Capital Improvement Plan - Government Building Facilities Facility Sqare Feet Cost per s.f. Total Cost Location Planned Timing Backup Documentation Civic Center - City Hall 71500 820 58630000 1001 W Center Street Fiscal Year 2028/29 for design, Phase I 2030, immediately following construction of the Police Station, Completion by 2035 2020 Space Needs Analysis done by LDA Partners Performing Arts Center 37000 721 26677000 Within the Family Entertainment Zone to be part of upcoming Master Plan Design to start by 2034, Completion by 2038 Conceptual design to be included as part of the updated FEZ Master Plan to occur in FY2025. Facility has been identified as a component of the FEZ in the Master Plan since 2016.
Library 55000 1195 65725000 320 W Center Street Design to start by 2034, Completion by 2038 Based on escalated costs from the 2006 analysis and recently constructed projects.
General Plan EF-4: Promote efforts to provide learning opportunities for all residents by working with San Joaquin County and stakeholders to provide modern library resources and programs.
City of Manteca Council Meeting on March 3, 2020 identifying the facilities needed to support growth.
Multi-Use Community Facility 32000 850 27200000 500-600 Moffat Blvd Design to start 2025/2026 or sooner, Completion by 2030 Direction from City based on conceptual plans Animal Shelter Expansion 8000 800 6400000 115 E Wetmore Avenue Design to start 2025/2026 or sooner, Completion by 2030 Direction from City based on the need to increase the existing Animal Shelter by more than 100% due to number of animals present onsite.
Police Station 45570 1232 56157791 Milo Candini & Wawona RFQ for Design in FY25, Design in 2025, Completion by 2030 2020 Space Needs Analysis done by LDA Partners and 2024 conceptual design and cost analysis completed by LDA Partners, approved by City Council on August 20, 2024.
Public Safety Training Facility (50%) 6000 600 3600000 Milo Candini & Wawona Design starting 2029 after completion of the Police Station, Completion by 2034 Direction from City based on conceptual plans Police Range 17500 530 9275000 Milo Candini & Wawona Design in 2030, after Police Station is completed, Completion by 2035 Based on escalated costs from the 2006 analysis and recently constructed projects.
Park and Public Works Corporation Yard 22800 236 5380800 2450 W Yosemite Avenue Design and construction starting 2032, or sooner, completion by 2034 CIP 17033 - Public Works Consolidation Project Additional Maintenance Facilities 45000 125 5625000 2450 W Yosemite Avenue Design and construction starting 2032, or sooner, completion by 2034 CIP 17033 - Public Works Consolidation Project Parks Satellite Corporation Yard 3000 585 1755000 South of Highway 120 Design and construction starting 2032, or sooner, completion by 2034 Based on escalated costs from the 2006 analysis and recently constructed projects.
Total 343370 266425591