RECOMMENDED ACTION
1. Receive an update and ratify contract Change Order Nos. 1 through 8 with Riverside Construction Company, Inc., for construction services on the Holland Road/I-215 Overcrossing, in the amount of $108,012.25 pursuant to Menifee Municipal Code §3.12.090; and
2. Approve and authorize the City Manager to execute Contract Change Order No. 9 with Riverside Construction Company, Inc. for construction services on the Holland Road/I-215 Overcrossing, in the amount of $35,000, increasing the contract value to a total amount not- to-exceed $25,991,416.10.
DISCUSSION
The Holland Road / I-215 Overcrossing, Capital Improvement Program (CIP) Project No. 13-03 (“Project”) is the construction of a four-lane bridge and road over the Interstate 215 from Haun Road to Hanover Lane connecting the City’s east and west sides. The Project improvements also include construction of Mechanically Stabilized Earth (MSE) retaining walls on the east side, drainage, irrigation, and landscaping improvements, and installation of two traffic signals at Haun Road and Hanover Lane.
On October 19, 2022, the City Council approved a construction budget of $27,647,109 and awarded the construction services contract to Riverside Construction Company, Inc. (“Contractor”) in the amount of $25,848,403.85. Construction work for the Project began in January 2023 and is ongoing.
Although staff makes every effort to carefully study and anticipate the extent of the scope of work required to achieve project goals, unforeseen needs are often encountered as a project progresses. Unknown site conditions, utility conflicts discovered during construction activities,
City of Menifee Staff Report
CIP 13-03 Contract Change Orders
April 17, 2024
2 1
4 1
design clarifications, and additional expenses to comply with contract documents can result in additional work outside of the original scope and contract amount.
Pursuant to Menifee Municipal Code §3.12.090, change orders in an amount greater than 10% of the contract amount or that exceed $25,000 must be approved by the City Council. In keeping with the provisions of the Menifee Municipal Code, Contract Change Order (CCO) No. 2 and CCO No. 9. associated with the Project require ratification / approval by the City Council.
CCO No. 2 provided for time and materials-based work, monitored by inspectors throughout the duration of the project including additional traffic control measures and other work required to address unknown underground utility conflicts and unanticipated safety elements identified during the course of construction.
CCO No. 9 is the result of an administrative compliance requirement which establishes a project Dispute Board Resolution (DRB) in accordance with the 2018 Caltrans Standard Specifications 5-1.43E. The DRB is required for projects within Caltrans right-of-way and is utilized for the timely resolution of disputes that arise out of the Project work and is necessary to pursue a claim, file for arbitration, or file for litigation. The DRB is composed of three impartial professional expert members selected by the City and Contractor. Pursuant to the 2018 Caltrans Standard Specification 5-1.43E(i), the City is required to reimburse the Contractor for half of the invoice costs to the DRB and half of the costs of any outside technical services. To date, there have been three DRB disputes related to unknown conditions or unclear plans/specifications claimed by the contractor including:
1. Unknown conditions related to drilling of Cast-in-place Holes (CIDH) piles.
2. Foundation rebar bid item and payment (not CIDH).
3. Time Related Overhead (TRO) for delays associated with unknown conditions.
Item 2 referenced above has been resolved in favor of the City, while items 1 and 3 are still pending a determination. CCO No.9 would ensure that adequate funding is available in the Project budget to meet this administrative requirement. The approval of CCO No. 9 would increase the total not-to-exceed value of the contract to $25,991,416.10.
To provide a full picture of the Project costs to date, a summary of CCO Nos. 1-9 is outlined in Table 1 on the following page. Continued progress in completion of the required Project work requires ratification of the CCO No. 1-8 and approval of COO No. 9.
City of Menifee Staff Report
CIP 13-03 Contract Change Orders
April 17, 2024
2 1
4 1
Table 1 - Contract Activity Summary
Contract
Activity
Approval Date Summary of Changes Amount
Original
Contract
October 19,
2022
Construction services $25,848,403.85
CCO No. 1 April 17, 2023 12” C900 DR 14 Fusible
Pipe
$20,537.39
CCO No. 2 May 15, 2023 Extra Work for
miscellaneous items
$49,000.00
CCO No. 3 May 31, 2023 Irrigation Modifications
Plan IP-5
($9,000.00)
CCO No. 4 July 27, 2023 Adjustment of Girder
Flare Thickness
$0.00
CCO No. 5 September 5,
2023
Misc. Extra Work T&M $16,824.94
CCO No. 6 September 21,
2023
Misc. Extra Work T&M
(EMWD)
$3,412.35
CCO No. 7 December 13,
2023
DB Electric Extra Work
for Frontier
$17,892.61
CCO No. 8 January 26,
2024
Modify bridge utility
opening and provide
additional rebar; perform
exothermic welding at
the bridge
$9,344.96
CCO No. 9 PENDING Caltrans required DRB
budget
$35,000.00
TOTAL $25,991,416.10
STRATEGIC PLAN OBJECTIVE
Connectivity and Mobility
FISCAL IMPACT
The total of all the CCO’s (1-9) is $143,012.25 or 0.55% of the total contract amount, well below the 10% threshold established in Menifee Municipal Code. The fiscal impact of the proposed CCO No. 9 is $35,000. The funding required to support the proposed change order is available in the adopted Project budget, as summarized in Table 2 below.
Table 2 - Existing Project Funding
Fund Project Account No. Available Budget
Menifee Valley
RBBD
Holland Road/I-215 Overcrossing 415-4555-58021 $415,496.40 No additional budget appropriation action(s) is required.
City of Menifee Staff Report
CIP 13-03 Contract Change Orders
April 17, 2024
2 1
4 1
ATTACHMENTS
1. Project Location Map
2. CCO No. 9
3. CCO No. 1
4. CCO No. 2
5. CCO No. 3
6. CCO No. 4
7. CCO No. 5
8. CCO No. 6
9. CCO No. 7
10. CCO No. 8