ITEM
NO. ITEM DESCRIPTION BID
QTY UNIT UNIT PRICE TOTAL
1 Mobilization & Demobilization 1 LS $ 550,000.00 $ 550,000.00 2 Stormwater Pollution Prevention Plan 1 LS $ 10,000.00 $ 10,000.00 3 Sheeting, Shoring, and Bracing 1 LS $ 7,000.00 $ 7,000.00 4 Primary Effluent Pump Station Improvements 1 LS $ 2,600,000.00 $ 2,600,000.00 5 North Plant Interior Improvements 1 LS $ 2,000,000.00 $ 2,000,000.00 6 North Internal Recycle Pump Station Improvements 1 LS $ 1,050,000.00 $ 1,050,000.00 7 South Plant Improvements 1 LS $ 1,800,000.00 $ 1,800,000.00 8 South Internal Recycle Pump Station Improvements 1 LS $ 1,150,000.00 $ 1,150,000.00 9 Startup, Commissioning, and Strees Testing 1 LS $ 50,000.00 $ 50,000.00 10 O&M Manuals and Training 1 LS $ 20,000.00 $ 20,000.00 11 Record Drawings 1 LS $ 20,000.00 $ 20,000.00
12 Overhead GCs, Taxes, Bonding, Insurance 1 LS $ 2,200,000.00 $ 2,200,000.00 13 All Other Items Not Included in Bid Items 1-12 1 LS $ 18,000.00 $ 18,000.00 WQCF Capacity Improvements Project CIP Nos. 23002, 23003, 23004, & 23005 C. OVERAA & CO. Engineers Estimate $11,200,000
August 19, 2024
RICHMOND, CA
TOTAL BASE BID ITEMS 1 - 13: $ 11,475,000.00
ITEM
NO. ITEM DESCRIPTION BID
QTY UNIT UNIT PRICE TOTAL
1 Mobilization & Demobilization 1 LS $ 220,000.00 $ 220,000.00 2 Stormwater Pollution Prevention Plan 1 LS $ 34,000.00 $ 34,000.00 3 Sheeting, Shoring, and Bracing 1 LS $ 100,000.00 $ 100,000.00 4 Primary Effluent Pump Station Improvements 1 LS $ 2,900,000.00 $ 2,900,000.00 5 North Plant Interior Improvements 1 LS $ 3,200,000.00 $ 3,200,000.00 6 North Internal Recycle Pump Station Improvements 1 LS $ 1,250,000.00 $ 1,250,000.00 7 South Plant Improvements 1 LS $ 2,150,000.00 $ 2,150,000.00 8 South Internal Recycle Pump Station Improvements 1 LS $ 2,100,000.00 $ 2,100,000.00 9 Startup, Commissioning, and Strees Testing 1 LS $ 200,000.00 $ 200,000.00 10 O&M Manuals and Training 1 LS $ 50,000.00 $ 50,000.00 11 Record Drawings 1 LS $ 20,000.00 $ 20,000.00
12 Overhead GCs, Taxes, Bonding, Insurance 1 LS $ 700,000.00 $ 700,000.00 13 All Other Items Not Included in Bid Items 1-12 1 LS $ 50,000.00 $ 50,000.00 WQCF Capacity Improvements Project CIP Nos. 23002, 23003, 23004, & 23005 MOUNTAIN CASCADE INC. Engineers Estimate $11,200,000
August 19, 2024
LIVERMORE, CA
TOTAL BASE BID ITEMS 1 - 13: $ 12,974,000.00
ITEM
NO. ITEM DESCRIPTION BID
QTY UNIT UNIT PRICE TOTAL
1 Mobilization & Demobilization 1 LS $ 340,300.00 $ 340,300.00 2 Stormwater Pollution Prevention Plan 1 LS $ 20,000.00 $ 20,000.00 3 Sheeting, Shoring, and Bracing 1 LS $ 25,000.00 $ 25,000.00 4 Primary Effluent Pump Station Improvements 1 LS $ 2,696,000.00 $ 2,696,000.00 5 North Plant Interior Improvements 1 LS $ 3,110,000.00 $ 3,110,000.00 6 North Internal Recycle Pump Station Improvements 1 LS $ 1,100,000.00 $ 1,100,000.00 7 South Plant Improvements 1 LS $ 2,410,000.00 $ 2,410,000.00 8 South Internal Recycle Pump Station Improvements 1 LS $ 1,815,000.00 $ 1,815,000.00 9 Startup, Commissioning, and Strees Testing 1 LS $ 85,000.00 $ 85,000.00 10 O&M Manuals and Training 1 LS $ 50,000.00 $ 50,000.00 11 Record Drawings 1 LS $ 10,000.00 $ 10,000.00
