CITY OF MERCED PROJECT NO. 117038 CHANGE ORDER NO. 4
DATE: 3/07/2022
PROJECT NAME: V Street Improvements - 16" Street to 18% Street PROJECT LOCATION: Merced, California
CONTRACTOR: Agee Construction Corporation.
ADDRESS: 1039 Hoblitt Ave. Clovis, CA 93612
REASON FOR CHANGE ORDER: Additional asphalt concrete cutbacks and revised wrought iron fence quantities.
THE NUMBER OF WORKING DAYS WILL BE ADJUSTED AS FOLLOWS: 0 SKETCH / BACKUP ATTACHED: Yes
DESCRIPTION OF CHANGE:
No. Description Unit Unit Price Qty. Total
Additional to Line Item 14 "Remove Asphalt Pavement SF $11.00 422 $4,642.00 and Base (3"/I")"
Credit for Line Item 16 "Remove and Relocate Wrought $215.00 5 ($1,075.00) Addition to Line Item 18 "AC Pavement Patch Arcas SF 7.50 403 $3.022.50 Total added cost for change order 4: $6,589.50
ORIGINAL CONTRACT AMOUNT: 558,883.00
CHANGE ORDER #1 AMOUNT: $ 32,501.33 FUNDS/ACCOUNTS VERIFIED:
CHANGE ORDER #2 AMOUNT: $ 18,215.85 078-1145-637.65-00
CHANGE ORDER #3 AMOUNT: $ 4.396.35
CHANGE ORDER #4 AMOUNT: $ 6,589.50
TOTAL PROJECT COST TO DATE: $ 620.586.03
Total: $ 6,589.50
FINANCE OFFICE DATE
ACCEPTED DATE 3/9/2022
ONTRACTOR)
RECOMMENDED DATE
(CITY ENGINEER)
RECOMMENDED DATE
(PROJECT CHAMPION)
APPROVED DATE
(CITY ATTORNEY)
AUTHORIZED DATE
(CITY MANAGER)
ATTESTED DATE
(ASSISTANT/DEPUTY CITY CLERK) (SEAL)