Contract Amendment & Change Order Third Quarter Report

Menifee City Council
May 20, 2026

Document
Contract Amendment & Change Order Third Quarter Report
Meeting
May 20, 2026
Body
Menifee City Council
Original file
48 KB
Text extracted from the city's file for reading and search. Open the original on cityofmenifee.primegov.com. That file is the official record.

Vendor Name Contract # PO # Department Contract Name Execution Date
Amendment
Type
Amend/
Change
Order
Number
Contract
Amount Before
Amendment /
Change Order
Amendment /
Change Order Revised Amount Term of
Agreement Revised Term Description of Change
Riverside, Riverside University
Health System- Behavioral Health
(RUHS-BH)
2024-0140 Pending Police Department
Memorandum of Understanding (MOU) with
County of Riverside, Riverside University
Health System Behavioral Health (RUHS-BH)
for Homeless Outreach Services
1/1/2026 Professional
Services 1 900,000.00 - 900,000.00 July 1, 2023 - June 30, 2028 No Change
Update the Low-to-Moderate Income (LMI)
thresholds established in the original MOU from
2023
Kimley Horn and Associates, Inc 2022-0208 24100317 Public Works & Engineering
CIP 22-24 Civic Center Parking Lot
Improvement Project for (“PS&E”) Services 1/5/2026 Professional Services 4 395,543.22 - 395,543.22 March 16, 2022 -
December 31,
2025
March 16, 2022
- April 30, 2026
Facilitate the completion of the final phases of
the project
Encode Plus 2019-0041 26100378 Information
Technology Title 9 Web Page ADA Update 1/9/2026
Software
Subscription
Services
2 151,000.00 3,750.00 154,750.00
September 1,
2018 - August 12,
2026
No Change
Execute comprehensive Web Accessibility
Compliance Services for the City's official
website
EPD Solutions, Inc 20250206 25100655 Community
Services
CIP 24-16 Quail Valley Park for Environmental
Documentation & Technical Services 1/14/2026 Professional Services 1 125,035.00 - 125,035.00 March 5, 2025 - June 30, 2028 No Change
Authorizes several modifications to the existing
scope of work to ensure comprehensive
biological & regulatory compliance
EPD Solutions, Inc 2023-0150 24100057 Community
Development
Ares Murrieta Road Warehouse Project
(CQA22-0022) 1/14/2026 Professional
Services 5 378,568.00 15,500.00 394,068.00 November 11,
2022 - June 30,
2026
No Change
Perform a peer review of memos & revise Final
EIR to include interim traffic scenario & related
noise analysis
Keystone Industrial Medicine
(Proactive Work Health Services) 20260019 26100358 Human Resources On Call Medical Consultant Services 1/15/2026 Professional Services 1 18,000.00 - 18,000.00 July 1, 2025 - June 30, 2026 No Change
Officially documenting the name change of the
consultant, effective September 1, 2025, from
Keystone Industrial Medicine to Proactive Work
Health Services
Tate Snyder Kimsey, Inc DBA TSK 2024-0184 24100100 Community Services
CIP 23-10 Community Center at La Piedra &
Menifee Road Project for
Architectural Design & Engineering Services.
2/17/2026 Professional
Services 1 1,100,000.00 51,000.00 1,151,000.00 January 17, 2024 - June 30, 2026 No Change To cover the costs of reimbursable services provided by the consultant
Ames Construction, Inc. 20250260 25100856
Public Works &
Engineering CIP 13-04 Bradley Bridge Over Salt Creek 2/19/2026 Contract Services 4 16,447,656.79 46,518.68 16,494,175.47 August 4, 2025 - August 19, 2026 No Change Additional work required to address Spectrum infrastructure conflict
Ames Construction, Inc. 20250260 25100856 Public Works & Engineering CIP 13-04 Bradley Bridge Over Salt Creek 2/19/2026 Contract Services 5 16,494,175.47 17,757.03 16,511,932.50 August 4, 2025 - August 19, 2026 No Change Utility potholing and manhole adjustments TKE Engineering, Inc 20250249 25100780 Community
Services
CIP 22-27 Audie Murphy Park Ranger Station
Project for Professional Engineering Design
Services
3/2/2026 Professional
Services 1 10,500.00 4,232.50 14,732.50 April 21, 2025 -
December 31,
2025
April 21, 2025 -
April 30, 2026
Extra design services specifically due to the
revised placements of the Ranger Station and
Ticket Booth
DaySmart Recreation 20260036 26100112 Information
Technology
Community Services Recreation Registration
Software 3/2/2026
Software
Subscription
Services
1 4,083.00 2,800.00 6,883.00 July 1, 2025 - December 1, 2025
July 1, 2025 -
April 30, 2026
Extension due to the transition to Rec
Technology not being completed by the
stipulated deadline of December 31, 2025
UpCodes 20260111 26100296 Information
Technology UpCodes Enterprise Subscription 3/9/2026
Software
Subscription
Services
1 3,744.00 1,682.24 5,426.24 August 14, 2025 - August 14, 2026 No Change Adding 8 additional licenses for UpCodes T.Y Lin International 2024-0172 25100924 Public Works & Engineering CIP 19-15 Central Park Amphitheater Project. 3/17/2026 Professional Services 2 199,286.00 - 199,286.00 December 6, 2023
- February 28,
2026
December 6,
2023 - June 28,
2026
Allowing additional time for the work to be
conducted
Tyler Technologies 2023-0197 24100113 Information
Technology
ERP Software Implementation and
Subscription Services 3/30/2026
Software
Subscription
Services
4 3,805,932.00 (46,292.00) 3,759,640.00 February 15, 2023 - February 15, 2032 No Change
Reducing contract by $46,292.00 due to the
removal of "Advanced Scheduling with Mobile
Access" module
Dokken Engineering 2022-0173 24100316 Public Works &
Engineering CIP 22-02 Valley Blvd. Widening Project 3/30/2026 Professional Services 6 1,451,364.81 - 1,451,364.81 January 19, 2022 - March 5, 2026
January 19,
2022 - July 3,
2026
Allowing additional time for the work to be
conducted
Adame Landscape, Inc 20250040
26100130;
26100134;
26100148
Community
Services
Landscape Maintenance Services for (Public
Right-of-Way ROW), Parks, & Facilities 3/30/2026 Contract Services 4 6,653,290.85 29,738.38 6,683,029.23 July 1, 2024 - June 30, 2029 No Change Incorporates changes to existing areas or new additions
Contract Amendments and Change Orders Quarterly Report - FY2025/26 Q3