12 Overhead GCs, Taxes, Bonding, Insurance 1 LS $ 1,750,000.00 $ 1,750,000.00 13 All Other Items Not Included in Bid Items 1-12 1 LS $ 50,000.00 $ 50,000.00 WQCF Capacity Improvements Project CIP Nos. 23002, 23003, 23004, & 23005
AUBURN CONSTRUCTORS,
LLC
Engineers Estimate $11,200,000
August 19, 2024
SACRAMENTO, CA
TOTAL BASE BID ITEMS 1 - 13: $ 13,461,300.00
ITEM
NO. ITEM DESCRIPTION BID
QTY UNIT UNIT PRICE TOTAL
1 Mobilization & Demobilization 1 LS $ 115,000.00 $ 115,000.00 2 Stormwater Pollution Prevention Plan 1 LS $ 40,000.00 $ 40,000.00 3 Sheeting, Shoring, and Bracing 1 LS $ 25,000.00 $ 25,000.00 4 Primary Effluent Pump Station Improvements 1 LS $ 3,153,000.00 $ 3,153,000.00 5 North Plant Interior Improvements 1 LS $ 3,117,000.00 $ 3,117,000.00 6 North Internal Recycle Pump Station Improvements 1 LS $ 1,300,000.00 $ 1,300,000.00 7 South Plant Improvements 1 LS $ 2,500,000.00 $ 2,500,000.00 8 South Internal Recycle Pump Station Improvements 1 LS $ 1,900,000.00 $ 1,900,000.00 9 Startup, Commissioning, and Strees Testing 1 LS $ 180,000.00 $ 180,000.00 10 O&M Manuals and Training 1 LS $ 15,000.00 $ 15,000.00 11 Record Drawings 1 LS $ 15,000.00 $ 15,000.00
12 Overhead GCs, Taxes, Bonding, Insurance 1 LS $ 2,074,000.00 $ 2,074,000.00 13 All Other Items Not Included in Bid Items 1-12 1 LS $ 5,000.00 $ 5,000.00 WQCF Capacity Improvements Project CIP Nos. 23002, 23003, 23004, & 23005
THOMPSON BUILDERS
CORPORATION
Engineers Estimate $11,200,000
August 19, 2024
NOVATO, CA
TOTAL BASE BID ITEMS 1 - 13: $ 14,439,000.00
ITEM
NO. ITEM DESCRIPTION BID
QTY UNIT UNIT PRICE TOTAL
1 Mobilization & Demobilization 1 LS $ 1,500,000.00 $ 1,500,000.00 2 Stormwater Pollution Prevention Plan 1 LS $ 85,000.00 $ 85,000.00 3 Sheeting, Shoring, and Bracing 1 LS $ 75,000.00 $ 75,000.00 4 Primary Effluent Pump Station Improvements 1 LS $ 2,800,000.00 $ 2,800,000.00 5 North Plant Interior Improvements 1 LS $ 4,778,500.00 $ 4,778,500.00 6 North Internal Recycle Pump Station Improvements 1 LS $ 1,300,000.00 $ 1,300,000.00 7 South Plant Improvements 1 LS $ 3,350,000.00 $ 3,350,000.00 8 South Internal Recycle Pump Station Improvements 1 LS $ 1,900,000.00 $ 1,900,000.00 9 Startup, Commissioning, and Strees Testing 1 LS $ 55,000.00 $ 55,000.00 10 O&M Manuals and Training 1 LS $ 20,000.00 $ 20,000.00 11 Record Drawings 1 LS $ 25,000.00 $ 25,000.00
12 Overhead GCs, Taxes, Bonding, Insurance 1 LS $ 750,000.00 $ 750,000.00 13 All Other Items Not Included in Bid Items 1-12 1 LS $ 10,000.00 $ 10,000.00
SUISUN CITY, CA
WQCF Capacity Improvements Project CIP Nos. 23002, 23003, 23004, & 23005
SHIMMICK CONSTRUCTION
COMPANY, INC.
Engineers Estimate $11,200,000
August 19, 2024
TOTAL BASE BID ITEMS 1 - 13: $ 16,648,500.00