1 RESOLUTION NO. 26-____

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MENIFEE, CALIFORNIA, ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2026/2027 FUNDED BY SENTATE BILL 1: THE ROAD REAPIR AND ACCOUNTABILITY ACT OF 2017 WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 to address the significant multi-modal transportation funding shortfalls statewide; and WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of the City of Menifee (the “City”) are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and WHEREAS, the City must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and WHEREAS, the City, will receive an estimated $3,235,597 in RMRA funding in Fiscal Year (FY) 2026/2027 from SB 1; and
WHEREAS, this is the tenth year in which the City is receiving SB 1 funding and will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City has undergone a public process through one public Capital Improvement Program workshop where pavement management projects were discussed to ensure public input into our community’s project list; and
WHEREAS, the City used a Pavement Management System to develop the SB 1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the communities priorities for transportation investment; and WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate arterial and residential road segments and support the FY 2026/2027 Citywide Pavement Management Program by resurfacing existing deteriorated roads throughout the City; and WHEREAS, the 2023 California Statewide Local Streets and Roads Needs Assessment found that the City’s streets and roads are in an “good” condition, and this revenue would assist in maintaining the overall quality of the City’s road system over the next decade; and WHEREAS, the SB 1 project list and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting-edge technology, materials and practices, will have significant positive co-benefits statewide.

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Menifee, California does hereby find, determine, and order as follows:
2026/2027 SB1 Projects
2 5
2 4
4 7
Section 1.The foregoing recitals are true and correct.

Section 2.The following list of newly proposed projects will be funded in-part or solely with FY 2026/2027 RMRA revenues:
(A). FY 2026/2027 Local Road AC Resurfacing Program– This project proposes to perform a header grind and resurface existing residential streets using the Asphalt Rubber Aggregate Membrane (ARAM) method, capped with a thin layer of asphalt hot mix.

Additionally, the project proposes to upgrade existing curb ramps to current standards and re-stripe the roadway. The FY2026/2027 project work location is planned for Bradley Road from Potomac Drive to Cherry Hills Boulevard. Construction is estimated to begin in February 2027 and be completed by June 2027. This project would have a useful life of 15 years for rehabilitated roads and 20 years for reconstructed roadways. (B). FY 2026/2027 Slurry Seal Resurfacing Program – This project proposes to resurface existing roadways in good condition via cape seal application to prolong their useful life. The project work will be performed within two residential communities; the first is located north of Holland Road and east of Bradley Road and the second residential community is located south of Holland Road between Menifee Road and Bell Mountain Road. Construction is estimated to begin in April 2027 and be completed by June 2027.

This project would have a useful life of five to seven years.

PASSED, APPROVED AND ADOPTED by the City Council of the City, State of California this 3rd day of June 2026.
___________________________
Ricky Estrada, Mayor
Attest:
___________________________
Stephanie Roseen, City Clerk
Approved as to form:
___________________________
Jeffrey T. Melching, City Attorney

← All documents from this meeting