteca.

City of Manteca approval of the final Operations and Maintenance Plan and recordation of the Maintenance Access Agreement is precedent to first building final inspection for this project. Two paper copies and an electronic copy of the final Operations and Maintenance Plan shall be provided to the City of Manteca.

Post-Construction Management Practices shall conform to the City’s adopted Multi-Agency Post Construction Stormwater Standards Manual.

Where conflict between standards arises, the standard most-protective to water quality, to public health and safety, and against flooding shall be utilized.

Prior to any land disturbing construction activities occurring on a project, Developer shall meet the requirements of NPDES. For sites exceeding 1 acre of disturbance area that are deemed non-exempt, contractor shall prepare and submit a Storm Water Pollution Prevention Plan (SWPPP) and apply for a permit under the California General Construction NPDES permit. SWPPP shall be prepared and signed by a Qualified SWPPP Developer (QSD) certified by the State Water Resources Control Board. All modifications to SWPPP shall be implemented by a QSD in responsible charge for the project. The SWPPP shall be implemented under the supervision of a Qualified SWPPP Practitioner (QSP). For permit information, contact the State Water Resources Control Board (SWRCB) at:

State Water Resources Control Board
PO Box 1977, Sacramento, CA 95812-1977
Attn: Storm Water Permitting Section
Telephone: (916) 341-5537
To log in to the SWRCB Storm Water Multiple Application and Report Tracking System (SMARTS) to enter site information and apply for permit, please contact the City of Manteca Engineering Department to establish a project and authorize data entry access.

All other sites shall conform to the City of Manteca Standards, the California Green Building Standards, and Section E.10 of the NPDES permit 2013-0001-DWQ. All construction involving land disturbing activities shall submit for approval an Erosion Control and Sedimentation Plan (ESCP) prepared and signed by a QSD. All ESCP treatment measures and BMPs must be maintained at all times until construction is completed and the site is stabilized as defined under the Construction General NPDES permit.

Prior to issuance of the first grading or building permit for a project, a copy of the SWPPP or ESCP shall be submitted by the developer and approved by Authorized Signatory or Legally Responsible Person (LRP) for the City’s NPDES program. Contact the City of Manteca Engineering Department to identify appropriate person for review and approval of plans and documents.

It is recognized that the design and calculations which have been submitted thus far to demonstrate this project’s compliance with the City’s Post-Construction Stormwater Standards Manual is approved for project entitlements but may require further refinement for final approval, which is precedent to issuance of any building, grading, or construction permits.

Developer shall pay fair-share costs for storm drainage improvements, including improvements downstream to improve capacity or water quality treatments needed to conform to current Storm Drain Master Plan, City standards and support the development.

Developer shall complete the CDD development memorandum, required by Storm Drainage Agreement Amendment No. 1, and submit it to SSJID for review.

Sanitary Sewer
Improvements shall be constructed in conformance with the latest version of the City Wastewater Collection System Master Plan and City Standards.

The City’s Sewer Master Plan and User Rate Charges are currently being analyzed and updated by Stantec. The update of the Master Plan is anticipated to be completed in late 2023. The Sewer Master Plan will identify improvement projects that need to be engineered and constructed for both the collection system and the Wastewater Quality Control Facility (WQCF). As the needed projects, both collection and at the WQCF are identified, and associated costs estimated, user rates, connection charges, and Public Facilities Implementation Plan (PFIP) fees will likely increase. New development projects will have to pay the following fees, as adopted by the City Council, that are in place at the time of development/permit issuance: (1) User Rate Charges, (2) Connection Charges, and (3) PFIP fees.

A manhole shall be located at the back of the sidewalk, adjacent to City right-of-way, where the sanitary sewer main enters the development. This manhole shall be the end of the City’s maintenance responsibility for the sanitary sewer system.

Any existing septic tank(s) on the property that will not be approved by the City shall be abandoned in accordance with the permitting requirements of the San Joaquin County Environmental Health Department prior to issuance of the first building permit.

A preliminary sewer plan shall be submitted to the City Engineer for approval concurrently with the first improvement plan submittal. The plan shall be accompanied by calculations for peak wet weather flows showing pipe sizes and slopes for the entire development.

City of Manteca Public Works, Park Planning and Projects The Developer shall be required to pay fees as specified in the current Park Acquisition and Improvement Fee Policy (both park acquisition and improvement fee and park in-lieu of fee would apply).

All landscaping at back of walk/curb shall be the responsibility of the Owner.

City of Manteca Public Works, Solid Waste
Refuse bins shall not be larger than four (4) yards.

City of Manteca Fire Department, Office of the Fire Marshal Site Address:  Building address numbers shall be plainly visible from the street fronting the property.  Said building address numbers shall contrast with their background and be a minimum of 12” in height.

Building Numbers for rear buildings shall be visible from Main drive aisle. Building numbers will be placed in a uniform position on the building façade.

Individual units shall be numbered consecutively according to their floor. All units on the first floor shall be in the 100 series, second floor in the 200 series and third floor units in the 300 series.

Each building shall have a durable, all-weather sign listing the building designator and the units contained within.

