Contract Change Order Summary

Menifee City Council
November 6, 2024

Document
Contract Change Order Summary
Meeting
November 6, 2024
Body
Menifee City Council
Original file
89 KB
Text extracted from the city's file for reading and search. Open the original on cityofmenifee.primegov.com. That file is the official record.

Contract Change Order Summary – Roadway Engineering and Construction Corporation
Evans Park Design and Construction
(CIP No. 17-01)

Contract Change
Order No. Description
Date
Approved
Additional
Time Amount Percent
001 R&R AC and Sidewalk Repair 12/4/23 5 days $8,820 1.89% Totals 5 days $8,820 1.89%

Original Contract Amount: $466,042.00
Total Change Order Amount: $8,820.00
Revised Contract Amount: $474,862.00