Item #09
Date: June 2, 2026
To: Mayor and City Council
From: Jeramy Chapdelaine, Public Works Director
Subject: Approval of SB 1 Road Maintenance and Rehabilitation Project List for 2026-2027 Recommendation:
Pass a Motion to approve the Road Maintenance and Rehabilitation Act (RMRA) proposed project list for Fiscal Year 2026-2027 to be submitted to the California Transportation Commission (CTC).
Rationale for Recommendation:
SB 1 emphasizes the importance of accountability and transparency in the delivery of California's transportation programs. Therefore, in order to be eligible for RMRA funding, statute requires cities and counties to provide basic annual RMRA project reporting to the CTC. Prior to receiving an apportionment of RMRA funds from the State Controller in a fiscal year, the City must submit to the CTC a list of projects proposed to be funded with these funds.
Background:
On April 28, 2017, Governor Edmund G. “Jerry” Brown signed the Road Repair and Accountability Act of 2017, known as Senate Bill 1 (SB1), increasing per gallon fuel excise taxes, diesel fuel sales taxes, and vehicle registration fees with future inflationary adjustments for the purpose of addressing road maintenance, rehabilitation, and roadway safety needs. The State Controller will deposit portions of the new funding into the Road Maintenance and Rehabilitation Account (RMRA), which will be apportioned by formula to eligible cities and counties throughout the year. Funds were apportioned to cities and counties beginning in January 2018.
The City has completed and programed several street projects utilizing the findings made from the Pavement Management Program presented to City Council on April 17, 2018. At that meeting, the City Council directed staff to pursue a maintenance approach that prioritizes the maintenance of streets over the past maintenance and rehabilitation projects to try improving the Pavement Condition Index of the street system as cost effective as possible. This approach focuses on the maintenance of streets in better condition over reconstruction of the failing streets with preventative measures such as micro grinds overlays, rubberized slurry seal and crack sealing.
On April 16, 2019, City Council approved a list of 2019 projects based on the criteria and authorized the Community Services Department to plans and specifications for the 2019 Resurfacing Project. In September 2019 the first phase of the project was bid out and the work was completed, seal coating of E. 17th Street east of Ramirez Street, but Council decided to truncate the contract to just that segment to reevaluate the scope of the improvements and project list. The revised project list was developed and adopted by the City Council in April 2020. The project was put on hold to wait for the construction of the ATP funded Bike & Pedestrian Improvements Project that was completed in 2021.
The next phase of the SB 1 funded surfacing project was the 2021 SB 1 Pavement Project that paved B Street between 1st and 3rd Streets, 1st Street between B and E Streets, and F Street between 3rd and 6th Streets.
This was completed in late 2021.
Discussion & Analysis:
The City is required to submit a proposed project list to the CTC by July 1, 2026 in order to receive RMRA funds for Fiscal Year 2026-2027; once submitted, the City will continue to receive apportionments, averaging about $25,000 a month.
A current project list has been developed utilizing the previously approved projects lists that were based on findings made from the Pavement Management Program on April 17, 2018, City Council input, and projects already completed.
Note that this is a running list. The funds appropriated to the City of Marysville is typically “saved up” until there is enough to conduct a project. These projects could be funded with other funds but SB 1 funds cannot be spent on a project unless that project has been on a list adopted by City Council and submitted to the CTC by July 1 of each year. The list can be amended throughout the year.
Adding the CDBG Phase 3 project streets to the FY 26-27 Approved List:
16. Added - I St bet Featherside Way - North end - Resurfacing
17. Added - G St bet 10th St – 14th St - Resurfacing
18. Added - F St bet 10th St – 14th St - Resurfacing
19. Added - E St bet 10th St – 14th St - Resurfacing
20. Added – 11th St bet J St – Lake - Resurfacing
21. Added – 12th St bet H St – Lake - Resurfacing
22. Added – 13th St bet J St – Lake – Resurfacing
23. Added - D St bet 10th St – 14th St – Resurfacing
24. Added – Oak St (Officer Osmar Rodarte Memorial Way) 5 th St – 6th St – Resurfacing
Therefore, once approved by City Council the following table would represent the list of streets eligible for SB 1 funding in Fiscal Year 2025/26:
Project Title Project Description Project Location
Estimated
Useful
Life
(Years)
Originally
Listed
Project
Timeline
1 SB 1 - H St bet 3rd St
and 14th St
Resurfacing
Make minor pavement repairs to the
existing pavement section, micro grind
and overlay paved surface, and install
new pavement delineation.
H St. - 3
rd St. to 14th
St.
20-30 2019 June 2026 –
June 2027
10th to 14th
2 SB 1 - D St bet 1st St to
3rd St
Resurfacing
Make minor pavement repairs to the
existing pavement section, micro grind
and overlay paved surface, and install
new pavement delineation.
D St. – 1
st St. to
3rd St.
20-30 2019 September
2027 – June
2028
3 SB 1 - Yuba St bet 6th St
and 10th St
Resurfacing
Make minor pavement repairs to the
existing pavement section, micro grind
and overlay paved surface, and install
new pavement delineation.
