Cities Index.
Attachment 4 - Change Order No 2

Manteca City Council
August 18, 2026

Document
Attachment 4 - Change Order No 2
Meeting
August 18, 2026
Body
Manteca City Council
Pages
2
Original file
518 KB
Text extracted from the city's file for reading and search. Open the original on manteca-ca.legistar1.com. That file is the official record.

City of Manteca Change Order Change Order No. 02
Project Name: Fleet Maintenance Facility CNG Safety
Approval Date:

Systems Upgrades
Project Manager:

Avneet Mahil
CIP No. 24121
-Project
Contractor: Anaba Construction
Contract No: C2025-196
It is agreed to modify the Contract referred to above as follows:

CPR DESCRIPTION OF CHANGES CHANGE IN

CHANGE IN

CONTRACT PRICE CONTRACT TIME
PCO-5.1 Additional Fire Inspection Site Visits $3,380.00 0 days

Page 1 of 2 ends

It is agreed to modify the Contract referred to above as follows:
a. Contract Amount + Approved Change Orders:
$204,443.35
b. Net Increase (Decrease) of this Change Order:
$ 3,380.00
c. Revised Contract Amount + all Change Orders: (a +b = c) $207,823.35
d. Contract Time (Final Completion) Prior to this Change Order (Calendar Days): 187 days
e. Net Increase (Decrease) of this Change Order:

O days
f. Revised Contract Time with all Approved Changes
(Calendar Days): (d + e = f) 187 days
Change order to be accomplished in accordance with the terms, stipulations, and conditions of the original contract.

Shah Noor Broomand 07/13/2026
Approved by Contractor: Date
Mitellulu
07/13/2026
Recommended for Approval: Date
aMahil 7/13/24
Recommended for Approval: Date
City Project Manager
1/14|2026
Date
City Representative

CAN OF MANTEC

NCORPORATED

7.14.26 Attest City Clerk Date

Page 2 of 2 ends

ANABA Construction, Inc
CSLB License #: 1084589- A - General Engineering & C-21 Building Moving & Demolition WBE & SBE Certification ID 2039242; DIR#2000001415 ANABA Construction, Unc
CSLE LEO 16233-A. Canal Eageaping & C. 21 Baiding Mading CHANGE ORDER #5.1
Project: Fleet Maintenance Facility CNG Safety System Upgrades Owner: City of Manteca | Public Works Department
Contractor: ANABA Construction, Inc.

Date: July 3, 2026
Reference: Original Agreement and Drawings

DESCRIPTION OF CHANGE
This Change Order is issued to modify the Scope of Work to include additional fire inspection site visits.

Justification: Returned to the project site for a second and third fire inspection to verify that the fire alarm installation and all associated equipment were installed correctly and fully functional. Additional site visits were required for inspection coordination and attendance. No deficiencies were found with our work or equipment.

Per EMCOR Mesa Energy Systems Inc. Service Reports, the following work was performed:

Date Description
6/24/2026 Second fire inspection - Verified functional installation, no deficiencies found 7/1/2026 Third fire inspection - Verified functional installation, no deficiencies found

COST BREAKDOWN
Labor
Description Labor Total
Qty Unit
Rate Cost
anabaconsutruction.com (510) 826-9443/ [email protected] DUNS Number 119092482, CAGE Code 9LF29
ANABA Construction, Inc
CE sense caton 10 2039242, DIR#2000141C-21 Bulting Moving & Demolition ANABA Constriction, Unc
58L8 Mone 2842-2. Cane Enginest 2 eating Master,
Description Labor Total
Qty Unit
Rate Cost
Foreman Time - Fire Inspection & Travel
8 Hours $160.00 $1,280.00
(6/24/2026)
Foreman Time - Fire Inspection & Travel
(7/1/2026) 8 Hours $160.00 $1,280.00
Technician Time - Reset system after Fire
Alarm connections (6/24/2026) 8 Hours $110.00 $880.00
Labor Total:
$3,440.00
Materials & Equipment
Description Qty Unit Cost Total Cost
Smoke detector test spray (6/24/2026) 1 $24.74 $24.74
Smoke detector test spray (7/1/2026) 1 $24.74 $24.74
Vehicle (1.5% of field electrician & technician labor) - - $117.74 Field Tooling (1.5% of field electrician labor) - - $24.74 Materials & Equipment Subtotal: $191.96
Material Sales Tax (8.500%): $18.18
Materials & Equipment Total (with tax): $210.14
Direct Costs Subtotal
Description Amount
Labor Total $3,440.00
anabaconsutruction.com (510) 826-9443 / [email protected] DUNS Number 119092482, CAGE Code 9LF29
ANABA Construction, Inc
CEL Lo e 285lD 20022, 0IER200041C 21 Bulaing Moving & Demolition ANABA Construction, Inc
Description
Amount
Materials & Equipment Total (with tax) $210.14
Direct Costs Subtotal:
$3,650.14
MARKUP
Description Percentage
Amount
General Conditions / Overhead & Profit 15% $547.52
Subtotal (Direct Costs + 15% Markup): $4,197.66
Bonding Fee 1.5% $62.96
TOTAL CHANGE ORDER COST (before credit): $4,260.62

CREDIT TO OWNER
Description
Amount
Less: Credit to Owner (adjustment for cost efficiencies / negotiated reduction) -$880.62
NET CHANGE ORDER COST (after credit): $3,380.00

IMPACT ON CONTRACT PRICE AND SCHEDULE
anabaconsutruction.com (510) 826-9443/ [email protected] DUNS Number 119092482, CAGE Code 9LF29
ANABA Construction, Inc
COSE SEe can I 209242, DIR#2000011 C-21 Building Moving & Demolition ANABA Construction, Inc
Contract Price Summary
Item
Amount
Original Contract Price
$173,211.00
Net Change by Previous Modifications +$2,366.86
Change Order #3.1
+$14,765.71
Change Order #4.1 +$14,099.78
Change Order #5.1 (gross amount) + $4,260.62
Less: Credit to the Owner -$880.62
Net Change Order #5.1 +$3,380.00
Revised Contract Price $207,823.35
Schedule Impact
This change order is for additional inspection visits and does not require any additional construction work. No schedule impact is anticipated.

AUTHORIZATION
The undersigned agree that the above-described change in the Work, the adjustment to the Contract Price, and the impact on the Contract Time are approved. This Change Order shall be incorporated into and become a part of the original Agreement.

ACCEPTED FOR THE OWNER:

Bly of Mantee Lubic Works Department
Anne 1i4 EHS - Depuy Director of Public Works
anabaconstruction.com (510) 826-9443 / [email protected] DUNS Number 119092482, CAGE Code 9LF29
ANABA Construction, Inc
CSLB License #: 1084560 - A - General Engineering & C-21 Building Moving & Demolition WBE & SBE Certification ID 2039242; DIR#2000001415
ANABA Construction, Inc
ACCEPTED FOR THE CONTRACTOR: C3L8 Loney 1081225 -1-Comal oning 3 Cal Balding Meing ANABA Construction, Inc.

By:

Shah N. Broomand, PMP, President
Date:
anabaconsutruction.com (510) 826-9443 / [email protected] DUNS Number 119092482, CAGE Code 9LF29

← All documents from this meeting