CITY OF MERCED PROJECT NO. 117039
CHANGE ORDER NO. 1
DATE: April 13, 2022
PROJECT NAME: G Street Improvements Childs Avenue to 134 Street and Alley Ways 11 to 13t Streets PROJECT LOCATION: Merced, California
CONTRACTOR: Rolfe Construction, Inc.
ADDRESS: 3573 Southern Pacific Ave., Atwater, CA 95301
REASON FOR CHANGE ORDER: We are deleting Bid Item No. 47 Astroturf Landscaping and replacing it with Decomposed Granite (DG). We are also adding two SB-1 Signs that were not part of the bid package.
THE NUMBER OF WORKING DAYS WILL BE ADJUSTED AS FOLLOWS: None SKETCH / BACKUP ATTACHED: Yes
DESCRIPTION OF CHANGE:
1. Delete Bid Item 47 Astroturf Landscaping for a deletion to the project of (S235,950.00)
2. Add Decomposed Granite in place of Astroturf for an added cost to the project of $135,850.00
3. Add two (2) SB-1 Signs for an added cost to the project of Total deducted cost for change order 1: ($98,500.00)
ORIGINAL CONTRACT AMOUNT: $2,531,371.00 301837 PO# 144069 CHANGE ORDER #1 AMOUNT: -($ 98,500.00) FUNDS/ACCOUNTS VERIFIED:
TOTAL PROJECT COST TO DATE: S2,432,871.00
450-1104-637.65-00-117039 (100%) = (S98,500.00)
Total Change Order No. 1 = ($98,500.00)
Very D 5/2/22
FINANCE OFFICE
No funds to encumber leaved but $98,50020
ACCEPTED _DATE 4/31 ж 4/28/22
FL 4/29/22
RECOMMENDED DATE. 04/14/222
(CITY ENGINEER)
RECOMMENDED DATE 4-14-22
(PROTECT CHAMPION)
APPROVED Kimbal Cmady DATE 4/21/22
(CITY ATTORNEY)
AUTHORIZED up hance Mutz 5/2/22
DATE
ATTESTED
(ASSISTANT DEPUTY CITY CLERK) DATE
SEAL
88)
CORPORATED ARALY
Original Line Item Unit Cost
Astroturf Landscaping SF 31460 $ 7.50 $ 235,950.00
Minus Turf $115K & AB $15K ($130,000)
$ 105,950.00
Cost of DG $14K and Trucking $12K 26,000.00
Material Markup 15% 3,900.00
Total $ 135,850.00
Cost per SF @ 31460sf 4.32
R Date: 3/18/2022
ROLFE
CONSTRUCTION
Rolfe Construction Inc. To Vanessa Mendoza
3573 Southern Pacific Ave. Assistant Engineer
Atwater, Ca. 95301 City of Merced
P: 209.358.5548 678 W. 18th Street
CHANGE
F: 209.357.2916 Merced, CA 95340
[email protected] ORDER [email protected]
PROPOSAL
Job#: Payment
Job Terms Due Date
2137 G St Improvements-Project Signs UPON COMPLETION UPON COMPLETION Quantity Description Unit Price Line Total
2 EA 4'x 5' Project Signs-Per City Detail to be provided $800.00 $1,600.00 To Be: 4'x 5' with the anti-graffiti coating on
aluminum backing
Total $1,600.00
Thank you for your business!