AMENDMENT MODIFICATION SUMMARY - (E-76)
FEDERAL AID PROGRAM CALIFORNIA DEPARTMENT OF TRANSPORTATIONDLA LOCATOR: 10-SJ-0-MTCA PROJECT LOCATION:PREFIX: HSIPL YOSEMITE AVENUE FROM WALNUT AVENUE TO MAIN STREETPROJECT NO: 5242(036) TYPE OF WORK:SEQ NO: 6 INSTALL CLASS II BIKE LANES, A TWO WAY LEFT TURN LANE, PREV AUTH / AGREE DATES:STATE PROJ NO: 1019000190L-N FED RR NO'S: PE:AGENCY: MANTECA PUC CODES: R/W:

ROUTE:

PROJ OVERSIGHT:ASSUMED/LOCAL ADMIN CON:

DISASTER NO:

ENV STATUS / EIS 05/07/2025 SPR:

TIP DATA
RW STATUS / DT: 1 06/19/2025 MCS:

MPO: SJCOG
INV RTE: OTH:

FSTIP YR: 24/25
BEG MP:

STIP REF: 212-0000-0403
END MP:

FSTIP ID SJ07-3116
BRIDGE NO:

PROG CODE LINE NO IMPV TYPE FUNC SYS URBAN AREA URB/RURAL DEMO IDYS70 30 21YS70 31 17ZS30 10 15FUNDING SUMMARY

PHASE PROJECT COST FEDERAL COST AC COST PE
PE PREV. OBLIGATION $111,000.00 $99,900.00 $0.00PE THIS $0.00 $0.00 $0.00PE SUBTOTAL $111,000.00 $99,900.00 $0.00 R/W
RW PREV. OBLIGATION $0.00 $0.00 $0.00RW THIS REQUEST $0.00 $0.00 $0.00RW SUBTOTAL $0.00 $0.00 $0.00 CON
CON PREV. OBLIGATION $646,100.00 $581,490.00 $0.00
CON THIS REQUEST $342,028.90 $307,826.00 $0.00
CON SUBTOTAL $988,128.90 $889,316.00 $0.00
OTH
OTH PREV. OBLIGATION $0.00 $0.00 $0.00OTH THIS REQUEST $0.00 $0.00 $0.00OTH SUBTOTAL $0.00 $0.00 $0.00 TOTAL: $1,099,128.90 $989,216.00 $0.00
PROJECT END DATE (PED): 06/30/2027
ALT. PROJ NO:

STATE REMARKS
07/17/2019 * SEQ 1: Initial Authorization of federal funds for PE. 1 ) Project End Date (PED) established as 12-31-2021 effective SEQ 1 approval. 07/17/2019 2 ) PE Funding was advanced from FFY 21/22 to FFY 19/20 via EPSP request. 3 ) Final design is not to start until the environmental document (NEPA) is approved.4 ) Maximum available Federal Funds = $681,390 (HSIP Project). 12/20/2021 * SEQ 2: Extend Project End Date (PED) to 06/30/2024. No previous PED lapse or change in funding. * Effective SEQ 2 approval, the PED is extended from 12/31/21 to 06/30/2024 due to COVID - 19 causing a delay in conducting procurement and awarding a contract for Preliminary Engineering Services tocomplete the design as well as preparing for Authorization for Construction. 07/18/2024 Sequence #3 is a request to further extend the project end date (PED) from 6/30/24 to 12/31/25. The project has been delayed by a project scope change, staff turnover, and a prolonged consultant selection process. Due to a lapse in the PED, any expenditures incurred from 7/01/24 to the date of FHWA approval of this sequence are ineligible for federal reimbursement. 08/19/2024 Sequence #3 is a request to further extend the project end date (PED) from 6/30/24 to 12/31/25. The project has been delayed by a project scope change, staff turnover, and a prolonged consultant selection process. Due to a lapse in the PED, any expenditures incurred from 7/01/24 to the date of FHWA approval of this sequence are ineligible for federal reimbursement. 06/27/2025 SEQ 4: Initial authorization of Con/CE phase in the amount of $578,184.29 utilizing State fund State Advance Construction and $3,305.71 of YS70 to CE. PED is 06/30/2027.

ATTACHMENT - 08
11/10/2025 Convert the AC (CON and CE) funds to federal funds (CON $541,890+ CE $36,294.29) 11/18/2025 SEQ 5: Converting $578,184.29 of AC to a regular obligation of Federal YS70 for CON/CE01/30/2026 SEQ 6: Obligation of additional YS70 funds for CON. Additional funding for this post programming increase approved by the DLA Safety Program.

FEDERAL REMARKSAUTHORIZATION
AUTHORIZATION TO PROCEED WITH REQUEST:CON PREPARED IN FADS BY: HASAN, NABIL ON 2026-01-25 948-7786 FOR: CON-COST ADJ REVIEWED IN FADS BY: WULFF, DARLENE ON 2026-02-04 741-5450 DOCUMENT TYPE: AMOD SUBMITTED IN FADS BY: WULFF, DARLENE ON 2026-02-04 FOR CALTRANS PROCESSED IN FADS BY: SIGNATURE, NOT_REQUIRED ON 2026-02-04 FOR FHWA E-76 AUTHORIZED DATE IN FMIS JIYOUNG AHN ON 2026-02-10 19:43:37.0 SIGNATURE HISTORY FOR PROJECT NUMBER 5242(036) AS OF 02/11/2026

FHWA FMIS SIGNATURE HISTORY
MOD # SIGNED BY SIGNED ON5 WAII HAYS 02/10/2026
WAII HAYS 02/10/2026JIYOUNG AHN 02/10/2026
4 WAII HAYS 11/25/2025
WAII HAYS 11/25/2025JIYOUNG AHN 11/25/2025
3 WAII HAYS 07/02/2025
WAII HAYS 07/02/2025JIYOUNG AHN 07/03/2025
2 WAII HAYS 09/16/2024
WAII HAYS 09/16/2024GRACE REGIDOR 09/18/2024
1 SHUN HUEY 12/28/2021
SHUN HUEY 12/28/2021GRACE REGIDOR 12/29/2021
0 SHUN HUEY 10/31/2019
SHUN HUEY 10/31/2019JESSICA GORDON 10/31/2019