03/31/2025
ATTACHMENT 3
United Pavement Maintenance LIC. NO. 905503
P.O. Box 1017 DIR# 1000878534
Hughson, CA
Phone: 209-883-4345
TO: Kyzen Nicolas DATE: 2/10/2025
City of Manteca UPDATE:
209-456-8418 REV: 0
[email protected]
PROJECT: Main Street Bike & Pedestrian Improvement Project - Manteca JOB NO.: 24-84 RE: UPM CHANGE ORDER # 01.1
CCO# TBD
UNIT TOTAL
ITEM DESCRIPTION QTY UNIT PRICE AMOUNT
2" Grind & Overlay (approx. 364,562 SF) $ 732,735.00
Equipment 1 LS $ 56,225.00 $ 56,225.00
Material 1 LS $ 399,980.00 $ 399,980.00
Labor 1 LS $ 78,850.00 $ 78,850.00
Trucking 1 LS $ 169,680.00 $ 169,680.00
Sweeping 10 DAY $ 2,800.00 $ 28,000.00
Additional 2" Digouts (approx. 37,143 SF) $ 106,305.00
Equipment 1 LS $ 12,545.00 $ 12,545.00
Material 1 LS $ 42,000.00 $ 42,000.00
Labor 1 LS $ 22,640.00 $ 22,640.00
Trucking 1 LS $ 23,520.00 $ 23,520.00
Sweeping 2 DAY $ 2,800.00 $ 5,600.00
49 Adjust Water Valve Cover to Grade 36 EA $ 1,500.00 $ 54,000.00 50 Adjust Sanitary Sewer Manhole Cover to Grade 33 EA $ 2,000.00 $ 66,000.00 Adjust Telecom Cover to Grade 2 EA $ 2,800.00 $ 5,600.00 Traffic Control/Flagging 12 DAY $ 3,875.00 $ 46,500.00
Additional Mobilization 1 LS $ 13,440.00 $ 13,440.00
18 Cold Plane Asphalt Pavement (0.2' Depth) -1730 SY $ 20.70 $ (35,811.00) 31 Slurry Seal (Type II) -355 TON $ 378.00 $ (134,190.00) 15% $ 135,687.00
1.5% $ 13,568.70
$ 1,003,834.70
12 (WORKING DAYS)
CONDITIONS/SCOPE:
SIGNED:
UPM
DATE: 2/10/2025 DATE:
CHANGE ORDER REQUEST
OWNER / CONTRACTOR
TOTAL CHANGE ORDER REQUEST
CONTRACT TIME EXTENSION REQUEST
Option 1 -
2" Grind & Overlay;
Additional 2" Digouts;
Delete Slurry Seal
PROJECT OH&P
PROJECT BOND
Scott Yerzy
2" Grind & 2" HMA Overlay for entire project limits
Additional 2" Digouts at locations provided by TRC
Delete Slurry Seal - Waiting for response from APS about deletion of scope; Profit Loss cost may apply.
EXCLUSIONS:
Paving Fabric: Add $96,244 to cost if Paving Fabric is to be included; Additional $5,500 if placed in intersections.
Material testing, compaction testing & fees.
Additional OH&P and Bond Cost not included for Bid Line Item adjustments SIGNED:
Traffic Signal Loop replacement
Owner/Contractor * Project Management * Accounting * File POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 1 OF 11
POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 2 OF 11
POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 3 OF 11
POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 4 OF 11
POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 5 OF 11
POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 6 OF 11
POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 7 OF 11
POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 8 OF 11
POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 9 OF 11
United Pavement Maintenance LIC. NO. 905503
P.O. Box 1017 DIR# 1000878534
Hughson, CA
Phone: 209-883-4345
TO: Kyzen Nicolas DATE: 3/7/2025
City of Manteca UPDATE:
209-456-8418 REV: 0
[email protected]
PROJECT: Main Street Bike & Pedestrian Improvement Project - Manteca JOB NO.: 24-84 RE: UPM CHANGE ORDER # 004
CCO# TBD
UNIT TOTAL
ITEM DESCRIPTION QTY UNIT PRICE AMOUNT
Furnish & Install 4 Camera Video Detection
System at Main St & Northgate 1 LS $ 58,600.00 $ 58,600.00 5% $ 2,930.00
1.5% $ 922.95
$ 62,452.95
2 (WORKING DAYS)
CONDITIONS/SCOPE:
SIGNED: SIGNED:
UPM
DATE: 3/7/2025 DATE:
OWNER / CONTRACTOR
CHANGE ORDER REQUEST
Video Detection in lieu of Traffic Loops - Northgate
TOTAL CHANGE ORDER REQUEST
CONTRACT TIME EXTENSION REQUEST
PROJECT OH&P
PROJECT BOND
Scott Yerzy
- Cameras to be installed while performing similar work at other intersections. No additional mobilization included. - Price includes turn on support.
Owner/Contractor * Project Management * Accounting * File POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 10 OF 11
POTENTIAL CHANGE ORDER (PCO) ATTACHMENT 3
NO. 1 PAGE 11 OF 11