CITY OF MENIFEE
SUBJECT: Agreement Amendment with KOA Corporation for the McCall Boulevard Widening Project
MEETING DATE: September 17, 2025
TO: Mayor and City Council
PREPARED BY: Diego Guillen, Senior Engineer
REVIEWED BY: Nick Fidler, Public Works Director
APPROVED BY: Armando G. Villa, City Manager
-------------------------------------------------------------------------------------------------------------------------------

RECOMMENDED ACTION

1. Approve and authorize the City Manager to execute Amendment No. 6 to the Professional Services Agreement (PSA) with KOA Corporation for the McCall Boulevard Widening Project, Capital Improvement Program (CIP) Project No. 22-03, increasing the amount by $98,509, for a total not-to-exceed amount of $403,412.38.

DISCUSSION
The McCall Boulevard Widening Project, CIP Project No. 22-03 (Project), is located between Oakhurst Avenue and Junipero Road. The existing roadway consists of two lanes for approximately half a mile before expanding to a four-lane roadway. There is a need for additional vehicle lanes to support current and future traffic volumes due to the increased residential and commercial development in the area. Under the City’s General Plan, this segment of McCall Boulevard is designated as an arterial roadway that would ultimately provide six vehicle lanes.

The Project would widen the existing two-lane road to a four-lane corridor and establish horizontal and vertical alignments to meet the requirements of the California Highway Design Manual and City standards. The Project is currently in the final phase of design.

On June 21, 2023, the City Council approved a Professional Services Agreement (Agreement) with KOA Corporation (Consultant) to prepare civil design, Plans, Specifications, and Estimate (PS&E) services for the McCall Boulevard Widening Project. At the time the design phase began, the Menifee Valley Specific Plan (MVSP), a private development northeast of the Project area, was still in the entitlement process. The MVSP has since been approved, and the developer, Minor Ranch LLC (Brookfield), has been conditioned to complete roadway widening and other improvements within the Project limits. Because the original PS&E did not account for Brookfield’s conditioned improvements, revisions to the plans are now required. The Project design is currently

City of Menifee Staff Report
CIP 22-03 KOA Amendment No. 6
September 17, 2025

Page 2 of 3 ends

2 9
2 5
95% complete, however, the plans must be updated to remove improvements that would later be replaced by Brookfield as part of their development obligations.

Under proposed Amendment No. 6, the Consultant would revise the Project plans to capture these changes. Major modifications would include adjusting roadway alignment, reducing roadway width, and removing a retaining wall included in the City’s original design. These revisions would align the City’s plans with Brookfield’s conditioned improvements and are expected to generate an estimated $1 million in savings during the construction phase of the Project. Updating the PS&E at this stage would avoid redundant work, reduce potential conflicts during construction, and ensure that the final design remains consistent with City standards.

Amendment No. 6 is necessary to authorize additional Consultant services to complete these revisions, finalize the PS&E, and allow the Project to advance to the bidding and construction phases in the most cost-effective and efficient manner. The proposed Amendment No. 6 would increase the Consultant’s compensation by $98,509.00, increasing the total not-to-exceed amount of the Agreement to $403,412.38. The amendment history for the Project is summarized in Table 1 below.

TABLE 1 – KOA CORPORATION’S AGREEMENT HISTORY
Agreement
Activity
Approval
Date
Summary of Changes Value
Original Contract 6/21/2023 PS&E design services. $231,726.22 Amendment 1 7/20/2023 Hydrology report and drainage
engineering
$11,760.00
Amendment 2 12/6/2023 Term extension only, through
12/31/2025
N/A
Amendment 3 6/19/2024 Additional environmental focused
Studies: Burrowing owl survey, Narrow
endemic plants & rare plant survey.

Pre-construction survey (avian,
woodrat middens & jack rabbits),
streambed delineation, regulatory
permit.
$50,557.16
Amendment 4 10/2/2024 Ongoing design support for additional meetings, geotechnical evaluation, and
recommendations.
$3,300.00
Amendment 5 7/16/2025 Additional right-of-way engineering services.
$7,560.00
Amendment 6 PENDING Revise design plans & additional
engineering services.
$98,509.00
TOTAL $403,412.38
Pursuant to Resolution No. 24-1569 and Menifee Municipal Code §3.12.150, amendments or change orders in the aggregate amount greater than 10% of the agreement amount, that exceed a time extension of 120 days, or that exceed the City Manager’s signing authority, shall be approved by the City Council.

City of Menifee Staff Report
CIP 22-03 KOA Amendment No. 6
September 17, 2025

Page 3 of 3 ends

2 9
2 5

STRATEGIC PLAN OBJECTIVE
Connectivity and Mobility

FISCAL IMPACT
The fiscal impact of the proposed Amendment No. 6 with the Consultant is $98,509.00, for an Agreement total not-to-exceed amount of $403,412.38. Funding for the proposed Amendment No. 6 is available in the FY 2025/2026 CIP budget within the Measure A Fund (4320-PWD-CIPS- 900-02220-690050), as summarized in Table 2 below.

TABLE 2 – PROJECT BUDGET
Fund Project String No. Available Budget Anticipated Cost Measure A CIP22-03.2220.DES.CAE $1,005,801.31 $98,509.00 TOTAL $1,005,801.31 $98,509.00

ATTACHMENTS

1. Project Location Map

2. Amendment No. 6

3. Original Agreement