CITY OF MENIFEE
SUBJECT: Agreement and Bond for Encanto/McCall Gas Station by KA Menifee, LLC
MEETING DATE: April 17, 2024
TO: Mayor and City Council
PREPARED BY: Haile Ford, Senior Engineer
REVIEWED BY: Nick Fidler, Public Works Director
APPROVED BY: Armando G. Villa, City Manager
-------------------------------------------------------------------------------------------------------------------------------

RECOMMENDED ACTION

1. Approve and authorize the City Manager to execute a Public Improvement Agreement to guarantee the completion of required street and drainage improvements associated with Assessor Parcels 333-040-002, 333-040-003, and 333-040-004, for the Encanto/McCall Gas Station, located west of Encanto Drive and north of McCall Boulevard.

DISCUSSION
The Encanto/McCall Gas Station (“Project”) is the proposed development of a 2.1-acre parcel into a gas station, convenience store, automated drive-thru car wash, and a drive-thru fast-food restaurant. The Project is located on the west side of Encanto Drive and north of McCall Boulevard.

KA Menifee, LLC (“Developer”), is now requesting the approval of a Public Improvement Agreement (“PIA”) as required by the Project’s conditions of approval. The PIA requires that an improvement bond be posted to guarantee the completion of the required public improvements within 24 months from the City Council approval date of the PIA.

Staff has reviewed the Developer’s request and determined that the PIA meets the requirements of the Project’s conditions. A summary of the bond being posted to guarantee the required improvements is shown in Table1 below.

Table 1- Encanto/McCall Gas Station – Street and Drainage Improvements Improvement Bond No. Faithful Performance Labor & Materials Street and Drainage 4467238 $ 1,466,500 $ 733,250
Total $ 1,466,500 $ 733,250

City of Menifee Staff Report
Encanto/McCall Gas Station - PIA
April 17, 2024

Page 2 of 2 ends

2 1
2 0

STRATEGIC PLAN OBJECTIVE
Safe and Vibrant Community

FISCAL IMPACT
There is no fiscal impact associated with the recommended action.

ATTACHMENTS

1. Project Map

2. Agreement

3. Bond