Contract Change Order Summary –
David Ollis Landscape Development, Inc.
Cherry Hills Median Conversion Project
(CIP No. 24-22)
Contract Change
Order No. Description
Date
Approved
Additional
Time Amount Percent
001 Installation of an additional 28
cubic yards of cobble 2/20/2025 0 days $6,384 4.75%
Totals 0 days $6,384 4.75%
Original Contract Amount: $133,983
Total Change Order Amount: $6,384
Revised Contract Amount: $140,367