Cities Index.
Attachment 5 - Contract Change Order No.1

Manteca City Council
April 7, 2026

Document
Attachment 5 - Contract Change Order No.1
Meeting
April 7, 2026
Body
Manteca City Council
Pages
2
Original file
314 KB
Text extracted from the city's file for reading and search. Open the original on manteca-ca.legistar1.com. That file is the official record.
Page 1 of 2 ends

City of Manteca Change Order Change Order No. ___
Project Name: Approval Date:

Project Manager:

CIP No.

Contract No: Project
Contractor:

It is agreed to modify the Contract referred to above as follows:

CPR DESCRIPTION OF CHANGES CHANGE IN

CONTRACT PRICE

CHANGE IN

CONTRACT TIME
ATTACHMENT - 05

Page 2 of 2 ends

It is agreed to modify the Contract referred to above as follows:
a. Contract Amount + Approved Change Orders:
b. Net Increase (Decrease) of this Change Order:
c. Revised Contract Amount + all Change Orders: (a +b = c) d. Contract Time (Final Completion) Prior to this Change Order (Calendar Days):
e. Net Increase (Decrease) of this Change Order:
f. Revised Contract Time with all Approved Changes (Calendar Days): (d + e = f) Change order to be accomplished in accordance with the terms, stipulations, and conditions of the original contract. ___________________________________ ______________________________ Approved by Contractor: Date ___________________________________ ______________________________ Recommended for Approval: Date ___________________________________ ______________________________ Recommended for Approval: Date City Project Manager ___________________________________ ______________________________ Approved by: Date City Representative ___________________________________ ______________________________ Attest: City Clerk Date

TRANSPORTATION

CHANGE ORDER MEMORANDUM
CEM-4903 (REV 06/2016)

Page 1 ends

DATE
Yosemite Ave Bike and Pedestrian Improvement Project FILE CONTRACT NO. PENDING

CO-RTE-PM
FED NO. HSIPL 5242(036)
CHANGE ORDER NO.
01 SUPPLEMENT NO. 0 CATEGORY CODE
17058

CHANGE ORDER AMOUNT

INCREASE DECREASE
$585,479.62

SUPPLEMENTAL FUNDS PROVIDED
$0

ORIGINAL CONTRACT
TIME:
90 DAY(S)

TIME ADJUSTMENT
THIS CHANGE:
7 DAY(S)

PREVIOUSLY APPROVED
TIME ADJUSTMENTS:
0 DAY(S)

PERCENTAGE TIME ADJUSTED
(Including this change)
0 %
TOTAL # OF UNRECONCILED

DEFERRED TIME
(Including this change)
0 THIS CHANGE ORDER PROVIDES FOR (Use additional pages as needed):

This change order provides for:

Claim No. 01: grind and overlay, including fabric on Yosemite Ave from Walnut St to Willow St. Due to the existing pavement condition and the functional classification of the roadway as an arterial, the originally proposed slurry seal treatment is no longer considered appropriate. Field observations indicate moderate pavement distress, including cracking and surface deterioration, which cannot be effectively addressed with a slurry seal, as it is primarily a preventive maintenance treatment. A 3-inch grind and asphalt concrete overlay with pavement fabric is recommended to remove the distressed asphalt layer, improve ride quality, and restore structural capacity. The installation of pavement fabric will also help mitigate reflective cracking from the underlying pavement, extending the service life of the new overlay and providing a more durable long-term rehabilitation for the arterial roadway.

An additional 7 working days were added to the contract due to the additional scope of work requested.

Slurry Credit was provided by the contractor.

Reason for Change:

In accordance with Article 10.01 Authorized Changes in Work of the Standard General Conditions of the Construction, this change order compensates the contractor with a Payment Adjustment at Agreed Lump Sum of $585,479.62 for the claims listed above.

Method of Payment:

The agreed lump sum payment adjustment is based on a force account analysis. Records and calculations used to determine the payment adjustment are on file in the project records.

This change was discussed with the construction engineer and City Engineer. They agree that the contractor should receive the additional compensation.

Time Adjustment:

This change order affected the controlling activities and time adjustment is warranted.

TRANSPORTATION

CHANGE ORDER MEMORANDUM
CEM-4903 (REV 06/2016)

Page 2 ends

CONCURRED BY:

CONSTRUCTION ENGINEER/BRIDGE ENGINEER DATE

ESTIMATE OF COST

THIS REQUEST TOTAL TO DATE

PROJECT ENGINEER DATE

PROJECT MANAGER DATE
ITEMS

FORCE ACCOUNT

AGREED PRICE

ADJUSTMENT
TOTAL
$585,479.62
FHWA REP. DATE FEDERAL PARTICIPATION

PARTICIPATING PARTICIPATING IN PART NONE

ENVIRONMENTAL DATE
NON-PARTICIPATING (Maintenance) NON-PARTICIPATING
MAINTENANCE DATE FEDERAL SEGREGATION (If more than one funding source or P.I.P. type)

CHANGE ORDER FUNDED PER CONTRACT CHANGE ORDER FUNDED AS FOLLOWS

OTHER (SPECIFY) DATE

FEDERAL FUNDING SOURCE PERCENT

HQ OR DISTRICT PRIOR APPROVAL BY DATE

RESIDENT ENGINEER SIGNATURE DATE
$585,479.62
$585,479.62
$1,406,461.32

← All documents from this meeting