PLATEE ATTACHMENT 4
E MAntACA
FINAL PAYMENT CERTIFICATION
Date: May 20, 2026
PROJECT: Shasta Park Area Pavement Improvement Project CIP 25022 AMOUNT OF ORIGINAL BID: $1,083,421.70
AMOUNT OF Change Order/Field Changes(s): $1,093,002.69
AMOUNT DUE AFTER VERIFICATION OF
FIELD MEASUREMENTS: *$2,176,424.39
LESS ANY CITY WITHHOLDINGS: $0.00
FINAL COST OF PROJECT: $2,176,424.39
LESS 5% RETENTION: $108,821.22
(To be paid not less than 45 days after recording Notice of Completion at County Recorder's Office)
PAYMENTS MADE TO DATE: $2,067,603.17
OTHER PAYMENTS MADE AFTER June 16, 2026: $108,821.22
* No withholdings
Anna aari Date: 5/20/26
Contractor's Approval
5/20/26
Date:
Project Engineer's Approval: Toshiro Sessoms/
Donna Zapico