Yuba St. – 6
th St. to
10th St.
20-30 2020 September
2027 – June
2028
4 SB 1 - Yuba St bet E.
12th St and E. 17th St
Resurfacing
Make minor pavement repairs to the
existing pavement section, micro grind
and overlay paved surface, and install
new pavement delineation.
Yuba St. – E. 12th
St. to E. 17th St.
20-30 2020 September
2027 – June
2028
5 SB 1 - Ramirez St bet E.
12th St and E. 24th St
Resurfacing
Make minor pavement repairs to the
existing pavement section, micro grind
and overlay paved surface, and install
new pavement delineation.
Ramirez St. – E.
12th St. to E. 24th
St.
20-30 2020 June 2028 –
June 2029
6 SB 1 - E. 17th St bet
Chestnut St and Ramirez
St
Reconstruction
Remove or pulverize pavement section,
regrade and compact, install new
pavement section, and install new
pavement delineation.
E. 17th St. –
Chestnut St. to
Ramirez St.
20-30 2019 June 2028 –
June 2029
7 SB 1 - E. 22nd St bet
Ramirez St to Cheim
Blvd
Reconstruction
Remove or pulverize pavement section,
regrade and compact, install new
pavement section, and install new
pavement delineation.
E. 22nd St. –
Ramirez St. to
Cheim Blvd.
20-30 2020 June 2027 –
June 2028
8 SB 1 - Huston St bet E.
17th St and E. levee
Reconstruction
Remove or pulverize pavement section,
regrade and compact, install new
pavement section, and install new
pavement delineation.
Huston St. – E. 17th
St. to levee
20-30 2022 June 2026 –
June 2027
9 SB 1 - 5th St bet A
St/RR tracks and D St
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
5 th St. – A St./RR
Tracks to D St.
20-30 2025 June 2026 –
June 2027
10 SB 1 - 4th St bet A St
and F St
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
4 th St. – A St. to F
St.
20-30 2025 June 2026 –
June 2027
11 SB 1 - C St bet 5th St
and 6th St
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
C St. – 5
th St. to 6th
St.
20-30 2025 June 2026 –
June 2027
12 SB 1 - 3rd St bet A St
and E St
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
3rd St. – A St. to E
St.
20-30 2025 September
2027 – June
2028
13 SB 1 - 6th St bet B St
and C St
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
6 th St. – B St. to C
St.
20-30 2025 June 2026 –
June 2027
14 SB 1 – Hall St bet 17th
St and Johnson Ave
Seal Coating
Make minor pavement repairs to the
existing pavement section, cape seal the
pavement surface, and install new
pavement delineation.
Hall St bet 17th St
and Johnson Ave
20-30 2025 September
2027 – June
2028
15 SB 1 - Swezy St bet 17th
St and 19th St
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
Swezy St bet 17th
St and 19th St
20-30 2025 September
2027 – June
2028
16 SB 1 - I St bet
Featherside Way - North
end –
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
I St bet Featherside
Way - North end
20-30 2026 June 2026 –
June 2027
17 SB 1 - G St bet 10th St –
14th St –
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
G St bet 10th St –
14th St
20-30 2026 June 2026 –
June 2027
18 SB 1 - F St bet 10th St –
14th St –
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
F St bet 10th St –
14th St
20-30 2026 June 2026 –
June 2027
19 SB 1 - E St bet 10th St –
14th St –
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
E St bet 10th St –
14th St
20-30 2026 June 2026 –
June 2027
20 SB 1 – 11th St bet J St –
Lake –
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
11th St bet J St –
Lake
20-30 2026 June 2026 –
June 2027
21 SB 1 – 12th St bet H St –
Lake –
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
12th St bet H St –
Lake
20-30 2026 June 2026 –
June 2027
22 SB 1 – 13th St bet I St –
Lake –
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
13th St bet I St –
Lake
20-30 2026 June 2026 –
June 2027
23 SB 1 - D St bet 10th St –
14th St –
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
D St bet 10th St –
14th St
20-30 2026 June 2026 –
June 2027
24 SB 1 - Oak St (Rodarte
Way) bet 5th St and
6th St
Resurfacing
Micro grind surface, make pavement
repairs to the existing pavement section,
leveling course, pavement fabric, and
overlay paved surface, and install new
pavement delineation.
Oak St (Rodarte
Way) bet 5th St and
6th S
20-30 2026 June 2026 –
June 2027
Alignment with City Council Goal(s):
Goal #3: Improve Infrastructure
Environmental Impact:
This Resolution is exempt from the California Environmental Quality Act (Pub. Resources Code section 21000 et seq., "CEQA") pursuant to Public Resources Code section 21065 and CEQA Guidelines section 15061(b)(3) because there is no possibility that the activity in question may have a significant effect on the environment.
Legal Review:
This Agenda Item does not require legal review.
Fiscal Impact:
The City anticipates a total of $323,844 in tax proceeds for FY 2025-26 and is projected to receive $359,152 in Fiscal Year 2026-27.
Attachment(s):
1) Resolution 2026-XX
2) SB 1 Project Map