Fire Department Access:

Provide a diagram showing a minimum of 44’ external radius and internal radius of 25’ on all main entries, drive aisle and parking lot areas. The main drive aisle shall be designated Emergency Vehicle Access Lane and be a minimum of 26’ wide.

A diagram showing proposed “Fire Lane” shall be submitted for approval to the Office of the Fire Marshal. Fire Lanes shall be marked in accordance with California Fire Code (Appendix D103.6 SIGNS and Manteca Fire Code 15.24 Fire Hydrants:  Plans and specifications for fire hydrant systems shall be submitted for review and approval prior to construction.

Fire hydrants shall be installed on a minimum 8-inch looped water main.

Fire hydrants shall be installed around all buildings at a maximum spacing of 300 feet in accordance with the City of Manteca Standards and California Fire Code.  Corners should be utilized for hydrant locations when possible.

Hydrants subject to vehicular damage shall be protected in an approved manner and not be obstructed by vehicles or other obstructions.

Provide 15 feet of clearance on either side of fire hydrant from stopped or parked vehicles.

Additional fire hydrants may be required to meet the minimum spacing requirement of hydrants within 90 feet of Fire Department Connections, (FDC) for Fire Sprinkler Systems.

The on-site fire protection system (fire hydrants and associated water mains) shall be installed prior to the issuance of building permits.

Total Fire Flow (appendix B of CFC) shall be calculated and submitted as part of the permit submittal.

Underground piping for the fire sprinkler shall be approved by the Fire Department prior to permit issuance.

All above ground gas meter, regulators, and piping exposed to vehicular damage shall be protected in an approved manner.

Fire Suppression Systems:  All buildings must be protected by an approved monitored automatic sprinkler system in accordance to NFPA 13, CFC, CBC, and Manteca Municipal Code Section 15.24.

Fire Alarm/Sprinkler monitoring shall be point ID.

Fire Suppression Approval.  Plans and specifications for fire suppression systems shall be submitted for review and approval prior to construction.  If work differs from approved plans, a set of “as built” shall be submitted to the Fire Department prior to final inspection.

Plans proposed to be listed as deferred submittals shall be clearly labeled on the cover building permit plan submittal cover sheet.

Inspections.  Fire protection systems (fire hydrants, water mains, etc.) shall be installed, tested and approved by the City prior to the issuance of any building permits.  The Fire Department shall witness all system and acceptance tests.  Please provide 24-hour notice prior to any system or acceptance tests.  209-456-8340.

A Fire Department approved “key lock box” shall be properly installed near the main entrance. A 3200 series lock box(s) can be order online directly from KNOXBOX.COM. Contact the Office of the Fire Marshal at HYPERLINK "mailto:[email protected]" [email protected] for additional information.

All above ground gas meters, regulators, and piping exposed to vehicular damage shall be protected in an approved manner.

Trash enclosures/dumpsters shall not be allowed within 5 feet of any combustible walls, openings, or combustible roof eaves, unless protected by an automatic fire sprinklers.

Operations that require operational permits (High Piled Storage, Hot Work, Compressed Gas, Battery Storage and all others listed in CFC 105) shall be identified on the plan submittal.

All above comments shall be listed in the Building Permit Plan Submittal in a section designated for Fire Comments. Additionally, the Authority Having Jurisdiction should be listed as:

Authority having Jurisdiction:

City of Manteca Fire Department,
Office of the Fire Marshal
Fire Inspector II Luis “Art” Salas
1154 S. Union Road, Manteca CA 95337
HYPERLINK "mailto:[email protected]" [email protected] San Joaquin County Environmental Health Department
For the proposed Neighborhood Market, submit two (2) hardcopy sets, or one (1) electronic version, of food facility plans to the Environmental Health Department for review and approval prior to issuance of building permit(s) (California Retail Food Code, Article 1, 114380). The fee will be based on the current schedule at the time of payment.

A valid permit from EHD is required prior to operating food facility (California Retail Food Code, Chapter 13, Article 1, Section 14381).

Any geotechnical drilling shall be conducted under permit and inspection by The Environmental Health Department (San Joaquin County Development Title, Section 9-1115.3 and 9-1115.6).

Destroy any abandoned well(s), septic tanks, or brick lined seepage pits under permit and inspection by the Environmental Health Department as required by San Joaquin County Development Title, Section 9-601.020(e).

ACKNLOWLEDGEMENT OF TERMS AND CONDITIONS

MUST BE CERTIFIED BY A NOTARY PUBLIC
The City reserves the right to withhold the finalization of the structure(s) and/or terminate City utilities (i.e., shut off water and sewer) until all conditions of the City-approved site plan have been completed. Please contact the Development Services Department if you are unable to complete the site plan improvements prior to occupancy of the project.

The fees associated with this project are payable at the time of building permit issuance. For information on fees associated with the project, please contact the Building Safety Division at 209-456-8550.

I, as the site plan applicant, or authorized agent for the site plan applicant, have read and understand the conditions of approval and requirements for this development project. I, further, understand that this site plan runs with the ownership of the land and any transfer of ownership must include all uncompleted site plan requirements. I hereby acknowledge all conditions and requirements of the site plan approval. __________________ _______________________________________________ Date Authorized Signature
__________________ _______________________________________________ Date Authorized Signature