CITY OF MERCED PROJECT NO. 120060
CHANGE ORDER NO. 2
FINAL CHANGE ORDER
DATE: 01/28/2022
PROJECT NAME: N Street Improvements - 16'h Street to 18th Street PROJECT LOCATION: Merced, California
CONTRACTOR: TBS Contractors.
ADDRESS: 1605 E. Gerard Ave. Merced, CA 95344
REASON FOR CHANGE ORDER: This Change Order has miscellaneous items. See list below:
- Right of way delays,
- Additional demolition at the Thorington Building,
- Fill pit with pea gravel,
- New barricade and signage at 16' Street,
- Removal of existing crosswalk along 16h Street,
- Additional roadway demolition work,
- New GFI electrical pedestal outlets within medians,
- Various electrical work,
- Addition of Line Item 13 "Remove concrete driveway approach" at $3.01/ SF, - Addition of Line Item 12 "Remove concrete sidewalk" at $1.54/ SF, - Addition of Line Item 11 "Remove concrete curb and gutter" at $ 9.84/ LF, - Addition of Line Item 10 "Remove asphalt pavement and base" at $1.23/ SF, - Addition of Line Item 19 "Concrete sidewalk and access ramp" at $11.62/ SF, - Addition of Line Item 20 "Curb and gutter" at $54.12/ LF, - Addition of Line Item 21 "Stamped and colored sidewalk" at $24.94/ SF, - Addition of Line Item 26 "Asphalt concrete patch (3" AC/ 11" AB)" at $6.15/ SF, and, - Credit for Line Item 25 "Asphalt Concrete Overlay (3"')" at $2.52/ SF THE NUMBER OF WORKING DAYS WILL BE ADJUSTED AS FOLLOWS: 0 SKETCH /BACKUP ATTACHED: Yes
DESCRIPTION OF CHANGE:
No. Description Unit Cost
Qty. Total
1. Right of way delays LS
$50,489.94 $50,489.94
2. Additional demolition at the Thorington Building 1 LS $14,913.46 $14,913.46
3. Fill pit with pea gravel 1
LS $926.00 $926.00
4. New barricade and signage at 16' Street 1 LS
$1,961.43 $1,961.43
5. Removal of existing crosswalk along 16th Street
1 LS $1,650.00 $1,650.00
6. Additional roadway demolition work 1 LS
$59,739.58 $59,739.58
7. New GFI electrical pedestal outlets within medians 1 LS $8,437.33 $8,437.33
8. Various electrical work
LS $7,435.81 $7,435.81
9 Addition of Line Item 13 "Remove concrete driveway approach" 182.51 SF $3.01 $549.36
10. Addition of Line Item 12 "Remove concrete sidewalk" 242.77 SF $1.54 $373.87
11. Addition of Line Item 11 "Remove concrete curb and gutter" 6.75 LF $9.84 $66.42
12. Addition of Line Item 10 "Remove asphalt pavement and base" 28 SF $1.23 $34.44
13. Addition of Line Item 19 "Concrete sidewalk and access ramp" 1,187.77 SF $11.62 $13,801.89
14. Addition of Line Item 20 "Curb and gutter" 182.51 LF $24.94 $4,551.80
15. Addition of Line Item 21 "Stamped and colored sidewalk" 74.75 SF $54.12 S4,045.47
16. Addition of Line Item 26 "Asphalt concrete patch (3" AC/ 11" AB)" SF $6.15 $172.20
17. Credit for Line Item 25 "Asphalt Concrete Overlay (3)" 5,432 $2.52 (S13,688.64) Total added cost for Change Order 2: $ 155,460.36
ORIGINAL CONTRACT AMOUNT: $ 962,459.37
CHANGE ORDER #1 AMOUNT: 95,500.91 FUNDS/ACCOUNTS VERIFIED:
CHANGE ORDER #2 AMOUNT: $ 155,460.36 075-1145-637.65-00 TOTAL PROJECT COST TO DATE: $ 1,213,420.64 078-1145-637.65-00 Total: $ 155.460.36
FINANCE OFFICE DATE
ACCEPTED _DATE_ 2,8/22
(CONTRACTOR)
RECOMMENDED DATE
(CITY ENGINEER)
RECOMMENDED DATE
(PROJECT CHAMPION)
APPROVED _DATE
(CITY ATTORNEY)
AUTHORIZED _DATE
(CITY MANAGER)
ATTESTED DATE
(ASSISTANT/DEPUTY CITY CLERK) (SEAL)